The Navy proposes to impact 2.04 acres of forested wetlands for the Special Operations Forces Demolition Training Complex upgrade at Dam Neck Annex in Virginia Beach, Virginia. Of that total, 0.37 acres of forested wetlands would be cleared and filled and 1.67 acres permanently converted from forested wetlands to emergent wetlands.
Oct. 18, 2019
CENAO-WR-R
NAO-1990-02033/19-V1698
FEDERAL PUBLIC NOTICE
The district commander has received a joint application for federal and state permits as described below:
APPLICANT
Naval Air Station Oceana
Capt. Chad P. Vincelette, Commanding Officer, NAS Oceana
1750 Tomcat Blvd.
Virginia Beach, VA 23460-2191
WATERWAY AND LOCATION OF PROPOSED WORK: The project is located in wetlands that drain into Lake Redwing, a tributary to Ashville Bridge Creek, at Dam Neck Annex, Naval Air Station Oceana in Virginia Beach, Virginia.
PROPOSED WORK AND PURPOSE: The applicant proposes to impact 2.04 acres of forested wetlands for the Special Operations Forces Demolition Training Complex upgrade at Dam Neck Annex in Virginia Beach. Of that total, 0.37 acres of forested wetlands would be cleared and filled and 1.67 acrespermanently converted from forested wetlands to emergent wetlands. The purpose of the proposed project is to construct additional breaching and containment walls, a grenade trainer and range support building to ensure that Naval Special Warfarepersonnel have the full capability to conduct grenade training andability to meet their research, development, test and evaluation requirements. The applicant has indicated off-site alternatives would not meet their purpose and need. The applicant considered other on-site configurations, but they were rejected, since the other layouts would have additional wetland impacts. The applicant has proposed to mitigate for the impacts through the purchase of 2.41 credits (2:1 for fill impacts to forested wetlands and 1:1 for conversion impacts of forested wetlands) at an approved mitigation bank in the service area.
In addition to the required Department of the Army permit, the applicant must obtain a Virginia Water Protection Permit from the Virginia Department of Environmental Quality,assuringapplicable laws and regulations pertaining to water quality are not violated. Project drawings are attached.
AUTHORITY: Permits are required pursuant to Sections 401 and 404 of the Clean Water Act (Public Law 95-217) and Title 62.1 of the Code of Virginia.
FEDERAL EVALUATION OF APPLICATION: The decision whether to issue a permit will be based on a probable-impactevaluation, including cumulative impacts of the proposed activity on the public interest. Itwill reflect the national concern for both protection and utilization of important resources. The benefits that reasonably may be expected from the proposal must be balanced againsttheir reasonably foreseeable detriments. All of the proposal's relevant factors will be considered, including conservation, economics, aesthetics, general environmental concerns, wetlands; cultural, fish,wildlife and flood-plain values; flood hazards,land use, navigation, shoreline erosion and accretion, recreation; water supply,conservation andquality; energy and mineral needs, safety, food and fiber production,property ownership and, in general, the people's needs and welfare. The Environmental Protection Agency's "Guidelines for Specification of Disposal Sites for Dredged or Fill Material" will also be applied (Section 404(b)(1) of the Clean Water Act).
The Corps of Engineers is soliciting comments from the public; federal, state, and local agencies and officials; Indian tribes and other interested parties in order to consider and evaluate the proposed activity's direct, indirect and cumulative impacts. Any comments received will be considered by the Corpsto determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, the environment and other public-interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or Environmental Impact Statement pursuant to the National Environmental Policy Act. Theyare also used to determine the need for a public hearing andoverall public interest inthe proposed activity. Anyone may request a public hearing to consider this permit application by writing to the district commander within 30 days ofthis notice date, stating specific reasons for holding it.The district commander will then decide if a hearing should take place.
Preliminary review indicates: (1) no Environmental Impact Statement will be required; (2) the Navy has initiated coordination under the Endangered Species Act of 1973 (16 U.S.C. 1531-1544, 87 Stat. 884, as amended); and (3) no known properties eligible for inclusion or included in the National Register of Historic Places are in or near the permit area, or would likely be affected by the proposal. The Navy has completed itsreview and determinedthe project will have no effect on historic properties.
For compliance with the Coastal Zone Management Act of 1972, as amended for Tidewater projects, the applicant must certify that federally licensed or permitted activities affecting Virginia's coastal uses or resources will be conducted in a manner consistent with the Virginia Coastal Zone Management Programand obtain concurrence from the Department of Environmental Quality, Office of Environmental Impact Review. The Corps hasnot received applicant certificationprior to this public notice's publication. It is the applicant’s responsibility to submit a consistency certification to the Office of Environmental Impact Review for concurrence or objection, and proofmust be submitted to the Corps beforefinal permit issuance. Afederal consistency certification template can be found at www.deq.virginia.gov/Programs/EnvironmentalImpactReview/FederalConsistencyReviews.aspx#cert. For more information or to obtain a list of the Virginia Coastal Zone Management Program's enforceable policies, contact the Department of Environmental Quality's Office of Environmental Impact Review at 804-698-4330 or email bettina.sullivan@deq.virginia.gov or john.fisher@deq.virginia.gov.
COMMENT PERIOD: Comments on this project should be in writing. Theycan be sent byemail to melissa.a.nash@usace.army.mil or regular mail, addressed to:Norfolk District, Corps of Engineers (ATTN: CENAO-WR-R), 803 Front St., Norfolk, VA 23510-1011. All comments should be received byclose of business Nov.18.
PRIVACY & CONFIDENTIALITY: Comments and information, including submitter identity, providedin response to this public notice may be disclosed, reproduced and distributed atU.S. Army Corps of Engineers discretion. Informationsubmitted in connection with the public notice cannot be maintained as confidential by USACE. Submissions should not include any informationthe submitter seeks to preserve as confidential.
If you have questions about this project or the permit process, contact Melissa Nash at melissa.a.nash@usace.army.mil or 757-201-7489.