In compliance with U.S.C. Title 33, Chapter 9, Subchapter 1, Section 408, the Kansas Gas Service (requester) has requested permission from the U.S. Army Corps of Engineers (USACE) for the retirement of a gas pipeline crossing the Arkansas River.
Requester proposes to decommission existing section of pipeline by removing natural gas, capping pipeline ends, and sealing with grout. Additionally, a section of pipeline that was exposed through channeling by recent heavy flows will be capped and removed. To access the pipeline, requester anticipates the need to dig exposure holes relatively small in diameter and less than five feet deep. Exposure holes will be backfilled upon project completion.