Please address comments to: Nashville District Corps of Engineers, Regulatory Division (Attn: Katie Alston), 3701 Bell Road, Nashville, TN 37214-2660; katherine.c.alston@usace.army.mil; (615) 369-7521
SUBJECT: Proposed discharge of fill material into waters of the United States associated with construction of Westhaven Subdivision-Residential Additions, located in Franklin, Williamson County, Tennessee. This additional Public Notice is being provided because the project has been modified and impacts have significantly increased since the July 2021 Public Notice (PN 21-21).
TO ALL CONCERNED: The application described below has been submitted for aDepartment of the Army (DA) Permit pursuant to Section 404 of the Clean Water Act(CWA) (33 U.S.C. 1344).
APPLICANT: Wes Magill
Southern Land Company
3990 Hillsboro Pike, Suite 400
Nashville, TN 37215
LOCATION: The proposed project comprises approximately 60 acres located on 3 parcels within the Westhaven Community in Franklin, Williamson County, TN (Exhibit 1). The wetlands and streams on the subject site are located within the Harpeth River Watershed (HUC 05130204). The center coordinates for the residential development are Latitude N. 36.917878°, W.-86.924471°. The project site can be found on the U.S. Geological Survey (USGS) Leipers Fork, TN 7.5 Minute quadrangle map.
DESCRIPTION: The applicant proposes to construct a residential addition to the Westhaven Subdivision, consisting of approximately 184 units, and to expand Boyd Mill Pike to meet City of Franklin’s road safety requirements. The addition shown in Exhibit 2 is a conceptual drawing of the final stage of Westhaven Master Plan, as approved by the City of Franklin. The proposed discharge of fill material within five tributaries to the West Harpeth River, three wetlands, and one open-water pond associated with Boyd Mill Pike expansion (Exhibit 3-5), roadway crossings (Exhibits 6-8), and grading (Exhibit 6) to build out the community to the south and west is summarized in the table below.
Impact and Mitigation Requirement
Aquatic Resource
Impact (Linear Foot or Acre)
Impact Type
Proposed Compensatory Mitigation
Main UT Harpeth River Crossing 1
155 LF
Road crossing (culvert & wing walls)
Yes
≤ 50 LF
Rip Rap (upstream and downstream)
Yes
≤ 50 LF
Rip Rap outside of wingwalls (if required)
NA
Main UT Harpeth River Crossing 2
125 LF
Road crossing (culvert & wing walls)
Yes
≤ 50 LF
Rip Rap (upstream & downstream)
Yes
≤ 50 LF
Rip Rap outside of wingwalls (if required)
NA
S80 - INT
34 LF
Road expansion (culvert & wing walls)
Yes
25 LF
Rip-rap (downstream only)
Yes
S1 – INT
9.8 LF
Culvert length modification
Yes
S40B - EPH
856 LF
filled for grading
Yes
S44B - EPH
864 LF
filled for grading
Yes
Wetland W4
0.18 acre
filled for grading
Yes
Pond 4
0.18 acre
filled for grading
Yes
Wetland W2
0.26 acre
filled for grading
Yes
Wetland W3
0.45 acre
filled for grading
Yes
Totals
448.8 LF of intermittent streams, 1720 LF of ephemeral streams, and 1.07 acres of wetlands/ponds
Other actions proposed by the applicant include impacts to intermittent stream feature S80 associated with in-kind replacement of two culvert crossings and a span bridge for pedestrians (Exhibit 3-5) and temporary impacts to intermittent stream feature S1 (Exhibits 9-10) associated with utility line installation. These would not result in additional permanent impacts to waters of the United States; therefore, compensatory mitigation is not proposed. Plans of the proposed work are attached to this notice. If you wish to view additional plans, please contact this office or visit our web site at:http://www.lrn.usace.army.mil/Media/PublicNotices.aspx.
PURPOSE AND NEED: The proposed residential construction within the existing Westhaven Community to meet the continued growing demand for housing located in Franklin, Williamson Tennessee and the proposed road expansion would meet City of Franklin road safety requirements.
AVOIDANCE AND MINIMIZATION OF IMPACTS TO WATERS OF THE U.S.: The applicant’s Alternatives Analysis for the project included review of no action, onsite design, and off-site design alternatives. The analysis of off-site alternatives found adjacent parcels are either not zoned for residential development or are not currently available for purchase. Onsite design alternatives considered impacts to endangered species and their habitat, wetlands, and streams. Erosion Prevention and Sediment Control measurements will be submitted with the complete design plans.
COMPENSATORY MITIGATION: The applicant proposes to provide compensatory mitigation by purchasing stream credits from Setters Ridge Mitigation Bank (located in Williamson County) and Harpeth River Mitigation Bank (located in Rutherford County) and purchasing wetland credits in the Lower Cumberland Service Area of the Tennessee Mitigation Fund Wetland In-Lieu Fee Program.
PUBLIC INTEREST REVIEW/CUMULATIVE EFFECTS: The decision whether to issue a permit will be based on an evaluation of the probable impacts including cumulative impacts of the activity on the public interest. That decision will reflect the national concern for both
protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the work, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the work, will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people.
SOLICITATION OF COMMENTS: USACE is soliciting comments from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. The Corps, Regulatory Division, will consider any comments received prior to a final decision concerning the authorization of the project, i.e., the issuance, modification, or denial of the requested DA permit. To make this decision, comments are used to assess impacts on endangered species, historical properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment (EA) and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
HISTORIC AND CULTURAL RESOURCES: Since the July 2021 Public Notice, the applicant has conducted Phase I and Phase II Archaeological Surveys of the proposed development area, and the USACE will be requesting a Phase III. The survey must meet guidelines and standards set forth by the Tennessee Department of Archaeology (https://www.tn.gov/content/dam/tn/environment/archaeology/documents/arch_TNSHPO_2018b.pdf).
ENDANGERED/THREATENED SPECIES REVIEW: A review of the United States Fish and Wildlife Service (USFWS) website, http://ecos.fws.gov/ipac identified the following federally-listed species that are known to or believed to occur in the vicinity of the proposed project (Table 3):
Table 3. Potential Endangered and Threatened Species in the Proposed Project
Group
Common Name/ Scientific Name
Federal Status
Mammal
Gray bat /Myotis grisescens
Endangered
Mammal
Indiana bat / Myotis sodalis
Endangered
Mammal
Northern Long-eared Bat / Myotis septentrionalis
Threatened
Plants
Price’s Potato-bean / (Apios priceana)
Endangered
Plants
Leafy prairie-clover / Dalea foliosa
Endangered
A copy of this notice is being furnished to USFWS for their review. After receipt of any comments, the USACE will evaluate the potential effects to proposed and/or listed species and their designated critical habitat, and initiate consultation with the U.S. Fish & Wildlife Service, if required.
OTHER APPROVALS: In addition to the DA permit reissuance, other federal, state, and/or local approvals may be required for the proposed work, including but not limited to:
Before a permit can be issued, water quality certification must be provided by the State of Tennessee Department of the Environment and Conservation, pursuant to Section 401(a)(1) of the CWA (33 U.S.C. 1341), that applicable water quality standards will not be violated.
Other federal, state, and/or local approvals that may be required for the activity.
COMMENT PERIOD: Written statements received in this office by February 26, 2023 (30 days) will become a part of the record and will be considered in the determination. Any response to this notice should be directed to the Nashville District Corps of Engineers, Regulatory Division, Attention: Ms. Katie Alston at the above address, by phone: 615-369-7500, or by email: katherine.c.alston@usace.army.mil.
\s\
William E. Worrall, P.E.
Chief, Technical Services Branch
Regulatory Division
U.S. Army Corps of Engineers
Nashville District