You can copy from here when filling out the rest of the page.
NEW 12” DIAMETER HYDROGEN PIPELINE IN ST. CHARLES, JEFFERSON, AND PLAQUEMINES PARISHES.
NAME OF APPLICANT: Phillips 66, c/o Morris P. Hebert, Inc., Attention: Timothy Robertson, 8724 Jefferson Highway, Baton Rouge, Louisiana 70809.
LOCATION OF WORK: Project site is located in St. Charles, Jefferson, and Plaquemines Parishes, in Louisiana, as shown on the attached drawings.
POB: Latitude: 29.921364 Longitude: -90.348911
POE: Latitude: 29.684492 Longitude: -89.9802
Hydrologic Unit Codes: 08090301, East Central Louisiana Coastal
CHARACTER OF WORK: Clear, grade, excavate and fill for a new 12” diameter hydrogen pipeline from an existing Luling facility to the Alliance Refinery, to include the installation of four (4) valve and meter sites and intermediate platform valve site. The pipeline will be installed via open cut and horizontal directional drills, and bores under roadways, waterways and levees. The project as proposed would directly impact 60.8 acres (permanently) and 108.3 acres (temporarily) of jurisdictional wetlands and 208.8 acres of other waters. The applicant proposed to contract with an approved mitigation bank in order to offset the adverse impact to jurisdictional wetlands.