Summary: The proposed project is located within unnamed tributaries to Stillwater Creek

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

Summary: The proposed project is located within unnamed tributaries to Stillwater Creek, approximately one mile southwest of Morristown, Ohio, Union Township, Belmont County, Ohio. The applicant proposes to discharge approximately 1,270 cubic yards of fill material into 1,942 linear feet (If) of seven jurisdictional streams and one jurisdictional wetland for the purpose of extracting coal from the #9 Meigs and #11 Waynesburg coal seams.

PUBLIC NOTICE: The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It is also to solicit your comments and information to better enable us to make a reasonable decision on factors affecting the public interest. We hope you will participate in this process. REGULATORY PROGRAM: Since its early history, the United States Army Corps of Engineers (USACE) has played an important role in the development of the nation's water resources. Originally, this involved construction of harbor fortifications and coastal defenses. Later duties included the improvement of waterways to provide avenues of commerce. An important part of our mission today is the protection of the nation's waterways through the administration of the USACE Regulatory Program. The USACE is directed by Congress under Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) to regulate all work or structures in or affecting the course, condition or capacity of navigable waters of the United States (U.S.). The intent of this law is to protect the navigable capacity of waters important to interstate commerce. The USACE is directed by Congress under Section 404 of the Clean Water Act (33 USC 1344) to regulate the discharge of dredged and fill material into all waters of the U.S., including wetlands. The intent of the law is to protect the nation's waters from the indiscriminate discharge of material capable of causing pollution and to restore and maintain their chemical, physical and biological integrity. TO WHOM IT MAY CONCERN: The following application has been submitted as a request for a USACE Permit, under the provisions of Section 404 of the Clean Water Act, for the proposed discharge offill material in waters of the U.S. The proposed discharge is in conjunction with the construction, operation and reclamation of the Shugert South Area Surface Mine, currently being reviewed by the Ohio Department of Natural Resources, Division of Minerals Resource Management (ODNR-DMRM) under surface mining application 10481 pursuant to the Surface Mining Control and Reclamation Act of 1977 (SMCRA). APPLICANT: Oxford Mining Company, LLC., 544 Chestnut Street, Coshocton, Ohio 43812 LOCATION: The proposed project is located within unnamed tributaries to Stillwater Creek, on Wilson Road (Township Highway 260) approximately one mile southwest of Morristown, Ohio, within Sections 25, 26, and 32, Township 8 North, Range 5 West, Union Township, Belmont County, Ohio. Latitude 40.05503, Longitude -81.0958.

DESCRIPTION OF THE PROPOSED WORK:

LOCATION: The proposed project is located within unnamed tributaries to Stillwater Creek, on Wilson Road (Township Highway 260) approximately one mile southwest of Morristown, Ohio, within Sections 25, 26, and 32, Township 8 North, Range 5 West, Union Township, Belmont County, Ohio. Latitude 40.05503, Longitude -81.0958. The applicant proposes to discharge approximately 1,270 cubic yards of fill material into 1,942 linear feet (If) of seven jurisdictional streams and one jurisdictional wetland for the purpose of extracting coal from the #9 Meigs and #11 Waynesburg coal seams. The applicant proposes direct permanent impacts to 989 If of stream for coal extraction and direct temporary impacts to 953 If of stream for pond construction. Stream Impacts are identified in the attached Stream Impact/ Avoidance Summary Table. The applicant proposes direct permanent impacts to one 0.72 acre jurisdictional wetland for coal extraction. Wetland Impacts are identified in the attached Wetlands Impact/Avoidance Summary Table. In addition, 2,728 If of stream would be indirectly impacted due to waste transport (sediment transport) from the toe of fills to sediment ponds. ALTERNATIVES ANALYSIS: This project is not water dependent; therefore, the applicant is required to show that other less damaging practicable alternatives, which do not require placing fill material into waters of the U.S., are not available. No permit will be issued unless the alternatives analysis clearly demonstrates that practicable upland alternatives are not available to achieve the overall project purpose. The applicant addressed three alternatives, the preferred, minimal degradation and non degradation alternative. Under the applicant's preferred alternative a total of 0.72 acre of one wetland and 4,670 If of seven streams would be impacted as described above under description of proposed work. The applicant's minimal degradation alternative would result in impacts to 1,240 If of five jurisdictional streams (131 If direct impact and 1,109 indirect impacts). No wetland impacts would occur under the minimal degradation alternative. Stream impacts for the minimal degradation alternative are identified on the attached Stream/Impact Avoidance Summary Table. The applicant's non-degradation alternative would not include impacts to jurisdictional streams or wetlands. The applicant's alternatives analysis is under review.

