The applicant proposes to impact 140-linear-foot of a tributary.
pport the access road as it crosses Tributary A.
Full Public Notice Project Plans
REVISED PROJECT DESCRIPTION: The applicant proposes to impact 300-linear-foot of a tributary (Tributary A) to facilitate the installation of reinforced-concrete box (RCB) culvert at the “Main Entrance” and an “Access Road” at the south end of the project site to cross Tributary A. The 20-linear-foot of concrete riprap will serve as erosion control for water entering and exiting the previously permitted culvert at the "Main Entrance". The remaining 280-linear-foot of impacts to Tributary A is for the construction of the “Access Road”. The 100-linear-foot of culvert will structurally support the access road as it crosses Tributary A.