You can copy from here when filling out the rest of the page.
This is an After-the-Fact permit application.
Full Public Notice Project Plans TCEQ Tier II Questionnaire & Alternatives Analysis
PROJECT DESCRIPTION: This is an After-the-Fact permit application. The applicant installed 3,444’ - 8” of steel sheet pile bulkhead, 65 mooring piles, dredged approximately 21,000 cubic yards of material from approximately 3.56 acres of unvegetated water bottom and placed approximately 5,839 cubic yards of fill behind the bulkhead below mean high tide (approx. 1.09 acre). The dredged material was deposited onsite in uplands and transported offsite for upland disposal.