AVOIDANCE & MINIMIZATION: The applicant reduced the original permit area from 380.3 acres to 265.6 acres. Jurisdictional waters within the permit area total 11,242 If of thirteen streams (5,105 If perennial, 6,136 If intermittent, and 251 If ephemeral) and 6.33 acres of five wetlands. The applicant has proposed to avoid 6,572 If of stream and 5.61 acres of wetlands within the permit area. The applicant reduced the original permit area from 380.3 acres to 265.6 acres. Jurisdictional waters within the permit area total 11,242 If of thirteen streams (5,105 If perennial, 6,136 If intermittent, and 251 If ephemeral) and 6.33 acres of five wetlands. The applicant has proposed to avoid 6,572 If of stream and 5.61 acres of wetlands within the permit area. COMPENSATORY MITIGATION PLAN (CMP): The applicant has proposed on site, in kind mitigation to compensate for unavoidable impacts to jurisdictional streams and wetlands associated with the proposed project. The applicant proposes to reconstruct/restore perennial and intermittent streams at their pre-mining locations. Proposed stream mitigation lengths are identified on the attached Table 3-Gain-Loss Summaries. The applicant proposes to mitigate for 112 If of permanent and 139 If of temporary impacts to ephemeral Stream 36 through the construction of additional wetland mitigation. The applicant proposes to mitigate for impacts to 0.72 acre of wetland through the construction of a 1.2 acre mitigation wetland at the location of temporary Pond #002. Wetland mitigation is identified in the attached Table 3-Gain-Loss Summaries. The applicant has proposed a protective covenant be placed on mitigation areas toprovide long term protection. This proposed CMP is open to comment and is subject to change based on comments received. After review of all submitted information, the USACE will make a determination of appropriate mitigation, in the event a decision is made to issue a permit to the applicant. (CMP): The applicant has proposed on site, in kind mitigation to compensate for unavoidable impacts to jurisdictional streams and wetlands associated with the proposed project. The applicant proposes to reconstruct/restore perennial and intermittent streams at their pre-mining locations. Proposed stream mitigation lengths are identified on the attached Table 3-Gain-Loss Summaries. The applicant proposes to mitigate for 112 If of permanent and 139 If of temporary impacts to ephemeral Stream 36 through the construction of additional wetland mitigation. The applicant proposes to mitigate for impacts to 0.72 acre of wetland through the construction of a 1.2 acre mitigation wetland at the location of temporary Pond #002. Wetland mitigation is identified in the attached Table 3-Gain-Loss Summaries. The applicant has proposed a protective covenant be placed on mitigation areas toprovide long term protection. This proposed CMP is open to comment and is subject to change based on comments received. After review of all submitted information, the USACE will make a determination of appropriate mitigation, in the event a decision is made to issue a permit to the applicant. HISTORIC AND CULTURAL RESOURCES: This project must be reviewed to determine any potential effects to properties that may be eligible for or listed in the National Register of Historic Places (NRHP), in accordance with Section 106 of the National Historic Preservation Act. The applicant conducted a Phase I Archaeological Survey in April 2011. No significant findings were observed on site. The Corps has made a preliminary no effect determination for the proposed project. This public notice will serve as coordination with the State Historic Preservation Office (SHPO) concerning any additional information they may have on the project's potential impacts on historic properties listed on or eligible for listing on the NRHP. ENDANGERED/THREATENED SPECIES REVIEW (Per Section 7 of the Endangered Species Act): The proposed project lies within the natural range of the federally listed endangered Indiana bat (Myotis sodalis). The applicant conducted a mist net survey of the project area on June 15, 16, and 17, 2010. The report was coordinated with the U.S. Fish and Wildlife service on August 19, 2010. The Corps has made a preliminary no effect determination for the proposed project regarding the Indiana bat. This public notice serves as coordination with the U.S. Fish and Wildlife Service (Service) concerning federally listed threatened or endangered species. If the Service believes any potential effects to federally listed species would be attributable to the Huntington District's proposed permitting action, it is requested the Service provide any additional information pursuant to Section 7 consultation. WATER QUALITY CERTIFICATION: An individual Section 401 Water Quality Certification (WQC) is required for this activity. It is the applicant's responsibility to obtain certification from the Ohio Environmental Protection Agency. PUBLIC INTEREST REVIEW AND CUMULATIVE EFFECTS: This application will be reviewed in accordance with 33 CFR 320-332, the Regulatory Program of the USACE, and other pertinent laws, regulations, and executive orders. Our evaluation will also follow guidelines published by the U.S. Environmental Protection Agency pursuant to Section 404(b)(1) ofthe CWA. The decision whether to issue a permit will be based on an evaluation of the probable impacts including cumulative impacts ofthe proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit that reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors that may be relevant to the proposal will be considered including the cumulative effects thereof; of those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare ofthe people.

