The applicant proposes to discharge fill material into waters of the U.S. associated with the expansion of the existing Affinity Refuse Impoundment.

PUBLIC NOTICE: The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It is also to solicit your comments and information to better enable us to make a reasonable decision on factors affecting the public interest. We hope you will participate in this process.

TO WHOM IT MAY CONCERN: The following application has been submitted for a Department of the Army Permit under the provisions of Section 404 of the Clean Water Act for the proposed discharge of fill material into waters of the United States (U.S.). A copy of the application, including all supplemental materials (alternative analysis, compensatory mitigation plan, etc.), is available for review in the Huntington District Office, by appointment. The proposed discharge is in conjunction with the expansion of an existing coal refuse facility at the applicant’s Affinity Refuse Impoundment (O-73-82, IBR No. 3), which is currently being reviewed by the West Virginia Department of Environmental Protection (WVDEP) pursuant to the Surface Mining Control and Reclamation Act of 1977 (SMCRA).

APPLICANT:Pocahontas Coal Company, LLC 109 Appalachian Drive Beckley, West Virginia 25801

LOCATION: The proposed project is located approximately 0.7 miles southeast of Midway in the Town District of Raleigh County, West Virginia. Specifically, the proposed project area is situated at latitude 37° 42' 34” and longitude -81° 13' 41" on the Crab Orchard USGS 7.5 quadrangle. The proposed project would result in the discharge of dredged or fill material into an unnamed tributary of Soak Creek. Soak Creek is a tributary of Piney Creek of the New River, a traditional navigable water of the U.S. See project Location Map in Exhibit 1 and the Stream Delineation Map in Exhibit 2.

DESCRIPTION OF THE PROPOSED WORK: The applicant proposes to discharge fill material into waters of the U.S. associated with the expansion of the existing Affinity Refuse Impoundment. The required SMCRA Permit O-73-82, IBR No. 3 is currently under review by the WVDEP. The basic project purpose is to provide additional storage for coal refuse material generated at the adjacent preparation plant (O-135-83).

The proposed refuse facility expansion (38.61 acres) would result in the discharge of approximately 68 cubic yards of fill material into a total of 1,334 linear feet (lf), within Tributary B (unnamed tributary (UT) of Soak Creek of Piney Creek of the New River). As shown in Table 1, the above figure includes permanent discharge of fill material into 711 lf of intermittent stream channel and 378 lf of ephemeral stream channel for the refuse facility expansion, and temporary discharge of fill material into 245 lf of intermittent stream channel during construction and maintenance of one (1) sediment control structure. A preliminary jurisdictional determination was completed by this office, for the proposed project area, on May 5, 2010 (Exhibit 2). A reference cross-section of Tributary B can be found in Exhibit 3.

Table 1 Affinity Coal Refuse Facility Expansion Stream Impact Summary

Project Feature & Stream Name

Permanent Intermittent Impacts (lf)

Permanent Ephemeral Impacts (lf)

Temporary Intermittent Impacts (lf)

Refuse Facility Expansion Tributary B (UT of Soak Creek)

711

378

0

Sediment Control Structure (Pond RP-5) Tributary B (UT of Soak Creek)

0

0

245

SUBTOTAL

711

378

245

TOTAL

1,334

ALTERNATIVE ANALYSIS: This project is not considered to be water dependent; therefore, the applicant is required to show that other less damaging practicable alternatives, which do not require the placement of fill material into waters of the U.S., are not available that would achieve the overall project purpose. No permit will be issued until we have determined that the alternative analysis clearly demonstrates that upland alternatives are not available to achieve the overall project purpose.

The applicant evaluated a full range of alternatives that included: not expanding the coal refuse facility; combined coarse and fine fills; coarse fill with underground injections; slurry cells; and a variety of impounding facilities, including a side-hill fill, impounding embankment, incised pond and a fully-diked impoundment. Information submitted by the applicant indicates that, in order to provide additional storage for coal refuse material, expansion of the existing coal refuse facility and construction of one (1) sediment control structure into waters of the U.S., within the SMCRA permit area, is required. The applicant concluded through its analysis of alternatives that it is not practicable to expand the coal refuse facility without excavation and subsequent discharge of fill material into jurisdictional waters of the U.S. The results of their analysis indicated that a combination of a refuse/impoundment, as proposed, would decrease the overall acreage disturbance required and reduce impacts to waters of the U.S. from the discharge of fill material, and would, therefore, represent the least environmentally damaging practical alternative (LEDPA) to meet the overall project purpose, considering cost, logistics, existing technology and environmental considerations. The applicant’s alternative analysis is available for review in the Huntington District Office.

