Permanent Lower Dock Barge Construction LaFarge-Holcim Facility: Cumberland River Mile 7.2 RDB
Sterling Industrial isconducting the final installation of the permanent lower dock barge at the Lafarge-Holcim facility at Cumberland River Mile 7.2 RDB. Installation beganFebruary 1, 2022 and is estimated to be complete onMarch 18, 2022. During this time, expect to seeseveral barges in the water (a 110’ x 51’ crane barge and a 100’ x 30’ material barge). After working hours, the barges will be moored at the down-river end of the new lower dock barge. Crews will monitor Marine Channels 13 and 78.