You can copy from here when filling out the rest of the page.
STATE - Ohio *** APPLICANT - Tunnel Hill Reclamation, LLC *** PURPOSE - The applicant proposes to discharge dredged or fill material into waters of the United States to facilitate the expansion of the current landfill operation.
TO WHOM IT MAY CONCERN: The following application has been submitted to the United States Army Corps of Engineers (Corps) for a Department of the Army (DA) Permit under the provisions of Section 404 of the Clean Water Act.
APPLICANT: Mr. Brian Ezyk
Tunnel Hill Reclamation, LLC
8822 Tunnel Hill Road
New Lexington, Ohio 43764
LOCATION: The proposed 400-acre project would be located at 8822 Tunnel Hill Road, in New Lexington, Perry County, Ohio (Latitude: 39.729761, Longitude: -82.161353). The project can be found on the New Lexington Ohio United States Geological Survey 7.5-minute quadrangle map. Waters on-site flow to Rush Creek, a direct tributary to the Hocking River, a traditional navigable water (TNW) of the United States. See Exhibit 1 – Site Location Map.
PROJECT HISTORY: On August 3, 2021, representatives from the Corps conducted a site verification for waters located within the Tunnel Hill Landfill Expansion Project. Following the site visit, a Preliminary Jurisdictional Determination and Approved Jurisdictional Determination were issued for the project area on March 21, 2022. The proposed landfill expansion project area is entirely within previously disturbed areas associated with previously permitted areas associated with surface coal mining. The Department of the Army permits associated with the previously permitted mining activities are LRH-1996-00327, LRH-1999-00797, LRH-2001-00269, and LRH-2001-00085. See Exhibit 5 – Previous Coal Mining Permit Areas
DESCRIPTION OF PROPOSED WORK: The applicant proposes to discharge dredged or fill material into waters of the United States to facilitate the expansion of the current landfill operation. The applicant has requested a DA permit to discharge dredged and/or fill material into 7.26 acres of wetlands, and 4,080 linear feet (0.29 acre) of streams, associated with the construction of the Tunnel Hill Landfill Expansion Project. Specifically, the project would consist of expanding the existing landfill footprint south and west by 156 acres to provide an additional 91 million cubic yards of disposal volume.
General Site and Design Plans of the proposal are attached to this notice (Exhibits 2-4).
ALTERNATIVES ANALYSIS: A total of 7.26 acres of five (5) wetlands, and 4,080 linear feet of two (2) streams would be filled as a result of the proposal. The project does not require access or proximity to or siting within the wetlands to fulfill its basic purpose and is considered a non-water dependent activity. The Section 404(b)(1) Guidelines state that for non-water dependent activities in special aquatic sites, practicable alternatives that do not involve wetlands are presumed to be available, unless clearly demonstrated otherwise. The applicant is required to provide an alternatives analysis that must overcome the presumption prior to receiving authorization for the discharge of fill material into the streams and wetlands. The applicant has submitted the required alternatives analysis and it is currently under review. A complete copy of the applicant’s alternatives analysis can be reviewed by appointment at the above address. No permit will be issued until our office determines practicable upland alternatives are not available to achieve the overall project purpose based upon the applicant’s alternative analysis.
AVOIDANCE AND MINIMIZATION: In evaluating a project area containing waters of the United States, consideration must be given to avoiding impacts on these sites. If waters of the United States cannot be avoided, then the impacts must be minimized. Approximately 8.38 acres of wetlands and 5,629 linear feet of streams exist on the project site that are subject to Section 404 Clean Water Act regulation. The applicant has indicated that there is no practicable alternative for the proposed project that completely avoids the discharge of dredged and/or fill material into waters of the United States and would meet the overall project purpose. Avoidance and minimization efforts were incorporated into the proposal to reduce the footprint of the proposed project. The applicant’s project would avoid 14% of the on-site streams and 12% of the on-site wetlands. According to the applicant, alternative plans were considered. Temporary sediment controls such as silt fence, straw bales, rock checks, dikes, and/or protective stream barriers would be used to prevent and minimize downstream sedimentation. In-stream construction activities would occur during low flow periods to the greatest extent practicable. Standard best management practices would be used. Project effluent would be managed pursuant to the approved Section 402 National Pollutant Discharge Elimination System permit to ensure water quality standards are met.
COMPENSATORY MITIGATION PLAN (CMP): To compensate for the losses of waters of the United States associated with the proposed project, the applicant proposes to purchase 6.1 acres of wetland credits from The Nature Conservancy through Ohio’s In-lieu Fee Program. The applicant’s CMP is currently under review. After review of all the submitted information, the Corps will determine it the type and level of compensatory mitigation are adequate in the even a decision is made to issue a DA authorization.
WATER QUALITY CERTIFICATION: The applicant must obtain a Section 401 Water Quality Certification (WQC) from the Ohio Environmental Protection Agency assuring that applicable laws and regulations pertaining to water quality are not violated. A DA permit, if otherwise warranted, would not be issued on this project until the Section 401 WQC has been issued or waived and the Section 401(a)(2) process has been completed with the U.S. Environmental Protection Agency (USEPA). The Reasonable Period of Time for the certifying authority (Ohio Environmental Protection Agency) to act on the Section 401 WQC will be 270 days from the date the Ohio Environmental Protection Agency receives a valid certification request (40 CFR 121.5). A pre-filing meeting request must be submitted to the Ohio Environmental Protection Agency 30 days prior to submitting a certification request. The certification request must be submitted to the Corps and the Ohio Environmental Protection Agency concurrently. A waiver may be explicit or will be deemed to occur if the Ohio Environmental Protection Agency fails or refuses to act on a request for certification within 270 days after receipt of a valid certification request.