AVOIDANCE AND MINIMIZATION: The applicant has indicated that there is no practicable alternative for the proposed project that completely avoids the discharge of fill material into waters of the U.S. However, the applicant’s proposed alternative incorporates the following measures to minimize impacts to aquatic resources: utilizing an existing refuse facility; utilizing an area outside of waters of the U.S., in the northwest portion of the proposed project area, that would store 70 percent of the total coal refuse material generated; and locating the sediment control structure as close as practical to the impoundment area. Utilization and expansion of the existing coal refuse facility, rather than constructing a refuse facility on an undisturbed site, would avoid 500 lf of temporary impacts and 2,400 lf of permanent impacts to waters of the U.S. As a result of these avoidance and minimization measures, the proposed alternative would result in filling approximately 1,334 lf of waters of the U.S., and would allow facilities that contribute coal refuse material to extract approximately 1,500,000 tons of coal annually, for fifteen (15) years.

COMPENSATORY MITIGATION PLAN: The applicant explored the use of mitigation banks, the West Virginia In-Lieu Fee Program (WV ILF), permittee-responsible on-site and in-kind mitigation, and permittee-responsible off-site and out-of-kind mitigation to compensate for the permanent and temporal loss of jurisdictional stream channels and wetlands. Currently, there are no approved mitigation banks or WV ILF credits available within the Soak Creek watershed. Therefore, the applicant chooses to provide permittee-responsible stream restoration (re-establishment) for the temporarily filled reach on-site, and stream restoration (rehabilitation) of the adjacent Whitestick Creek watershed. Whitestick Creek flows into Piney Creek and into the New River. A Compensatory Mitigation Plan (CMP) has been prepared by the applicant and is available for review in the Huntington District Office.

The applicant has used the West Virginia Stream and Wetland Valuation Metric (WV SWVM) to evaluate whether the proposed mitigation would adequately offset the impacts associated with discharge of fill material into waters of the U.S. Table 2 summarizes the proposed stream mitigation, and Exhibits 4 and 5 provide the location of the specific mitigation reaches in relation to the proposed project. A description of each mitigation element is provided below.

Table 2 Affinity Refuse Impoundment Compensatory Mitigation Summary for Streams

Proposed Stream Mitigation

Length (feet)

Stream Re-establishment and Restoration of the UT of Soak Creek

245

Stream Rehabilitation within the Whitestick Creek watershed

1,050

TOTAL

1,295

On-Site Restoration (Re-establishment) of the UT of Soak Creek: The applicant proposes to restore 245 lf of stream, impacted by the sediment control structure, during the reclamation of the Affinity Refuse Impoundment project. Restoration of the UT of Soak Creek would include removal of the sediment control structure and reconstructing the stream by re-grading the channels based upon representative cross sections of the pre-mining pattern, profile, and dimensions, utilizing natural channel design techniques. A riparian corridor would be re-established with a mixture of native woody and herbaceous vegetative species. The applicant believes that the natural channel design techniques would promote sediment transport and ecological function by restoring the natural functions and habitat characteristics of the streams, resulting in an ecological lift to the watershed.

Stream Restoration (Rehabilitation – Level 1) Within the Whitestick Creek Watershed: To offset the permanent loss of jurisdictional stream resulting from the coal refuse facility expansion, the applicant proposes to rehabilitate 1,050 lf of a perennial tributary of Whitestick Creek. The stream has been completely enclosed by concrete culverts and covered to hide the presence of the drain. Proposed restoration activities would day-light the stream channel, allowing for rehabilitation. The stream would be restored to previous channel morphology, using the following techniques: bank stabilization from the installation of j-hooks, cross-vanes, random boulders and rock and wood structures; re-establishment of riparian buffer zones (on each bank); and proper width-to-depth ratios creating a proper flood plain and proper bankfulls. A 50-foot riparian corridor would be re-established on each side of the stream channel, with a mixture of native woody and herbaceous vegetative species. Restoration efforts within the UT of Whitestick Creek would provide an ecological lift within the watershed. The stream restoration efforts are proposed to be initiated prior to, or concurrent with, the proposed coal refuse facility expansion activities.

The proposed CMP is open for comment and is subject to change based on comments received. After review of all submitted information, the Corps will determine appropriate mitigation, in the event a decision is made to issue a permit.

WATER QUALITY CERTIFICATION: A Section 401 Water Quality Certification is required for this project. It is the applicant’s responsibility to obtain certification from the WVDEP.

