The following application has been submitted for a Department of the Army (DA) Permit under the provisions of Section 404 of the Clean Water Act.  The applicant has requested a DA authorization to discharge dredged and/or fill material into waters of the United States in conjunction with the proposed McConnelsville Dam Project (See Table 1).  The existing McConnelsville Dam is beyond its serviceable lifespan and requires complete rehabilitation or replacement (See Sheet 3 of 3).

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

The following application has been submitted for a Department of the Army (DA) Permit under the provisions of Section 404 of the Clean Water Act.  The applicant has requested a DA authorization to discharge dredged and/or fill material into waters of the United States in conjunction with the proposed McConnelsville Dam Project (See Table 1).  The existing McConnelsville Dam is beyond its serviceable lifespan and requires complete rehabilitation or replacement (See Sheet 3 of 3).

TO WHOM IT MAY CONCERN: The following application has been submitted for a Department of the Army (DA) Permit under the provisions of Section 404 of the Clean Water Act.

APPLICANT: Mr. Jeremy Wenner

Ohio Department of Natural Resources (ODNR)

Division of Engineering

2045 Morse Road

Columbus, Ohio 43229

LOCATION: As depicted on the attached Sheet 1-2 of 3, the proposed project would be located within the watershed of the Muskingum River (Latitude 39.644005, Longitude -81.850183) at the Muskingum River Locks and Dam No. 7 in McConnelsville, Morgan County, Ohio. The waters on-site include and flow to the Muskingum River, a navigable water of the United States.

DESCRIPTION OF PROPOSED WORK: The applicant has requested a DA authorization to discharge dredged and/or fill material into waters of the United States in conjunction with the proposed McConnelsville Dam Project (See Table 1). The existing McConnelsville Dam is beyond its serviceable lifespan and requires complete rehabilitation or replacement (See Sheet 3 of 3). The applicant has indicated the proposed project is a Design Build Project where the final footprint, type of activity (rehabilitation or replacement), construction sequence, construction methods, and construction access would not be finalized until all site-specific variables and seasonal flow rates/volumes have been considered. Phased construction of dam rehabilitation or replacement activities would allow for the Muskingum River flow to be maintained via channel diversion. Lock No. 7 and its feeder canal would be avoided, and both would remain functional throughout the construction process to continue to provide navigability during the project’s duration.

The rehabilitation of the McConnelsville Dam would include the encapsulation of the existing dam structure and would result in the temporary discharge of dredged and/or fill material into 150 linear feet (0.70 acre) of the Muskingum River and the permanent discharge of dredged and/or fill material into 623 linear feet (5.19 acres) of the Muskingum River and 0.247 acre of three (3) wetlands (See Table 1). The existing cellular dam would be enclosed with concrete within a double sheet piling envelope. The existing fill from the cellular dam cells would be removed and replaced with concrete. The cellular dam fill would be placed as substrate in the Muskingum River. A temporary construction access causeway would be constructed upstream of the existing dam using clean rock to an elevation one (1) foot above the existing dam. The temporary causeway would be phased with the first phase extending approximately 390 feet southerly across the Muskingum River and encapsulating the existing dam as the causeway is progressed. The second phase would include extending the temporary causeway from the southern bank of the Muskingum River. Encapsulating the existing dam would require a 58-foot base width. The north abutment is anticipated to be 64 feet in length and the south abutment is anticipated to be 90 feet in length, each with a footing width of approximately 14 feet. The north abutment would remain raised cellular elements with 30 feet of driven steel sheeting. The south abutment would include a concrete wall with concrete footer.

