Beginning 24 Feb 2020 and ending 10 Apr 2020, maintenance workers will be cutting slots for stoplogs

Beginning 24 Feb 2020 and ending 10 Apr 2020, maintenance workers will be cutting slots for stoplogs at Old Hickory Lock at Cumberland River Mile 216.1that will require complete closure of the lock. The scheduled closures are as follows:

• 24 Feb – 20 Mar:

o Complete closure of the lock to all traffic beginning at 0730 on 24 Feb.

• 20 Mar – 25 Mar:

o Temporary opening of the lock to all traffic for a 5 day period beginning at 0600 on 20 Mar and ending at 0600 on 25 Mar.

• 25 Mar – 10 Apr:

o Complete closure of the lock to all traffic beginning at 0600 on 25 Mar and ending at 1630 on 10 Apr.

The lock is expected to return to operation after completion of the project at 1630 on 10 Apr 2020.

For more information contact: Harold "Skeeter" Deskins at Harold.A.Deskins@usace.army.mil or (615) 240-4037.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas