You can copy from here when filling out the rest of the page.
The proposed work is to repair and armor approximately 1,500 linear feet (lf) of the left descending bank of the MKARNS immediately downstream of Newt Graham, Lock 18.
Approximately 50,000 tons of 24” rock would be placed along approximately 1,500 lf of the left descending bank of the MKARNS immediately downstream of Newt Graham, Lock 18, as depicted on the enclosed plans (Enclosure 1 and Enclosure 2). No dredging or disposal of dredged materials would occur as part of this project.