Home

Tulsa District

Run scraper

In compliance with U.S.C. Title 33

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

In compliance with U.S.C. Title 33, Chapter 9, Subchapter 1, Section 408, the Kansas Gas Service (requester) has requested permission from the U.S. Army Corps of Engineers (USACE) for the retirement of a gas pipeline crossing the Arkansas River.

Requester proposes to decommission existing section of pipeline by removing natural gas, capping pipeline ends, and sealing with grout. Additionally, a section of pipeline that was exposed through channeling by recent heavy flows will be capped and removed. To access the pipeline, requester anticipates the need to dig exposure holes relatively small in diameter and less than five feet deep. Exposure holes will be backfilled upon project completion.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas