You can copy from here when filling out the rest of the page.
CONSTRUCTION OF A BULKHEAD AND STORM WATER COLLECTION SYSTEM AT BULK TERMINAL #1 IN CALCAISEU PARISH
NAME OF APPLICANT: Southland Environmental, L.L.C., obo Lake Charles Harbor and Terminal District; Attn: Jared King; 510 Clarence Street, Lake Charles, Louisiana 70601.
LOCATION OF WORK: A 2.5-acre site off of the Bayou D’ Inde Road and along the Calcasieu River, in Sections 16 and 17, Township 10 South, Range 9 West, Calcasieu Parish Louisiana, as shown on attached drawings.
Center of Location: Latitude: 30.191325° N, Longitude: -93.299558° W.
Hydrologic Unit Code: 08080206 – Lower Calcasieu, Calcasieu River Basin.
CHARACTER OF WORK: Installation of a new bulkhead and storm water collection system at the Bulk Terminal #1 Facility Dock along the Calcasieu River in Westlake, Louisiana. The new bulkhead is proposed for erosion protection and infrastructure for the storm water collection system. The purpose of the storm water collection system is the containment of coke particulates to the Bulk Terminal #1 site and prevention of impacts to the Calcasieu River watershed. Work includes backfilling with 12,500 cubic yards of earthen material, 2,800 cubic yards of concrete material, and 4,100 cubic yards of aggregate material. Approximately 1.17 acres of permanent scrub shrub impacts and 0.7 acres of impacts to Waters of the United States are proposed. If a Department of the Army permit is warranted, the applicant has proposed to mitigate unavoidable wetlands impacts at an approved mitigation bank within the New Orleans District.