HISTORIC AND CULTURAL RESOURCES: The proposed project was reviewed by the West Virginia State Historic Preservation Officer (SHPO) to determine if the project would result in impacts to archeological resources and/or architectural resources (properties) listed on or eligible for inclusion on the National Register of Historic Places (National Register). In a letter dated October 27, 2011,the SHPO stated there are no archaeological resources in the project area listed on or eligible for inclusion in the National Register; therefore, no further consultation is necessary with regard to archaeological resources. Additionally, the SHPO stated that no buildings, sites or structures, listed in or eligible for the National Register were located in the project’s Area of Potential Effect; therefore, no further consultation is necessary with regard to architectural resources.

Based on this information, the Corps has determined the proposal would have no effect on properties listed or eligible for listing in the National Register. This public notice serves as coordination with the SHPO, pursuant to Section 106 of the National Historic Preservation Act. If the SHPO has new information and believes that the Corps proposed permitting action may potentially affect properties listed or eligible for listing in the National Register, it is requested the SHPO provide such information.

ENDANGERED/THREATENED SPECIES REVIEW: Two federally listed endangered species, the Indiana bat (Myotis sodalis) and Virginia big-eared bat (Corynorhinus townsendii virginianus) may occur within the project area. The applicant retained the services of Compliance Monitoring Labs, Inc., to complete a survey to determine presence or probable absence of the Indiana bat (Myotis sodalis) within the proposed project area. Two (2) mist net survey sites were selected and surveyed between June 30, and July 1, 2011. No Indiana bats were captured during either survey. The survey report also indicates the project area was surveyed for abandoned mine portals that could support summer or winter colonies of the endangered Virginia big-eared bat (Corynorhinus townsendii virginianus) or provide hibernaculum for the Indiana bat (Myotis sodalis). No abandoned mine portals were found within the proposed project area.

The WVDEP reviewed the survey results and determined that the proposed surface mine project is not likely to adversely affect endangered or threatened bat species or their critical habitat. The validity of the survey results expire on June 1, 2012. Based on this information, the Corps has determined that the project as proposed is not likely to adversely affect the Indiana bat, Virginia big-eared bat or its designated critical habitat. This Public Notice serves as coordination with the United States Fish and Wildlife Service for any additional information they may have concerning the project’s potential effect on federally listed threatened and endangered species pursuant to Section 7 of the Endangered Species Act of 1972 (as Amended).

PUBLIC INTEREST REVIEW AND CUMMULATIVE EFFECTS: This application will be reviewed in accordance with 33 CFR 320‑332, the Regulatory Program of the Corps, and other pertinent laws, regulations, and executive orders. Our evaluation will also follow the guidelines published by the United States Environmental Protection Agency pursuant to Section 404(b)(1) of the CWA. The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit that reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors that may be relevant to the proposal will be considered including the cumulative effects thereof; of those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.

The project lies within the New River (050500040102) 12-digit hydrologic unit code watershed. The Corps is assessing the potential cumulative effects that the proposed stream impacts may have on public interest factors when considered with other activities in that watershed. The assessment includes use of the Corps analytic tool, Cumulative Effects Analysis Prototype for LRD Regulatory Districts. The tool uses available State and Federal data for each 12-digit hydrologic unit code watershed to analyze past and present activities that may currently be affecting streams.

SOLICITATION OF COMMENTS: The Corps is soliciting comments from the public; Federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. For accuracy and completeness of the administrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding of the reasons for support or opposition. Any person who has an interest that may be adversely affected by the issuance of a permit may request a public hearing. The request must be submitted in writing to the District Engineer on or before the expiration date of this notice and must clearly set forth the interest, which may be adversely affected, and the manner in which the interest may be adversely affected by the activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements on these factors received in this office on or before the expiration date of this public notice will become a part of the record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest.

CLOSE OF COMMENT PERIOD: All comments pertaining to this Public Notice must reach this office on or before the close of the comment period listed on page one of this Public Notice. If no comments are received by that date, it will be considered that there are no objections. Comments and requests for additional information should be submitted to:

U.S. Army Corps of Engineers ATTN: CELRH-RD-E Public Notice No. LRH-2010-240-NEW 502 Eight Street Huntington, West Virginia 25701-2070

Please note that names and addresses of those who submit comments in response to this public notice become part of our administrative record and, as such, are available to the public under provisions of the Freedom of Information Act. Thank you for your interest in our nation's water resources. If you have any questions concerning the above, please contact Samantha Dailey of the Energy Resource Branch at (304) 399-5610.

(W)

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas