You can copy from here when filling out the rest of the page.
Section 408 permit application from the City of Peoria, through the Flood Control District of Maricopa County, has requested permission from the U.S. Army Corps of Engineers (USACE) to alter the New River Dam Impoundment Area, a part of the federal project titled Gila River Basin, Phoenix Arizona and Vicinity (Including New River), New River Dam, Maricopa County, Arizona.
Construction of Paloma Community Park Phase 2, a 45-acre expansion of Paloma Community Park, formerly known as Northern Community Park, in a parcel owned by the Flood Control District of Maricopa County. The purpose of the project is to serve the community of Peoria, Arizona by providing recreational park facilities.