Summary: Today the U.S. Army Corps of Engineers (Corps) would like to announce that we have approved the permit request by Huntington Marine Services, Inc. (HMS) to construct and operate a barge fleeting facility along the left descending bank of the Ohio River between river miles 312.5 and 313.3, near the Westmoreland area of Huntington, Wayne County, West Virginia.
Notice of Permit Authorization
Subject: Corps Approves Barge Fleeting Facility Permit
Today the u.s. Army Corps of Engineers (Corps) would like to announce that we have approved the permit request by Huntington Marine Services, Inc. (HMS) to construct and operate a barge fleeting facility along the left descending bank of the Ohio River between river miles 312.5 and 313.3, near the Westmoreland area of Huntington, Wayne County, West Virginia.
History: HMS previously submitted two applications to the Corps proposing a barge fleeting facility at this location which were described in prior public notices issued by this office: Public Notice (PN) No. 199600803-1 and PN No. 199600803-2. PN No. 199600803-1 was issued on July 27, 2001 and PN No. 199600803-2 was issued on July 14, 2005. These two initial applications proposed a maximum fleeting capacity of 200-barges and both applications were withdrawn. On May 10, 2010, this office received an application from HMS proposing a 135- barge capacity fleeting facility at this location which was also withdrawn. HMS submitted a revised application on April 26, 2011 and PN No. LRH-201 0-465-0HR was issued on June 13, 2011 .
The HMS application, received in this office on April 26, 2011 , proposed the construction and operation of a 90-barge capacity fleeting facility along the left descending bank of Ohio River between river miles 312.5 and 313.3. Barges were proposed to be moored in three clusters, each of which would be 6-barges wide by 5-barges long. However, HMS revised their proposal to avoid any potential adverse impacts to a nearby combined sewer overflow (CSO), a sewage treatment plant outfall and future sewage plant upgrades.
The applicant's modified proposal includes the construction and operation of a maximum 72-barge capacity fleeting facility at this location. Implementation of the proposal will include the installation of six deadman anchors above the ordinary high water elevation. Nine mooring floats, attached to the deadmen anchors and parked barges, will be utilized to secure the proposed fleeting configuration. The deadmen anchors will be installed by mechanized equipment operated from land (or alternatively by floating plant).
The proposed fleeting area will be of sufficient size to accommodate 72 (35 feet by 195 feet-sized) barges. Barges will be moored in three fleets. Two fleets will be 6-barges wide by 5-barges long and one fleet will be 6-barges wide by 2-barges long. A variety of barge sizes may be moored at the proposed facility; however any arrangement will not exceed a proposed 260 feet (riverward) x 2,840 feet (parallel to shoreline) mooring area. In addition, no barges will be moored within buffer areas which extend 325 feet upstream of the sewage treatment plan outfall and 300 feet downstream of the CSO. No initial or maintenance dredging has been proposed. Likewise, this proposal does not include any unloading, dock facilities, topside cleaning or barge maintenance/repair activities.
The facility is designed to provide sufficient staging area and water depth for safe and efficient barge fleeting operations. This additional barge fleeting will accommodate the capacity for current harbor services including receiving, fleeting, staging and configuring tows.
The decision to issue a permit is based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity in consideration of the public interest. Evaluation of the probable impacts which the activity may have on the public interest requires a careful weighing of many factors which may include: conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.
The benefits which reasonably may be expected to accrue from any proposal must be balanced against its reasonably foreseeable detriments. The decision to approve this permit, and the conditions under which it will be allowed to occur, was determined by the outcome of this general balancing process. That decision reflects the national concern for both protection and utilization of important resources.
The Corps is neither a proponent nor opponent of any permit proposal. In accordance with 33 Code of Federal Regulation 320.4, "a permit will be granted unless the district engineer determines that it would be contrary to the public interest". Authorization by the Corps neither conveys property rights nor does it authorize any injury to property or invasion of other rights.
For more information, contact the Huntington District public affairs office at 304-399-5353 or visit our website: www.lrh.usace.army.mil.
Ginger Mullins, Chief
Regulatory Division