The overall purpose of this work is for the proposed pipeline installation within multiple WOUS

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

The overall purpose of this work is for the proposed pipeline installation within multiple WOUS, at single and complete project locations, associated with the supply of up to 160,000 barrels per day of crude oil from tankage located in Cushing, Oklahoma to the two refinery facilities located in Tulsa, Oklahoma. The project is not a water dependent activity.

Location: There are 130 single and complete projects for crossings of waters of the United States (WOUS) that would traverses portions of Creek, Payne, and Tulsa Counties.

Project Description:The application is for the placement of dredge or fill material for 130 single and complete projects for crossings of WOUS associated with the construction of approximately 47 miles of 16-inch steel crude oil pipeline. Please note, the scope of each single and complete project impacting WOUS would have been evaluated for verification under Nationwide (NWP) 12 for Utility Line Activities, however, the Corps is enjoined from authorizing any dredge or fill activities associated with construction of new oil & gas pipelines under NWP 12 due to a recent court case (Northern Plains Resource Council v. U.S. Army Corps of Engineers, 2020).

Description of Work: The applicant proposes to place dredge or fill material temporarily into 24 emergent wetlands (each individual crossing is less than 0.10 ac). Additionally, 30 intermittent streams (each crossing location less than 0.10 ac) and 76 ephemeral streams (each individual crossing is between a minimum 11 lf and 476 lf) would be crossed by this proposed utility line. At the wetland crossings, where the pipe would be installed by conventional open cut trench, segregated topsoil and trench spoil (soil other than topsoil from trench excavations that may be temporarily sidecast for no longer than three months) would be temporarily sidecast and stored in the wetland. Once the pipe is lowered into the trench, the trench spoil and topsoil would be replaced in the strata from which it was removed. At all intermittent stream crossings and most ephemeral stream crossings, additional temporary workspace has been added on setbacks of approximately 50 feet from the top of bank for spoil storage. For intermittent stream crossings, no spoil would be temporarily side cast within the limits of the ordinary high water mark. Once the pipe is installed in the trench, the spoil and topsoil would be replaced and the crossing would be restored to pre-construction contours.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas