LEVEE RE-FURBISHMENT AND WATER CONTROL STRUCTURE REPLACEMENT WORK NEAR THE MERMENTAU RIVER IN CAMERON PARISH

NAME OF APPLICANT: Cameron Parish Gravity Drainage District #5, c/o Lonnie G. Harper & Associates, Inc., Attn: Mr. Mitch Thomas, 2746 Highway 384, Bell City, LA 70630.

LOCATION OF WORK: In Cameron Parish, Louisiana; located at 29.790792 North, -92.882708 approximately two miles upstream of the Mermentau River bridge near Grand Chenier, Louisiana, as shown on the attached vicinity map.

CHARACTER OF WORK: Restore 133,085 linear feet of five existing levee segments and 29 water control structures for water level management and tidal surge control. Approximately 780,520 cubic yards of adjacent water bottom material will be dredged to restore the levees. Approximately 730 cubic yards of rock will be used as rip-rap and placed around the inlets and outlets of the water control structures for erosion protection. The levee will have a top width varying from 6 to 12 feet and a bottom width varying from 20 to 40 feet with a 1 on 2 side slope. Project implementation will impact approximately 134 acres of non-vegetated water bottoms and 104 acres of existing degraded levees.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas