STATE - Kentucky APPLICANT - Nugent Sand Company PROJECT PURPOSE - To suction dredge for the commercial sale of sand

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

STATE - Kentucky APPLICANT - Nugent Sand Company PROJECT PURPOSE - To suction dredge for the commercial sale of sand, to scrap dredge for navigation purposes, to construct a new fleet, to replace a cell with a tripod dolphin, and to consolidate past permit authorizations into one authorization.

This notice announces an application submitted for a Department of the Army (DA) Permit subject to Section 10 of the Rivers Act of 1899 and Section 404 of the Clean Water Act.

APPLICANT: Nugent Sand Company

Bob Holt

1833 River Road

Louisville, Kentucky 40206

LOCATION: The proposed project is located on the left bank of the Ohio River, Mile Marker 552.1 to 552.8, in Milton, Trimble County, Kentucky.

Latitude: 38.737658 N

Longitude: -85.283152

7.5 Minute Quad: Madison East

PURPOSE: To suction dredge for the commercial sale of sand, to scrap dredge for navigation purposes, to construct a new fleet, to replace a cell with a tripod dolphin, and to consolidate past permit authorizations into one authorization.

FACILITY HISTORY: Currently, the Nugent Sand Company, Milton Facility, is authorized to load and unload aggregate, coal, and other dry bulk commodities.

The existing lower yard (downriver end of entire facility) has a previously authorized unloading dock, also referred to as a cell structure, which is currently under construction. The purpose of the cell structure is to extend riverward access for landward operations. The unloading operation includes a hopper and excavator mounted on the cell structure. The permitted activity also includes a 12’x 34.5’ floating dock that can be used to moor a towboat anchored to the downriver end of the cell structure. Two 195’ x 35’ barges, configured one wide and two long, are permitted to be secured to the unloading cell structure and a dolphin tripod

structure. Loaded barges are processed through the unloading operation with the use of a winch and cable system. The cell mounted excavator removes the commodity from the barge to the hopper/conveyor system which transports the material to the approved upland stockpile yard. Once unloaded, barges are moved to the downriver end of the cell structure where the barges will be cleaned. Any associated wash water/slag is pumped to an upland permitted settling basin.

The upper yard (upriver end of entire facility) has a previously authorized loading facility and two approved fleeting areas. The loading facility uses a conveyor hopper system to transport aggregate and gypsum material from the processing and stockpile yard, located adjacent to the river facility near KY Highway 36, to barges docked at the loadout hopper. Barges being loaded are maneuvered through the loading dock via a winch and cable system. Once barges are loaded, they are staged at the existing fleeting area, with a configuration of 2 long and 5 wide, before being transported. Immediately upriver of the loading dock, the applicant is approved for an empty barge fleet with a maximum configuration of 3 long by 5 wide. The fleets at the upper yard and the loading operations are secured to a series of 13 cells and dolphins.

DESCRIPTION OF PROPOSED WORK: The applicant is requesting authorization to conduct dredging for a period of 10 years. The dredging would occur in two phases. The first phase would include dredging the entire length of the transloading facility, approximately 4,215 linear feet long and approximately 70 feet in width (6.8 acres) of river bottom. This activity would be completed by suction dredging and would remove approximately 15,000 cubic yards of material, consisting mostly of silt and sand. The dredged material would be loaded onto barges and offloaded at the facility where it would be commercially sold or disposed of the fill material in an existing upland disposal area. Return water from the dredging operation would be processed through the barge operations at the lower yard and returned to the Ohio River in situ. The applicant expects that dredging would need to be completed on a 4 to 5-year cycle.

The second phase of dredging activities would involve scraper dredging in selected areas (Scraping Areas A and B) along the transloading facility and toward the riverbank for the purpose of maintaining adequate river depth for navigation to and from the facility. Scraping Area A would include dredging an area approximately 1,350 feet in length and approximately 70 in width, while Scraping Area B would include dredging an area approximately 1,050 feet in length and approximately 70 feet in width. The goal minimum depth of the river bottom is 14 feet of depth. The scraper dredge would remove in total approximately 2,500 cubic yards of material and dispose of it back into the previously proposed dredged areas. This scrapper dredging is proposed to occur twice annually. Records demonstrate that periodic maintenance dredging has occurred at this facility since at least the 1970’s.

In addition, the applicant requests authorization to install a new fleet, configured 3 long and 5 wide, secured by 4 new tripod dolphin structures approximately 600 feet downriver from the unloading portion of the facility. The proposed tripod dolphin structures would be driven a minimum of 10 feet into the river bottom and barges would be secured to said structures utilizing a 5/8 inch steel cable.

The applicant is also requesting authorization to remove a failing 6-foot square cell downriver of the loading facility and to replace it with a new tripod dolphin structure. The maximum riverward projections of the transloading operations, including the fleets at Normal Pool (elevation 420 feet mean sea level, Ohio River Datum), would be 240 feet.

It is noted that this proposed mitigation plan is open to comment and subject to change. The Corps will make a determination of appropriate mitigation, upon review of all submitted information.

REVIEW PROCEDURES: A DA Permit cannot be issued if any legally required Federal, State, or local authorization or certification is denied. A DA permit, if otherwise warranted, will not be issued until a State of Kentucky Water Quality Certification or waiver is on file at this office. In order to comply with Section 401 of the Clean Water Act, the applicant must apply for State certification from the Kentucky Energy and Environment Cabinet Division of Water (KDOW).

Copies of this notice are sent to the appropriate Federal and State Fish and Wildlife Agencies. On November 3, 2021, the Corps determined that the proposed project would have No Effect on Federally-listed threatened or endangered species. For mussel species, this determination is based on a bathometric survey conducted in 2017 which found that the project area lacks suitable mussel habitat. Also, the area has undergone dredging since the 1970’s. Additionally, the determination for all listed species is based on lack of suitable habitat due to extensive ground disturbance activities that have occurred since the 1970’s.

Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. A request for a public hearing must state the specific interest which might be damaged by issuance of the DA Permit.

On November 9, 2021, the Corps determined that the project would have No Effect to Historic Properties. This determination is based on extensive past disturbance at the project site. However, if we are made aware, as a result of comments received in response to this notice, or by other means, of specific archaeological, scientific, pre-Columbian, or historical sites or structures which might be affected by the proposed work, the District Engineer will immediately take the appropriate action necessary pursuant to the National Historic Preservation Act of 1966 – Public Law 89-665 as amended (including Public Law 96-515).

The decision whether to issue a permit will be based on an evaluation of the probable impact of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utiliza­tion of important resources. The benefits which reasonably may be expected to accrue from the proposal must be balanced against its reasonably fore­seeable detriments. All factors which may be relevant to the proposal will be considered; among those are conservation, economics, aesthetic values, general environmental concerns, historic values, fish and wildlife values, flood damage prevention, land use, navigation, recreation, water supply, water quality, energy needs, safety, food production, and in general, the needs and welfare of the public. In addition, the evaluation of the impact of the activity on the public interest will include application of the guidelines (40 CFR Part 230) promulgated by the Administrator, United States Environmental Protection Agency, under authority of Section 404(b) of the CWA.

The Corps of Engineers is soliciting comments from the public; Federal, State, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. It is presumed that all interested parties and agencies will wish to respond; therefore, a lack of response will be interpreted as meaning that there is no objection to the proposed project. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

Written statements received in this office on or before the closing date will become a part of the official record and will be considered in the determination on this permit request. Any objections which are received during this period will be forwarded to the applicant for possible resolution before the determination is made whether to issue or deny the requested DA Permit. A permit will be granted unless its issuance is found to be contrary to the public interest.

Information pertaining to this application is available for public examination during normal business hours upon prior request. Drawings are available on Louisville District's Internet site at http://www.lrl.usace.army.mil/Missions/Regulatory/Public-Notices/. All comments regarding this proposal should be addressed to Kimberly J. Simpson, CELRL-RDN at the address noted above and should refer to the Public Notice Number LRL-2021-00920.

If you desire to submit your comments by email, you must comply with the following:

a) In the subject line of your email, type in ONLY the Public Notice ID No. LRL-2021-00920.

Example:

Subject: LRL-2021-00920

b) Provide your physical mailing address and telephone number.

c) Send your email to: lrl.regulatorypubliccomment@usace.army.mil

d) If you are sending attachments greater than 10 Mb in size with your email, you must send a hard copy (CD or paper) to the Corps’ physical address as well.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas