The application is for the discharge of fill material into the MKARNS located on the Verdigris River and Arkansas River. The activity includes outlet channel repairs, support cell repairs, and approximately 2,325 linear feet of new bank stabilization and approximately 970 linear feet of embankment maintenance and repairs.
Description of Work:
WEBBERS FALLS L&D #16 – REPAIR OUTLET CHANNEL: Work includes the mucking out of silt and other material from the outlet channel vicinity of the backfill drainpipe. The backfill drainpipe shall be cleared of all obstructions and returned to operating function. The area shall be returned to design grade. Work also consists of clearing and removal of existing vegetation debris with minimal earthwork grading along the Webbers Falls L&D #16 outlet channel east bank running approximately 695LF. 24-inch quarry run stone to be placed along slope in a manner that infills gaps and provides a consistent rocked slope from the top of the slope to the water’s edge, approximately 75FT of slope distance, while maintaining existing slope angle.
WEBBERS FALLS L&D #16 – REPAIR CHANNEL EROSION: Work shall consist of clearing and removal of existing vegetation debris with minimal earthwork grading along the Webbers Falls L&D #16 eastern shoreline running approximately 1,100 LF. Approximately 1,100 LF of 24-inch quarry run stone shall be placed along slope in a manner that infills gaps and provides a consistent rocked slope from the top of the slope to the water’s edge, approximately 75 FT of slope distance, while maintaining existing slope angle. Work includes the placement of stone in support cells from previously displaced stone.
CHOUTEAU L&D #17 – REPAIR EMBANKMENT: Work shall consist of clearing and removal of existing vegetation debris with earthwork grading along the Chouteau L&D #17 shoreline running approximately 1,225 LF. Approximately 1,225 LF of 24-inch quarry run stone shall be placed along the bank to the waters edge. Excavate slope if existing slope exceeds 1:1.5 slope to match section slope. Taper ends to meet and match existing grades if slope is in excess of 1:1.5. If end slopes exceed 1:1.5 use end detail provided in drawings (RE: C-401). 9-inch bedding stone and #57 stone to be placed along slope.
CHOUTEAU L&D #17 – REPLACE RIP RAP AND REPAIR SCOUR HOLES:
Work shall consist of clearing and removal of existing vegetation debris with minimal earthwork grading along the Chouteau L&D #17 eastern shoreline running approximately 275 LF. 24-inch quarry run stone shall be placed along slope in a manner that infills gaps and provides a consistent rocked slope from the top of the slope to the water’s edge, approximately 50 FT of slope distance, while maintaining existing slope angle.