You can copy from here when filling out the rest of the page.
DRILL THE HOMER PROSPECT WELL IN TERREBONNE PARISH
NAME OF APPLICANT: Hilcorp Energy Company, c/o Providence Engineering and Environmental, 1201 Main Street, Baton Rouge, Louisiana 70802.
LOCATION OF WORK: In Terrebonne Parish, located approximately 4.5 miles southwest of Chauvin, Louisiana, 29.472083, -90.646714, as shown on the attached drawings. Hydrologic Unit 08090302.
CHARACTER OF WORK: The applicant proposes to use a drill barge to drill the Homer Prospect Well. Approximately 78,563 cubic yards of propwashing is required to achieve an access route depth of 7.5 feet to reach the prospect. If the prospect is successful, approximately 15,980 linear feet of four-inch diameter flowline will be installed from the Homer Prospect to the Houma South Test Platform to the Houma South Production Barge. A flowline will be installed on top of marsh via airboat and in open water via jetting to a minimum of four feet below the mudline. Bankline stabilization will also be installed to prevent erosion in the oil and gas exploration and production area. Permanent impacts to jurisdictional wetlands are not expected. All temporary impacted areas would be returned to pre-project conditions upon completion of the proposal.