The City of Martinez (Contact: Kara Dewhurst, Anchor QEA LLC, 33 New Montgomery Street, San Francisco, CA 94105) has applied for a ten-year Department of the Army permit to conduct maintenance dredging within the Martinez Marina located in Martinez, Contra Costa County,
California. The purpose of the proposed dredging is to return the marina to its original design depths in order to facilitate safe navigational depths for recreational vessels. This Department of the Army Permit application is being processed pursuant to the provisions of Section 404 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1344 et seq.) and Section 10 of the Rivers and Harbors Act of 1899, as amended (33 U.S.C. § 403 et seq.).
SAN FRANCISCO DISTRICT
PUBLIC NOTICE
PROJECT: Martinez Marina Maintenance Dredging
PUBLIC NOTICE NUMBER: 2012-00070
PUBLIC NOTICE DATE: August 11, 2022
COMMENTS DUE DATE: August 26, 2022
PERMIT MANAGER: Melissa France TELEPHONE: 415-503-6768 E-MAIL: Melissa.M.France@usace.army.mil
1. INTRODUCTION: The City ofMartinez(Contact: Kara Dewhurst, Anchor QEA LLC, 33 New Montgomery Street, San Francisco, CA 94105) hasapplied for a ten-year Department of the Army permit to conduct maintenance dredging within theMartinez Marina located in Martinez, Contra Costa County, California. The purpose of the proposeddredging is to return the marina to its original design depths in order to facilitate safenavigational depths for recreational vessels. This Department of the Army Permit applicationis being processed pursuant totheprovisions of Section 404 of the Clean Water Act of 1972, asamended (33 U.S.C. § 1344 et seq.) and Section 10 of the Rivers and Harbors Act of 1899, as amended
(33 U.S.C. § 403 et seq.).
2. PROPOSED PROJECT:
Project Site Location: The Martinez Marina is located in the city of Martinez, Contra Costa County,California.
Project Site Description: The site encompasses approximately 4.4 acres and is located along thesouthern shoreline of the Carquinez Strait at 7 North Court Street in the City of Martinez, ContraCosta County, as depicted in Figures 1 and 2.
Project Description: As shown in the attached drawings, the applicant plans to removeapproximately 54,200 cubic yards (cys) of sediment from the 4.4-acre (approximately) basin in a
single dredging episode. The design depth for the proposed project is -6 feet MLLW plus anadditional 2-foot overdredge allowance.
The material would be removed using a clamshell orexcavator and removed by barge to an in-bay disposalsite such as SF-9 (Carquinez Strait).Prior to each dredging episode, the Dredge MaterialManagement Office (DMMO) will evaluate thesediments to be dredged for disposal or reuse suitability.The DMMO includes representatives from the U.S.Environmental Protection Agency, San Francisco BayConservation and Development Commission(BCDC), San Francisco Bay Regional Water QualityControl Board (RWQCB), and the Corps. The DMMOis tasked with approving sampling and analysis plansin conformity with testing manuals, reviewing the testresults and reaching consensus regarding a suitabledisposition for the material.
Basic Project Purpose: The basic project purposecomprises the fundamental, essential, or irreduciblepurpose of the project, and is used by the Corps todetermine whether the project is water dependent.Although the purpose of the project, as stated above,is for safe navigational depths, for consideration inSection 404(b)(1) (Clean Water Act), the basicpurpose of the project is navigation.
Overall Project Purpose: The overall projectpurpose serves as the basis for the Section 404(b)(1)alternatives analysis and is determined by furtherdefining the basic project purpose in a manner thatmore specifically describes the applicant's goals forthe project, while allowing a reasonable range ofalternatives to be analyzed. The overall projectpurpose is the disposal of dredged material frommaintenance dredge projects in the San Francisco BayRegion consistent with the adopted LTMS (LongTerm Management Strategy for the Placement ofDredged Material in the San Francisco Bay Region)EIR/EIS and LTMS Management Plan of 2001.
Project Impacts: The detrimental effects onerosion/sedimentation rates, substrate, water quality,fish habitat, air quality, and noise are all expected tobe minor and short term. No permanent negativeeffects such as undesired substrate alteration,decreased water quality, loss of fish habitat, decreaseair quality, and noise pollution are anticipated. Thebeneficial effects on economics, employment, safetyand navigation, and of the removal of contaminants,are major and long term.