SOLICITATION OF COMMENTS: The USACE is soliciting comments from the public; Federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts ofthis proposed activity. Interested parties are invited to state any objections they may have to the proposed work. For accuracy and completeness of theadministrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding ofthe reasons for support or opposition. Any person who has an interest that may be adversely affected by the issuance of a permit may request a public hearing. The request must be submitted in writing to the District Engineer on or before the expiration date of this notice and must clearly set forth the interest which may be adversely affected and the manner in which the interest may be adversely affected by the activity. Any comments received will be considered by the USACE to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements on these factors received in this office on or before the expiration date of this public notice will become a part ofthe record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest. The USACE is soliciting comments from the public; Federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts ofthis proposed activity. Interested parties are invited to state any objections they may have to the proposed work. For accuracy and completeness of theadministrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding ofthe reasons for support or opposition. Any person who has an interest that may be adversely affected by the issuance of a permit may request a public hearing. The request must be submitted in writing to the District Engineer on or before the expiration date of this notice and must clearly set forth the interest which may be adversely affected and the manner in which the interest may be adversely affected by the activity. Any comments received will be considered by the USACE to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements on these factors received in this office on or before the expiration date of this public notice will become a part ofthe record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest. CLOSE OF COMMENT PERIOD: All comments pertaining to this Public Notice must reach this office on or before the close of the comment period listed on page one ofthis Public Notice. The applicant's application is currently under review, and is available for public review at Huntington District's, Dillon Lake Regulatory Field Office, by appointment Ifno comments are received by that date, it will be considered that there are no objections. Comments and requests for additional information should be submitted to Sheila Newman, Project Manager, Energy Resource Branch, CELRH-RD-E, U. S. Army Corps of Engineers Huntington District, 4969 Dillon Dam Road, Zanesville, Ohio 43055. Please note that names and addresses of those who submit comments in response to this public notice become part of our administrative record and, as such, are available to the public under provisions of the Freedom ofInformation Act. Thank you for your interest in our nation's water resources. If you have any questions concerning the above, please contact Sheila Newman of the Energy Resources Branch at 740-454-2225 ext. 5 . All comments pertaining to this Public Notice must reach this office on or before the close of the comment period listed on page one ofthis Public Notice. The applicant's application is currently under review, and is available for public review at Huntington District's, Dillon Lake Regulatory Field Office, by appointment Ifno comments are received by that date, it will be considered that there are no objections. Comments and requests for additional information should be submitted to Sheila Newman, Project Manager, Energy Resource Branch, CELRH-RD-E, U. S. Army Corps of Engineers Huntington District, 4969 Dillon Dam Road, Zanesville, Ohio 43055. Please note that names and addresses of those who submit comments in response to this public notice become part of our administrative record and, as such, are available to the public under provisions of the Freedom ofInformation Act. Thank you for your interest in our nation's water resources. If you have any questions concerning the above, please contact Sheila Newman of the Energy Resources Branch at 740-454-2225 ext. 5 . (0)

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas