You can copy from here when filling out the rest of the page.
The applicant proposes to discharge fill material during the construction of a commercial waste management facility, including amenities.
Public Notice Plans Mitigation Plan
The applicant proposes to permanently discharge fill material into 0.63-acre of palustrine forested (PFO) wetlands, 0.16-acre of palustrine shrub scrub (PSS) wetlands, 1.13-acres of palustrine emergent (PEM) wetlands, 0.16-acre of manmade ponds, and 2,103-linear-feet of streams. Additional temporary impacts include the discharge of fill material into 0.07-acre of PFO wetlands, 0.03-acre of PSS wetlands, 0.09-acre of PEM wetlands, 0.8-acre of manmade ponds, and 1,409-linear-feet of streams on a 32-acre tract for a multi-use, commercial waste management facility, including amenities such as a two-story office building, refueling stations, a maintenance shop, visitor and employee parking lot, container shop, container storage area, and two stormwater water retention/detention basins.