The replacement of the McConnelsville Dam would include the construction of a new dam within the McConnell’s Island limits of the Muskingum River and would result in the temporary discharge of dredged and/or fill material into 164 linear feet (1.4 acres) of the Muskingum River and 0.026 acre of one (1) wetland and the permanent discharge of dredged and/or fill material into 423 linear feet (5.03 acres) of the Muskingum River and 0.265 acre of four (4) wetlands (See Table 1). The three (3) types of dams being considered include a double steel sheet pile wall with concrete fill, a sloped-face concrete gravity wall, and a roller-compacted concrete wall. The proposed new dam structure would be approximately 595 feet in total length with a 195-foot spillway positioned in the center of the river with wing walls. The anticipated width of the new dam and associated stilling basin varies from 45 to 54 linear feet at its base, depending on design. The proposed elevation for the crest of the new dam spillway would maintain the established reservoir elevation of 650.2 feet above mean sea level. Construction of a replacement dam would include phased construction. The first phase of construction would include the new dam’s northern two-thirds, or approximately 390 feet, and the 195-foot spillway and north abutment. The second phase of construction would include the remaining portion of the new dam, approximately 200 feet, and the south abutment. Depending on the dam’s location, construction may require a temporary causeway and staging areas. If the Muskingum River is deep enough to permit barge construction, barge construction would be utilized and a temporary causeway with associated staging areas would not be required. Once the new dam is constructed, the old structurally deficient dam would be removed. Removal of the existing dam would require two (2) barges to be positioned on the upstream side of the structure. The existing dam structure would be removed down to the riverbed elevation. Cribbing and remnants from the existing dam structure would be left in place.

A temporary bridge spanning the lock canal is planned for bidirectional construction access for both replacement or rehabilitation and would be located west of the existing swing bridge. It is anticipated that the end of the bridge would align with, or be located just west of, South 9th Street. The temporary bridge would span the existing lock canal at an approximate 90-degree angle and would be constructed in a similar manner and clearance of the existing bridge.

After construction, any temporary fill material would be removed in its entirety and the affected areas returned to pre-construction elevations and revegetated, as appropriate. Any suitable rubble (rock channel protection concrete, natural stone/rock) from the dam replacement or rehabilitation would be repurposed for bank stabilization and restoration activities along the Muskingum River north bank following the conclusion of all other construction activities on McConnell’s Island.

ALTERNATIVES ANALYSIS: As a result of the proposal, fill material would be discharged into waters of the United States as described above and in the attached Table 1. The project does not require access or proximity to or siting within special aquatic sites to fulfill its basic purpose and is considered a non-water dependent activity. The Section 404(b)(1) Guidelines state for non-water dependent activities, practicable alternatives that do not involve special aquatic sites are presumed to be available, unless clearly demonstrated otherwise. The applicant is required to provide an alternatives analysis that must overcome this presumption prior to receiving authorization for the discharge of dredged and/or fill material. No permit will be issued until our review of the alternative analysis clearly demonstrates that practicable upland alternatives are not available to achieve the overall project purpose.

AVOIDANCE AND MINIMIZATION: In evaluating a project area containing waters of the United States, consideration must be given to avoiding impacts on these sites. If waters of the United States cannot be avoided, then the impacts must be minimized. A total of 0.64 acre of eight (8) emergent wetlands and 1,890 linear feet of one (1) perennial stream, the Muskingum River, are located within the proposed project area. The applicant has avoided and minimized impacts to waters of the United States to the maximum extent practicable. Stormwater management planning would incorporate best management practices and water pollution controls necessary to maintain compliance with the Federal Water Pollution Control Act and Ohio Water Pollution Control Act. Stormwater management and erosion control systems would be implemented during construction, including silt fences, mulch and/or earthen berms, temporary seeding, hay bales, inlet protection, temporary collection basins, diversion ditches, and construction entrances. All disturbed areas would be seeded and/or revegetated with native plant species and native seed mixes after completion of construction activities. After construction, any temporary fill material would be removed in its entirety and the affected areas returned to pre-construction elevations and revegetated, as appropriate.

COMPENSATORY MITIGATION PLAN (CMP): To compensate for the loss of waters of the United States associated with the proposed project, the applicant proposes to purchase 0.6 acre of non-forested wetland mitigation credit from the Nature Conservancy’s In-Lieu Fee Program. The applicant’s CMP is currently under review. After review of all the submitted information, the Corps will make a determination of the appropriate compensatory mitigation in the event a decision is made to issue a DA authorization.

WATER QUALITY CERTIFICATION: The applicant must obtain a Section 401 Water Quality Certification (WQC) from the Ohio Environmental Protection Agency assuring that applicable laws and regulations pertaining to water quality are not violated. A DA permit, if otherwise warranted, would not be issued on this project until the Section 401 WQC has been issued or waived.

HISTORIC AND CULTURAL RESOURCES: The Corps is mandated by the National Historic Preservation Act (NHPA) to ensure no federal undertaking, including a Corps permit action, which may affect historic resources, is commenced before the impacts of such action are considered and the Advisory Council on Historic Preservation and the State Historic Preservation Office (SHPO) are provided an opportunity to comment as required by the NHPA, 36 CFR 800, and 33 CFR 325, Appendix C. It has been determined that the McConnelsville Dam Project would affect the National Register of Historic Places (NRHP) listed Muskingum River Lock and Dam No. 7 (Ohio Historic Inventory MRG-00-3250), a contributing resource of the Muskingum River Navigation Historic District (NRHP reference # 07000025). We have determined the proposed undertaking would have no adverse effect on the NRHP listed Muskingum River Lock and Dam No. 7 pending the stipulations and issuance of the Programmatic Agreement between the Corps, the Ohio SHPO, and the ODNR regarding the Muskingum River Locks and Dams Assessments and Improvements, Coshocton, Morgan, Muskingum, and Washington Counties, Ohio. A copy of this public notice will be furnished to the Ohio SHPO for their review. Comments concerning archaeological sensitivity of the project area should be based on collected data. No DA permit will be issued until all obligations under Section 106 of the National Historic Preservation Act of 1966 have been fulfilled.

THREATENED AND ENDANGERED SPECIES: The proposed project is located within the known or historic range of the endangered Indiana bat (Myotis sodalis), the threatened northern long-eared bat (Myotis septentrionalis), the endangered fanshell mussel (Cyprogenia stegaria), the endangered pink mucket pearly mussel (Lampsilis abrupta), the endangered sheepnose mussel (Plethobasus cyphyus), the endangered snuffbox mussel (Epioblasma triquetra), and the endangered American burying beetle (Nicrophorus americanus). The proposed project area is comprised of regularly maintained turf (via mowing), the rocky shorelines of the Muskingum River, a low head dam, an abandoned early mill foundation, an abandoned early hydroelectric power plant foundation, 0.64 acre of eight (8) emergent wetlands, and 1,890 linear feet of one (1) perennial stream, the Muskingum River. The proposed project area could provide potential habitat for the Indiana bat and the northern long-eared bat. The applicant has agreed to conduct tree clearing operations associated with the proposed project prior to April 1 and after September 30, as recommended by the United States Fish and Wildlife Service (USFWS), to minimize effects on the Indiana bat and the northern long-eared bat. The Corps has determined the proposed project may affect, but is not likely adversely affect the Indiana bat or the northern long-eared bat. Lawhon and Associates, Inc., on behalf of the applicant, completed a mussel survey and relocation in August and September 2020 in the vicinity of the proposed project. No live or fresh dead federally listed species were observed during the mussel survey. Live mussel species were relocated downstream of the dam. Additionally, mussel species located in the project vicinity would be relocated prior to the commencement of construction. The Corps has determined the project may affect, but is not likely adversely affect the fanshell mussel, the pink mucket pearly mussel, the sheepnose mussel, and the snuffbox mussel. The Corps has consulted the most recently available information and information provided by the applicant and has determined the proposed project area does not provide suitable habitat for the American burying beetle. The Corps has determined the proposed project would have no effect on the American burying beetle. This Public Notice serves as a request for concurrence from the USFWS for the aforementioned effect determination and for any additional information they may have on whether any listed or proposed to be listed endangered or threatened species may be present in the area which would be affected by the activity, pursuant to Section 7(c) of the Endangered Species Act of 1972 (as amended). No DA permit will be issued until the Corps has verified that all obligations under Section 7 of the Endangered Species Act have been fulfilled.

PUBLIC INTEREST REVIEW AND CUMULATIVE EFFECTS: This application will be reviewed in accordance with 33 CFR 320‑332, the Regulatory Program of the Corps, and other pertinent laws, regulations, and executive orders. Our evaluation will also follow the guidelines published by the United States Environmental Protection Agency pursuant to Section 404(b)(1) of the Clean Water Act (40 CFR part 230). The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity on the public interest. That decision will reflect the national concern for both the protection and the utilization of important resources. The benefit that reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors that may be relevant to the proposal will be considered, including the cumulative effects thereof; among those factors are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.

