Cheatham Lock 2022 Lock Closure Schedule There will be no restrictions during the temporary openings
Cheatham Lock 2022 Lock Closure Schedule There will be no restrictions during the temporary openings Cheatham Lock at Cumberland River Mile 148.7 will be closed to navigation beginning at 0600 16 May 2022 and continuing through 05 August 2022 due to repairs on upper gates and culvert valves. The USACE Light Capacity Fleet will be moored to the upper mooring cells throughout the duration of the project.There will be temporary openings to allow navigation passage during the listed phases posted below. During these temporary openings there will not be any restriction.
Cheatham Lock Temporary Openings
Task Name
Duration
Start
Finish
Phase 1
14 Days
05/16/2022
05/29/2022
Lock Closed
11 Days
05/16/2022
05/26/2022
Lock Open
3 Days
05/27/2022
05/29/2022
Phase 2
14 Days
05/30/2022
06/15/2022
Lock Closed
11 Days
05/30/2022
06/09/2022
Lock Open
3 Days
06/10/2022
06/12/2022
Phase 3
14 Days
06/13/2022
06/26/2022
Lock Closed
11 Days
06/13/2022
06/23/2022
Lock Open
3 Days
06/24/2022
06/26/2022
Phase 4
14 Days
06/27/2022
07/10/2022
Lock Closed
4 Days
06/27/2022
06/30/2022
Lock Open
10 Days
07/01/2022
07/10/2022
Phase 5
14 Days
07/11/2022
07/24/2022
Lock Closed
11 Days
07/11/2022
07/21/2022
Lock Open
3 Days
07/22/2022
07/24/2022
Phase 6
11 Days
07/25/2022
08/04/2022
Lock Closed
11 Days
07/25/2022
08/04/2022
Lock Open/Project Complete
08/05/2022