On January 13, 2021, the U.S. Army Corps of Engineers (Corps) published a final rule in the Federal Register (86 FR 2744) announcing the reissuance of 12 existing nationwide permits (NWPs) and four new NWPs, as well as the reissuance of NWP general conditions and definitions with some modifications. These 16 NWPs will go into effect on March 15, 2021 and will expire on March 14, 2026.
FINAL PUBLIC NOTICE
PUBLIC NOTICE FOR THE FINAL REGIONAL CONDITIONS IN TEXAS WITHIN ALBUQUERQUE DISTRICT THAT ARE
APPLICABLE TO THE 16 NATIONWIDE PERMITS PUBLISHED IN THE FEDERAL
REGISTER ON JANUARY 13, 2021
On January 13, 2021, the U.S. Army Corps of Engineers (Corps) published a final rule in the Federal Register (86 FR 2744) announcing the reissuance of 12 existing nationwide permits (NWPs) and four new NWPs, as well as the reissuance of NWP general conditions and definitions with some modifications. These 16 NWPs will go into effect on March 15, 2021and will expire on March 14, 2026:
NWP 12 – Oil or Natural Gas Pipeline Activities
NWP 21 – Surface Coal Mining Activities
NWP 29 – Residential Developments
NWP 39 – Commercial and Institutional Developments
NWP 40 – Agricultural Activities
NWP 42 – Recreational Facilities
NWP 43 – Stormwater Management Facilities
NWP 44 – Mining Activities
NWP 48 – Commercial Shellfish Mariculture Activities
NWP 50 – Underground Coal Mining Activities
NWP 51 – Land-Based Renewable Energy Generation Facilities
NWP 52 – Water-Based Renewable Energy Generation Pilot Projects
NWP 55 – Seaweed Mariculture Activities
NWP 56 – Finfish Mariculture Activities
NWP 57 – Electric Utility Line and Telecommunications Activities
NWP 58 – Utility Line Activities for Water and Other Substances
The January 13, 2021, Federal Register notice is available for viewing at https://www.federalregister.gov/documents/2021/01/13/2021-00102/reissuance-and-modification-ofnationwide-permits.As an alternative, interested parties can access the January 13, 2021, final rule and related documents at: https://www.usace.army.mil/Missions/Civil-Works/Regulatory-Program-and-Permits/Nationwide-Permits/.
There are 40 existing NWPs that were not reissued or modified by the January 13, 2021 final rule. Those 40 NWPs were published in the January 6, 2017, issue of the Federal Register (82 FR 1860) and those NWPs remain in effect until the Corps issues a final rule reissuing those NWPs or March 18, 2022, whichever comes first. The 40 2017 NWPs that remain in effect are:
NWP 1 – Aids to Navigation
NWP 2 – Structures in Artificial Canals
NWP 3 – Maintenance
NWP 4 – Fish and Wildlife Harvesting, Enhancement, and Attraction Devices and Activities
NWP 5 – Scientific Measurement Devices
NWP 6 – Survey Activities
NWP 7 – Outfall Structures and Associated Intake Structures
NWP 8 – Oil and Gas Structures on the Outer Continental Shelf
NWP 9 – Structures in Fleeting and Anchorage Areas
NWP 10 – Mooring Buoys
NWP 11 – Temporary Recreational Structures
NWP 13 – Bank Stabilization
NWP 14 – Linear Transportation Projects
NWP 15 – U.S. Coast Guard Approved Bridges
NWP 16 – Return Water From Upland Contained Disposal Areas
NWP 17 – Hydropower Projects
NWP 18 – Minor Discharges
NWP 19 – Minor Dredging
NWP 20 – Response Operations for Oil or Hazardous Substances
NWP 22 – Removal of Vessels
NWP 23 – Approved Categorical Exclusions
NWP 24 – Indian Tribe or State Administered Section 404 Programs
NWP 25 – Structural Discharges
NWP 27 – Aquatic Habitat Restoration, Establishment, and Enhancement Activities
NWP 28 – Modifications of Existing Marinas
NWP 30 – Moist Soil Management for Wildlife
NWP 31 – Maintenance of Existing Flood Control Facilities
NWP 32 – Completed Enforcement Actions
NWP 33 – Temporary Construction, Access, and Dewatering
NWP 34 – Cranberry Production Activities
NWP 35 – Maintenance Dredging of Existing Basins
NWP 36 – Boat Ramps
NWP 37 – Emergency Watershed Protection and Rehabilitation
NWP 38 – Cleanup of Hazardous and Toxic Waste
NWP 41 – Reshaping Existing Drainage Ditches
NWP 45 – Repair of Uplands Damaged by Discrete Events
NWP 46 – Discharges in Ditches
NWP 49 – Coal Remining Activities
NWP 53 – Removal of Low-Head Dams
NWP 54 – Living Shorelines
The regional conditions for these 40 NWPs that were approved by the Division Engineer in 2017 remain in effect and can be found at https://www.spa.usace.army.mil/Missions/Regulatory-Program-and-Permits/NWP/.
TEXAS CWA SECTION 401 WATER QUALITY CERTIFICATIONS
With the exception of NWP 55 and NWP 56 for which no water quality certification was requested, the Environmental Protection Agency (EPA) Region 6, by letter dated December 14, 2020, on behalf of Ysleta del Sur Pueblo, Alabama-Coushatta Tribe of Texas, and Kickapoo Traditional Tribe of Texas, granted CWA Section 401 certification, with no conditions, for these 16 NWPs (Encl 3). EPA Region 6 has determined that any discharge that could be authorized under these 14 NWPs would comply with water quality requirements, as defined at 40 CFR 121.1(n).
The Texas Commission on Environmental Quality (TCEQ), by letter dated December 18, 2020, conditionally certified these 16 NWPs, with the exception of NWP 48, NWP 55, and NWP 56 which were certified with no conditions (Encl 4). TCEQ has determined that any discharge that could be authorized under these 16 NWPs would comply with water quality requirements, as required by CWA Section 401 certification and pursuant to Title 30 Texas Administrative Code (TAC) Chapter 279. Conditions for each NWP were defined in the TCEQ’s water quality certification letter.
The Texas Railroad Commission (TxRRC), by letter dated December 18, 2020, conditionally certified NWP 12, NWP 43, and NWP 58 (fka D) and determined that they should not result in a violation of Texas Surface Water Quality Standards as required by CWA Section 401 and pursuant to 16 TAC §3.93 (Encl 5). Conditions for each NWP were defined in TxRRC’s water quality certification letter. Under Texas Natural Resource Code, Title 3, and the Texas Water Code, Chapter 26, the TxRRC has the responsibility for the prevention of pollution that might result from activities associated with the exploration, development, and production of oil, gas, or geothermal resources of the State.
TEXAS REGIONAL CONDITIONS
Dredge and Fill Activities in Lakes, Intermittent and Perennial Streams, and Special Aquatic Sites: For all activities subject to regulation under the CWA Section 404 in lakes, intermittent and perennial streams, and special aquatic sites (including wetlands, riffle and pool complexes, and sanctuaries and refuges), Pre-Construction Notification to the District Engineer is required in accordance with General Condition 32.
Suitable Fill: Use of broken concrete as fill or bank stabilization material is prohibited unless the applicant demonstrates that its use is the only practicable material (with respect to cost, existing technology, and logistics). Any applicant who wishes to use broken concrete as bank stabilization must provide notification to the District Engineer in accordance with General Condition 32 (Pre-Construction Notification) along with justification for such use. Use of broken concrete with rebar, used tires (loose or formed into bales), or car bodies is prohibited in all waters of the United States.
ADDITIONAL INFORMATION
The following provides additional information regarding minimization of impacts and compliance with existing General Conditions:
Permittees are reminded of General Condition 6 which prohibits the use of unsuitable material. Organic debris, building waste, asphalt, car bodies, individual tires, concrete jersey barriers, and trash are not suitable fill material.
General Condition 12 requires appropriate erosion and sediment controls (i.e., all fills must be permanently stabilized to prevent erosion and siltation into water and/or wetlands at the earliest practicable date). Streambed material or other small aggregate material placed along a bank as stabilization will not meet General Condition 12.