You can copy from here when filling out the rest of the page.
The applicant proposes to discharge.
Public Notice Project Plans Mitigation Plan Alternative Analysis
The applicant proposes to discharge approximately 11,136.97-cubic yards of fill into approximately 2.23-acres and 133-ft of waters associated with the installation of an approximate 360-foot x 310-foot new electrical substation, an approximate 2,195-foot x 25-foot access road, an approximate 215-foot x 52-foot detention pond, and an approximate 455-foot x 733-foot transmission line cut-in. Such activities include permanent impacts (loss) to approximately 1.63-acres of palustrine forested wetlands (PFO), 0.003-acre of palustrine emergent wetlands (PEM), and the permanent conversion of 0.38-acre of PFO wetlands to PEM wetlands. Temporary impacts include 0.19-acre of PEM wetlands, and 0.03-acre (133-linear-feet) of waters associated with temporary workspaces.