This notice announces a prospectus has been submitted for the development of the Swanson Wetland Mitigation Bank pursuant to 33 CFR 332, Compensatory Mitigation for Losses of Aquatic Resources (Federal Register: April 10, 2008, effective June 9, 2008).
Public Notice No. 20-36
Application No. LRN-2020-00267
Date: May 18, 2020; Expires: June 17, 2020
Please address comments to:
Nashville District Corpsof Engineers,
Regulatory Division
3701 Bell Road,
Nashville, TN 37214-2660
SUBJECT: This notice announces a prospectus has been submitted for the development of the Swanson Wetland Mitigation Bank pursuant to 33 CFR 332, Compensatory Mitigation for Losses of Aquatic Resources (Federal Register: April 10, 2008, effective June 9, 2008).
BANK SPONSOR: Grow Environmental Solutions LLC
1406 Wilson Avenue
Tullahoma, TN 37388
LOCATION: The proposed Swanson Wetland Mitigation Bank is located in Rutherford County, Tennessee (Latitude/Longitude: 35.798222, -86.331983), approximately 2,000 ft. southwest of the intersection of Highway 99 and Dilton Mankin Road.
PURPOSE: The proposed project would provide compensatory mitigation for permitted wetland impacts within the proposed geographic service area of the Stones River (05130203) watershed.
GENERAL INFORMATION: Mitigation banks are defined as a site, or suite of sites, where aquatic resources (e.g., wetlands, streams, riparian areas) are restored, established, enhanced, and/or reserved for the purpose of providing compensatory mitigation for impacts authorized by Department of the Army (DA) permits pursuant to Section 10 of the Rivers and Harbors Act of 1899 and/or Section 404 of the Clean Water Act. In general, units of restored, established, enhanced or preserved wetlands or streams are expressed as “credits” which may subsequently be withdrawn to offset “debits” incurred at a permitted project site. In this way, a permit requirement to provide compensatory mitigation can be transferred to the mitigation bank sponsor. The operation and use of a mitigation bank are governed by an approved mitigation banking instrument (MBI). The MBI is the legal document for the establishment, operation and use of a mitigation bank. This bank is intended to be a private commercial bank. The sponsor would be responsible for the successful development of the mitigation bank including monitoring and reporting requirements.
A group of federal and state regulatory and resource agency representatives known as the Interagency Review Team (IRT) would oversee the execution and management of the project. The IRT is chaired by the US Army Corps of Engineers, Nashville District (USACE). The primary role of the IRT is to facilitate establishment of the mitigation site through the development of a MBI. The IRT will review the prospectus, instrument, and other appropriate
documents and provide comments to the USACE.
Approval of the use of the bank for specific projects is the decision of the USACE pursuant to Section 10 of the Rivers and Harbors Act of 1899 and/or Section 404 of the Clean Water Act and/or the Tennessee Department of Environment and Conservation (TDEC) pursuant to Section 401 of the CWA
and/or applicable state of Tennessee statute(s) and regulation(s).
PROJECT DESCRIPTION: The approximately 70 acre site has been in sod and soybean production for the last eight years and historically was used for agricultural production. Site hydrology has been manipulated over the years by various agricultural practices, including ditching. The applicant
reports that the proposed project area currently contains more than 60 acres of wetlands, making this site a candidate for wetland enhancement and restoration.
For more details on the proposed project, the prospectus can be viewed byclicking here. Information in the prospectus will serve as the basis for establishing the wetland mitigation banking instrument (MBI). The MBI will describe in detail the physical and legal characteristics of the bank and how the bank will be established and operated.
HISTORIC AND CULTURAL RESOURCES: A search of the National Register of Historic Places returned no findings of historic properties within or near the mitigation site. A Phase I cultural/archaeological survey has not been conducted for the site. At this early stage in the regulatory process, no project design plans have been submitted; therefore, USACE cannot complete an effects determination for historic and cultural resources. The Corps invites responses to this public notice from American Indian Tribes or tribal governments; Federal, State, and local agencies; historical and archeological societies; and other parties likely to have knowledge of or concerns regarding historic properties and cultural significance at or near the project area.
Upon submittal of the design plans, USACE would evaluate the design plans along with any substantive comments from this public notice to determine the potential of impacts to historic and cultural resources for Section 106 compliance. If the Corps determines that consultation is required, the Corps would consult with the Tennessee Historic Commission (SHPO) and American Indian Tribes in accordance with Section 106 of the National Historic Preservation Act, as appropriate.
ENDANGERED/THREATENED SPECIES REVIEW: A review of the United States Fish and Wildlife Service (USFWS) website, http://ecos.fws.gov/ipac identified the following federally-listed species that are known to or believed to occur in Rutherford County, Tennessee:
Species Nomenclature
Federal Status
Mammals
Gray bat (Myotis grisescens)
Endangered
Indiana bat (Myotis sodalis)
Endangered
Northern Long-eared bat (Myotis septentrionalis)
Threatened
Freshwater Mussels
Littlewing Pearlymussel (Pegias fabula)
Endangered
Flowering Plants
Braun's Rock-cress (Arabis perstellata)
Endangered
Guthrie's (=pyne's) Ground-plum (Astragalus bibullatus)
Endangered
Leafy Prairie-clover (Dalea foliosa)
Endangered
Acopy of this notice is being furnished to USFWS for their review. After receipt of any comments, the USACE will evaluate the potential effects to proposed and/or listed species and their designated critical habitat, and initiate consultation with the U.S. Fish & Wildlife Service, if required.
COMMENT PERIOD: Written statements received in this office by June 17, 2020 will become a part of the record and will be considered in the determination. Any response to this notice should be directed to the Nashville District Corps of Engineers, Regulatory Division, Attention: Mr. Ryan
Evans at the above address or by email: ryan.evans@usace.army.mil.
\s\
Joshua W. Frost
Chief, Technical Services Branch
Regulatory Division