HISTORIC AND CULTURAL RESOURCES: The Corps is required by the National Historic Preservation Act (NHPA) to ensure no federal undertaking, including a Corps’ permit action, which may affect historic resources, is commenced before the impacts of such action are considered and the Advisory Council on Historic Preservation and the State Historic Preservation Office (SHPO) are provided an opportunity to comment as required by the NHPA, 36 CFR 800, and 33 CFR 325, Appendix C. The National Register of Historic Places (NRHP) has been consulted and it has been determined that there are no properties currently listed on the NRHP that would be indirectly or directly affected by the proposed work. The proposed project is entirely within a previously disturbed area from surface coal mining and reclamation activities. Structures on-site consists of a scale house and a prefabricated office building. In the immediate vicinity of the project site, attendant features for the existing landfill operations are present and includes a railway, maintenance building, and rail unloading structure. Therefore, based on the provided information, the Corps has determined that no historic properties listed on, or eligible for listing on, the NRHP would be affected by the proposed undertaking. A copy of this Public Notice will be furnished to Ohio SHPO for their review. Comments concerning archaeological sensitivity of the project area should be based on collected data. No DA permit will be issued until all obligations under Section 106 of the NHPA have been fulfilled.
THREATENED AND ENDANGERED SPECIES: The proposed project is located within the known or historic range of the following threatened (T) or endangered (E) species: Indiana bat (E), (Myotis sodalis), northern long-eared bat (T), (Myotis septentrionalis), eastern masssauga (T), (Sistrusrus catenatus), and the American burying beetle (E), (Nicrophorus americanus).
Suitable habitat for the Indiana bat, and the northern long-eared bat, may be present within the site. The applicant has agreed to conduct tree clearing operations associated with the proposed project prior to April 1 and after September 30, as recommended by the United States Fish and Wildlife Service (USFWS), to minimize effects on the federally-protected bat species. The Corps has determined the proposed project may affect, but is not likely adversely affect either the Indiana bat or the northern long-eared bat. The project site contains wetlands that may provide potential suitable habitat for the eastern massasauga. Thus, the Corps has determined that the proposed project may affect but is not likely to adversely affect the eastern massasauga. The project site contains grasslands that may provide potential suitable habitat for the American burying-beetle. Thus, the Corps has determined that the proposed project may affect but is not likely to adversely affect the American burying-beetle. The USFWS IPAC Consultation Code is 03E15000-2021-SLI-2156.
This Public Notice serves as a request for concurrence from the USFWS for the aforementioned effect determination and for any additional information they may have on whether any listed or proposed to be listed E or T species may be present in the area which would be affected by the activity, pursuant to Section 7(c) of the Endangered Species Act of 1972 (as amended). No DA permit will be issued until the Corps has verified that all obligations under Section 7 of the Endangered Species Act have been fulfilled.
PUBLIC INTEREST REVIEW AND CUMULATIVE EFFECTS: This application will be reviewed in accordance with 33 CFR 320‑332, the Regulatory Program of the Corps, and other pertinent laws, regulations, and executive orders. Our evaluation will also follow the guidelines published by the USEPA pursuant to Section 404(b)(1) of the Clean Water Act (40 CFR part 230). The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity on the public interest. That decision will reflect the national concern for both the protection and the utilization of important resources. The benefit that reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors that may be relevant to the proposal will be considered, including the cumulative effects thereof; among those factors are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.
SOLICITATION OF COMMENTS: The Corps is soliciting comments from the public, federal, state, and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. For accuracy and completeness of the administrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding of the reasons for support or opposition. Any person may request, in writing, within the comment period specified in the notice, that a public hearing be held to consider the application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements received in this office on or before the expiration date of this public notice will become a part of the record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest.
CLOSE OF COMMENT PERIOD: All comments pertaining to this Public Notice must reach this office on or before the close of the comment period listed on page one (1) of this Public Notice. If no comments are received by that date, it will be considered that there are no objections. Comments should be submitted electronically to Mr. Kyle Moore by email at kyle.m.moore@usace.army.mil. If you do not have internet access, comments may be submitted through the U.S. Postal Service (USPS) to the following address:
United States Army Corps of Engineers
ATTN: CELRH-RDN
Public Notice No. LRH-2021-581-HOC
502 Eighth Street
Huntington, West Virginia 25701-2070.
Copies should only be provided through the USPS when electronic transmission is not possible. Precautionary internal mail handling procedures may be instituted to protect our workforce, which may result in longer than normal times to process and receive hard copy submissions. To be considered in our evaluation, comments submitted through the USPS should have a postmark dated on, or prior to, the close of the comment period listed on page one (1) of this Public Notice.
Please note names, addresses, and comments submitted in response to this Public Notice become part of our administrative record and, as such, may be available to the public under provisions of the Freedom of Information Act. Thank you for your interest in our nation’s water resources. If you have any questions concerning this Public Notice, please contact Mr. Kyle Moore of the North Branch, at 513-825-3444, by mail at the above address, or by email at kyle.m.moore@usace.army.mil.