Proposed Mitigation: The proposed dredgingwould not result in a permanent loss of waters of theUnited States. Temporary impacts to aquatic resourceswould be mitigated by proposed minimization andavoidance measures, including conducting work onlywithin the permitted environmental work windows.Therefore, no compensatory mitigation is proposed or
required.
3. STATE AND LOCAL APPROVALS:
Water Quality Certification: State water qualitycertification or a waiver is a prerequisite for theissuance of a Department of the Army Permit toconduct any activity which may result in a fill orpollutant discharge into waters of the United States,pursuant to Section 401 of the Clean Water Act of1972, as amended (33 U.S.C. § 1341 et seq.). Theapplicant has recently submitted an application to theCalifornia Regional Water Quality Control Board(RWQCB) to obtain water quality certification for theproject. No Department of the Army Permit will beissued until the applicant obtains the requiredcertification or a waiver of certification. A waiver canbe explicit, or it may be presumed if the RWQCB failsor refuses to act on a complete application for water
quality certification within 60 days of receipt, unlessthe District Engineer determines a shorter or longerperiod is a reasonable time for the RWQCB to act.
Water quality issues should be directed to theExecutive Officer, California Regional Water QualityControl Board, San Francisco Bay Region, 1515 ClayStreet, Suite 1400, Oakland, California 94612 by theclose of the comment period.
Coastal Zone Management: Section 307(c) ofthe Coastal Zone Management Act of 1972, asamended (16 U.S.C. § 1456(c) et seq.), requires anapplicant seeking a federal license or permit toconduct any activity occurring in or affecting thecoastal zone to obtain a Consistency Certification thatindicates the activity conforms with the state’s coastalzone management program. Generally, no federallicense or permit will be granted until the appropriatestate agency has issued a Consistency Certification orhas waived its right to do so.
Coastal zone management issues should bedirected to the Executive Director, San Francisco BayConservation and Development Commission, 375Beale Street, Suite 510, San Francisco, California94105, by the close of the comment period.
4. COMPLIANCE WITH VARIOUS FEDERALLAWS:
National Environmental Policy Act (NEPA):Upon review of the Department of the Army Permitapplication and other supporting documentation, theCorps has made a preliminary determination that theproject neither qualifies for a Categorical Exclusionnor requires the preparation of an EnvironmentalImpact Statement for the purposes of NEPA. At theconclusion of the public comment period, the Corpswill assess the environmental impacts of the project inaccordance with the requirements of the NationalEnvironmental Policy Act of 1969 (42 U.S.C. §§
4321-4347), the Council on Environmental Quality'sRegulations at 40 C.F.R. Parts 1500-1508, and theCorps Regulations at 33 C.F.R. Part 325. The finalNEPA analysis will normally address the direct,indirect, and cumulative impacts that result fromregulated activities within the jurisdiction of the Corpsand other non-regulated activities the Corpsdetermines to be within its purview of federal controland responsibility to justify an expanded scope ofanalysis for NEPA purposes. The final NEPA analysiswill be incorporated in the decision documentation
that provides the rationale for issuing or denying aDepartment of the Army Permit for the project. Thefinal NEPA analysis and supporting documentationwill be on file with the San Francisco District,Regulatory Division.
Endangered Species Act (ESA): Section 7(a)(2)of the ESA of 1973, as amended (16 U.S.C. § 1531 etseq.), requires federal agencies to consult with eitherthe U.S. Fish and Wildlife Service (USFWS) or theNational Marine Fisheries Service (NMFS) to ensureactions authorized, funded, or undertaken by theagency are not likely to jeopardize the continuedexistence of any federally-listed species or result in theadverse modification of designated critical habitat.Based on this review, the Corps has made apreliminary determination that the following
federally-listed species and designated critical habitatare present at the project location or in its vicinity, andmay be affected by project implementation.
Sacramento River winter-run Chinook salmon(Oncorhynchus tshawytscha) were federally-listed asendangered on January 4, 1994 (59 Fed. Reg.442).Adult winter-run Chinook salmonmigrate through SanFrancisco Bay, as well as Suisun Bay and Honker Bay,to spawning areas in the upper Sacramento River duringthe late fall and early winter. Juveniles travel
downstream through San Francisco Bay to the PacificOcean in the late fall as well. The movements of adultand juvenile salmon through the Bay system are thoughtto be rapid during these migrations. Since impacts to thewater column during disposal events would be short-term,localized and minor in magnitude, no potentiallyadverse effects to winter-run Chinook salmon that maybe near the disposal site are anticipated, if the dredgework is conducted from June 1 through November 30.
Central Valley Spring-Run ESU Chinook salmon(Oncorhynchus tshawytscha) were listed as threatenedon September 16, 1999 (64 FR 50394). Spring-runChinook salmon typically migrate upstream throughSan Francisco Bay to spawning areas between Marchand July. Spawning usually occurs between late-August and early October with a peak in September.Juveniles travel downstream through San Francisco Bayin late fall to spring and then to the Pacific Ocean oncethey have undergone smoltification. Since impacts tothe water column during disposal events would be short-term,localized and minor in magnitude, no potentiallyadverse effects to spring-run Chinook salmon that maybe near the disposal site are anticipated, if the dredgework is conducted from June 1 through November 30.
Central California populations of steelhead trout(Oncorhynchus mykiss) were federally classified asthreatened in August 1997. The steelhead that occur inSan Francisco Bay are included in this distinctpopulation segment and therefore receive protectionunder the Endangered Species Act. There is concern thatsteelhead migrating through the Bay to streams in theNorth Bay might enter San Francisco Bay and MartinezMarina. If a permit is issued for this proposed project itwill contain a condition that dredging is allowed onlyfrom June 1 through November 30 in any year, withoutconsultation (pursuant to Section 7 of the ESA) with andapproval from NMFS and the Corps.
The Central Valley California Distinct PopulationSegment (DPS) steelhead (Oncorhynchus mykiss) wasfederally-listed as threatened on March 19, 1998 (63FR 13347), and were reconfirmed as threatened onJanuary 5, 2006 (71 FR 834). Critical habitat forcentral valley California steelhead was designated onSeptember 2, 2005 (70 FR 52488). The DPS includesall naturally spawned populations of steelhead (andtheir progeny) in the Sacramento and San JoaquinRivers and their tributaries. Excluded are steelheadfrom San Francisco and San Pablo Bays and theirtributaries. All Central Valley steelhead are currentlyconsidered winter steelhead. Juvenile steelheads livein freshwater between one and four years, then becomesmolts and migrate to the sea from November throughMay. To protect the Central Valley steelhead,dredging shall only occur from June 1 throughNovember 30.
The North American green sturgeon (Acipensermedirosrtis) was listed as threatened under the Endangered Species Act on July 6, 2006 (71 Fed.Reg. 17757). Critical habitat for the North American green sturgeon southern DPS includes theSacramento River, lower Feather River, lower Yuba River, Sacramento- San Joaquin Delta, Suisun Bay,San Pablo Bay, and San Francisco Bay in California and was designated on October 9, 2009 (74 FR52300). The southern DPS consists of populations originating from coastal watersheds south of theEel River with spawning confirmed in the Sacramento Riversystem. Adult green sturgeon must travelthrough the San Francisco Estuary to pass between the ocean and the Upper Sacramento River Basinspawning area. Additionally, the San Francisco Estuary provides important rearing and holdingareas for juvenile and sub-adult green sturgeon.
If a permit is issued for this proposed project it will contain a condition that dredging isallowed only from June 1 through November 30. Dredging outside this environmental work window
would require consultation with the National Marine Fisheries Service (NMFS) (pursuant to Section 7 of the Endangered Species Act) and approval from the NMFS and the Corps.
Magnuson-Stevens Fishery Conservation and Management Act (MSFCMA): Section 305(b)(2) of the MSFCMAof 1966, as amended (16 U.S.C. § 1801 et seq.), requires federal agencies to consult with theNational Marine Fisheries Service (NMFS) on all proposed actions authorized, funded, or undertakenby the agency that may adversely affect essential fish habitat (EFH). EFH is defined as thosewaters and substrate necessary to fish for spawning, breeding, feeding, or growth to maturity. EFHis designated only for those species managed under a Federal Fisheries Management Plan (FMP), suchas the Pacific Groundfish FMP, the Coastal Pelagics FMP, and the Pacific Coast Salmon FMP. As thefederal lead agency for this project, the Corps has conducted a review of digital maps prepared byNMFS depicting EFH to determine the presence or absence of EFH in the project area. Based on thisreview, the Corps has madea preliminary determination that EFH is present at theproject location or in its vicinity, and that the criticalelements of EFH may be adversely affected by project implementation. The proposed project islocated within an area managed under the Pacific Groundfish, the Coastal Pelagic and/or the PacificCoast Salmon FMPs.
The Corps and NMFS completed a programmatic EFH consultation on June 9, 2011 for maintenancedredging. One of NMFS’s key concerns with dredging is potential impacts to eelgrass beds. The“Baywide Eelgrass Inventory of San Francisco Bay,” prepared by Merkel and Associates, dated October2004, does not show the area in and around Martinez Marina as having any eelgrass beds. Therefore,eelgrass is not expected to be established in this area and the Corps does not anticipate that theproposed dredging would affect eelgrass. Therefore, eelgrass minimization measures are notrequired.
National Historic Preservation Act (NHPA): Section 106 of the NHPA of 1966, as amended (16 U.S.C. §470 et seq.), requires federal agencies to consult with the appropriate State HistoricPreservation Officer to take into account the effects of their undertakings on historic propertieslisted in or eligible for listing in the National Register of Historic Places. Section 106 of theNHPA further requires federal agencies to consult with the appropriate Tribal Historic PreservationOfficer or any Indian tribe to take into account the effects of their undertakings on historicproperties, including traditional cultural properties, trust resources, and sacred sites, towhich Indian tribes attach historic, religious, and cultural significance.
Because the Martinez Marina has been previously dredged, historic or archeological resources arenot expected to occur in the project vicinity. If unrecorded archaeological resources are
discovered during project implementation, those operations affecting such resources will betemporarily suspended until the Corps concludes Section 106 consultation with the State HistoricPreservation Officer or the Tribal Historic Preservation Officer to take into account anyproject related impacts to those resources.
5. COMPLIANCE WITH THE SECTION404(b)(1) GUIDELINES: Projects resulting indischarges of dredged or fill material into waters of theUnited States must comply with the Guidelines
promulgated by the Administrator of theEnvironmental Protection Agency under Section404(b) of the Clean Water Act (33 U.S.C. § 1344(b)).An evaluation pursuant to the Guidelines indicates thedisposal of dredged material is not dependent onlocation in or proximity to waters of the United Statesto achieve the basic project purpose. This conclusionraises the (rebuttable) presumption of the availabilityof a less environmentally damaging practicablealternative to the project that does not require thedischarge of dredged or fill material into waters of theU.S.
6. PUBLIC INTEREST EVALUTION: Thedecision on whether to issue a Department of the ArmyPermit will be based on an evaluation of the probableimpacts, including cumulative impacts, of the projectand its intended use on the public interest. Evaluationof the probable impacts requires a careful weighing ofthe public interest factors relevant in each particularcase. The benefits that may accrue from the projectmust be balanced against any reasonably foreseeabledetriments of project implementation. The decision onpermit issuance will, therefore, reflect the nationalconcern for both protection and utilization ofimportant resources. Public interest factors whichmay be relevant to the decision process includeconservation, economics, aesthetics, generalenvironmental concerns, wetlands, cultural values,fish and wildlife values, flood hazards, floodplainvalues, land use, navigation, shore erosion andaccretion, recreation, water supply and conservation,water quality, energy needs, safety, food and fiberproduction, mineral needs, considerations of propertyownership, and, in general, the needs and welfare of
the people.
7. CONSIDERATION OF COMMENTS: TheCorps is soliciting comments from the public; federal,state and local agencies and officials; Native AmericanNations or other tribal governments; and otherinterested parties in order to consider and evaluate theimpacts of the project. All comments received by theCorps will be considered in the decision on whether toissue, modify, condition, or deny a Department of theArmy Permit for the project. To make this decision,comments are used to assess impacts on endangeredspecies, historic properties, water quality, and otherenvironmental or public interest factors addressed in afinal environmental assessment or environmentalimpact statement. Comments are also used todetermine the need for a public hearing and todetermine the overall public interest of the project.
8. SUBMITTING COMMENTS: During thespecified comment period, interested parties maysubmit written comments to Melissa France, SanFrancisco District, Operations and Readiness
Division, 450 Golden Gate Avenue, 4th Floor, Room1111, San Francisco, California 94102-3404;comment letters should cite the project name,applicant name, and public notice number to facilitatereview by the Permit Manager. Comments mayinclude a request for a public hearing on the projectprior to a determination on the Department of theArmy permit application; such requests shall state,with particularity, the reasons for holding a publichearing. All substantive comments will be forwardedto the applicant for resolution or rebuttal. Additionalproject information or details on any subsequentproject modifications of a minor nature may beobtained from the applicant and/or agent, or bycontacting the Permit Manager by telephone or e-mailcited in the public notice letterhead. An electronicversion of this public notice may be viewed under theCurrent Public Notices tab on the US Army Corps ofEngineers, San Francisco District website:http://www.spn.usace.army.mil/Missions/Regulatory.