SOLICITATION OF COMMENTS: The Corps is soliciting comments from the public, Federal, state and local agencies and officials, Indian Tribes and other interested parties in order to consider and evaluate the impacts of this proposed activity. For accuracy and completeness of the administrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding of the reasons for support or opposition. Any person may request, in writing, within the comment period specified in the notice, that a public hearing be held to consider the application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements received in this office on or before the expiration date of this Public Notice will become a part of the record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest.

CLOSE OF COMMENT PERIOD: All comments pertaining to this Public Notice must reach this office on or before the close of the comment period listed on page one of this Public Notice. If no comments are received by that date, it will be considered that there are no objections. Comments should be submitted electronically to Ms. Kayla Osborne by email at kayla.n.osborne@usace.army.mil. If you do not have internet access, comments may be submitted through the U.S. Postal Service (USPS) to the following address:

United States Army Corps of Engineers, Huntington District

ATTN: CELRH-RD-N Public Notice: LRH-2020-632-MUS

502 Eighth Street

Huntington, West Virginia 25701-2070

Copies should only be provided through the USPS when electronic transmission is not possible. Precautionary internal mail handling procedures may be instituted to protect our workforce, which may result in longer than normal times to process and receive hard copy submissions. To be considered in our evaluation, comments submitted through the USPS should have a postmark dated on, or prior to, the close of the comment period listed on page one (1) of this Public Notice.

Please note names, addresses, and comments submitted in response to this Public Notice become part of our administrative record and, as such, may be available to the public under provisions of the Freedom of Information Act. Thank you for your interest in our nation’s water resources. If you have any questions concerning this Public Notice, please contact Ms. Kayla Osborne of the North Branch, at 304-399-5850, by mail at the above address, or by email at kayla.n.osborne@usace.army.mil.

Table 1. Proposed discharges of dredged and/or fill material into Waters of the United States associated with the McConnelsville Dam Project, McConnelsville, Morgan County, Ohio (Latitude 39.644005, Longitude -81.850183) – LRH-2020-632-MUS-Muskingum River

Aquatic Resource

Latitude & Longitude

(°N) (°W)

Flow Regime or Cowardin Class

Estimated amount of aquatic resource in review area

Linear Feet (lf) and/or Acres (ac) of Fill

Other Pertinent Information

Dam Rehabilitation

Muskingum River

39.64326

-81.84870

Perennial Stream

1,890 linear feet

110 lf (0.50 ac)

Dam Encapsulation

413 lf (3.32 ac)

Rock Channel Protection

100 lf (1.37 ac)

Cellular Sheet Pile Fill

150 lf (0.70 ac)

Temporary Construction Access

Wetland B

39.64446

-81.84906

Emergent Wetland

0.026 ac

0.026 ac

Bank Stabilization

Wetland C

39.64318

-81.84697

Emergent Wetland

0.189 ac

0.189 ac

Bank Stabilization

Wetland D

39.64300

-81.84673

Emergent Wetland

0.032 ac

0.032 ac

Bank Stabilization

Total Permanent Stream Impacts

623 lf (5.19 ac)

Total Permanent Wetland Impacts

0.247 ac

Total Temporary Stream Impacts

150 lf (0.70 ac)

Dam Replacement

Muskingum River

39.64326

-81.84870

Perennial Stream

1,890 linear feet

110 lf (0.50 ac)

Dam Construction

213 lf (3.16 ac)

Rock Channel Protection

100 lf (1.37 ac)

Cellular Sheet Pile Fill

164 lf (1.4 ac)

Temporary Construction Access

Wetland B

39.64446

-81.84906

Emergent Wetland

0.026 ac

0.026 ac

Bank Stabilization

Wetland C

39.64318

-81.84697

Emergent Wetland

0.189 ac

0.189 ac

Bank Stabilization

Wetland D

39.64300

-81.84673

Emergent Wetland

0.032 ac

0.032 ac

Bank Stabilization

Wetland H

39.64192

-81.84733

Emergent Wetland

0.241 ac

0.018 ac

Dam Construction

0.026 ac

Temporary Construction Access

Total Permanent Stream Impacts

423 lf (5.03 ac)

Total Permanent Wetland Impacts

0.247 ac

Total Temporary Stream Impacts

164 lf (1.4 ac)

Total Temporary Wetland Impacts

0.026 ac

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas