The applicant proposes to discharge 929 cubic yards of fill material into 9

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

The applicant proposes to discharge 929 cubic yards of fill material into 9,844 linear feet of intermittent and ephemeral stream and 0.09 acre of wetland. Fill discharge would be required to accomplish coal extraction (mine through),construction of permanent and temporary dams for sediment ponds, haul road construction and rock channel protection.

PUBLIC NOTICE: The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It is also to solicit your comments and information to better enable us to make a reasonable decision on factors affecting the public interest. We hope you will participate in this process. The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It is also to solicit your comments and information to better enable us to make a reasonable decision on factors affecting the public interest. We hope you will participate in this process. TO WHOM IT MAY CONCERN: An application has been submitted to the Corps as a request for a permit, under the provisions of Section 404 of the Clean Water Act, for the proposed discharge of fill material into waters of the U.S., as described below. APPLICANT: B & N Coal, Inc. Post Office Box 100 Dexter City, Ohio 45771

LOCATION: The proposed project is located within unnamed tributaries and wetlands to the East Fork of Duck Creek (HUC 05030201 08) within the Little Muskingum-Middle Island watershed. The project is located at latitude 39.822503, longitude -81.384302, Sections 2, 3, 10 & 11, Township 7 North, Range 8 West, Marion Township, County, Ohio. Please see attached location map (Exhibit 1). DESCRIPTION OF THE PROPOSED WORK: The applicant proposes to discharge 929 cubic yards of fill material into 9,844 linear feet of intermittent and ephemeral stream and 0.09 acre of wetland. Fill discharge would be required to accomplish coal extraction (mine through), construction of permanent and temporary dams for sediment ponds, haul road construction and rock channel protection. Each discharge location and purpose is identified in Exhibit 2 (LRH- 2009-988-East Fork Duck Creek Proposed discharges of fill material into waters ofthe United States). In summary, three sediment control embankments would be constructed within streams St-1, St-10 and St-23 downstream of mine through operations to facilitate the mine's waste treatment system. These embankments would require direct fill discharge into 420 linear feet of intermittent stream and 34 linear feet of ephemeral stream. 1,4 70 If of streams St-1, St-1 0 and St 23 would be impounded in Ponds 004, 008, and 009 as part of the waste treatment system. Crossings for the haul road would be constructed through streams St-1, St-10, St-12, St-16, St-26 and St-38. Stream crossing construction would require discharge of fill material into 647lf of intermittent stream and 63 If of ephemeral stream. Rock protection would be required within streams St-1, St-10, St-12, St-16, St-23, St-26 and St-38 to prevent erosion. Rock protection placement would require direct fill discharge into 935 If of intermittent stream and 50 If of ephemeral stream. The remaining 7,695lfofstream (2,590 lfintermittent and 5,105lf ephemeral) and 0.09 acre oftwo wetlands (wetlands G and H) would be directly filled through excavation and backfill during coal extraction. Discharges would occur in conjunction with the Surface Mining Control and Reclamation Act permit D-2332-1 once approved by the Ohio Division ofNatural Resources, Division of Mineral Resources Management. Please see Exhibit 3 Sheets A through P for complete project plans and Exhibit 4 for pond construction plans. The applicant's Section 404 permit application (including the compensatory mitigation plan) is available for public review in the Corps' Regulatory office, by appointment. A copy of the application can also be obtained by written request under the Freedom of Information Act. ALTERNATIVES ANALYSIS: The applicant's stated overall project purpose is to develop and mine coal reserves in the Meigs Creek (No. 9) coal seam within the identified project area. This project is not water dependent; therefore, the applicant is required to show that other less damaging practicable alternatives, which do not require placing fill material into waters of the U.S., are available. The applicant's alternatives analysis is currently being reviewed. No permit will be issued unless the alternatives analysis clearly demonstrates that practicable upland alternatives are not available to achieve the overall project purpose. The applicant reviewed multiple mining methods for the proposed project to include underground mining, area mining, contour mining with three alternative highwall elevations, and a combination highwall/auger mining method. The applicant determined that contour mining was the preferred method with the final highwall elevation selected to provide both acceptable resource recovery rate and strip ratios. The applicant then constructed three alternatives (Alternative 1, Alternative 2, and Alternative 3) exploring how attendant facilities used to support the mining operation could be placed to avoid and minimize impacts to aquatic resources while still fulfilling the applicant's project purpose. Alternative 1 would result in the discharge of fill material into: 2,565 If of intermittent stream, 5,105 If of ephemeral stream, and 0.09 acre of wetland for mine through activities; 380 If of intermittent stream for pond dam construction; 64 7 If of intermittent stream and 63 If of ephemeral stream for haul road construction; and 875 If of intermittent stream and 20 If of ephemeral stream for rock channel protection. An additional 3, 730 If of intermittent stream and 250 If of ephemeral stream would be secondarily impacted by sediment transport and 1,440 If of intermittent stream and 0.09 acre of wetland would be impounded as part of the waste treatment system. Alternative 2 would result in the discharge of fill material into: 2,590 If of intermittent stream, 5,105 If of ephemeral stream, and 0.09 acre of wetland for mine through activities; 120 If of intermittent stream for pond dam construction; 275 If of intermittent stream for haul road construction; and 480 If of intermittent stream for rock channel protection. An additional 645 If of intermittent stream would be impounded as part of the waste treatment system. Alternative 3 would result in the discharge of fill material into: 2,590 If of intermittent stream, 5,105 If of ephemeral stream, and 0.09 acre of wetland for mine through activities; 420 If of intermittent stream and 97 If of ephemeral stream for pond dam construction; 64 7 If of intermittent stream for haul road construction; and 93 5 If of intermittent stream and 50 If of ephemeral stream for rock channel protection. An additional 1,280 If of intermittent stream and 190 If of ephemeral stream would be secondarily affected as part of the waste treatment system. The applicant has stated that Alternative 3 is the preferred alternative to accomplish the overall project purpose and need. The table below displays a summary of the discharges of fill material associated with each alternative.

Alternative

Flow Regime

Mine Through

Pond Construction

Haul Road

Rock Channel Protection

Total Stream Length

and wetland acreage

Alternative 1

Intermittent

2565

380

647

875

4467

Ephemeral

5105

63

20

5188

Wetland

0.09

0.09

Alternative 2

Intermittent

2590

120

275

480

3465

Ephemeral

5105

5105

Wetland

0.09

0.09

Alternative 3 (Preferred)

Intermittent

2590

420

647

935

4592

Ephemeral

5105

97

50

5252

Wetland

0.09

0.09

MINIMIZATION OF IMP ACTS TO WATERS OF THE U.S: The applicant has indicated that there is no practicable alternative for the proposed project that completely avoids the discharge of fill material into waters of the U.S. The applicant proposes to utilize the following methods to minimize the effects of suspended particles entering streams and wetlands during mining: the construction of diversions, construction of sediment ponds, installation of silt fences, removal and storage of top soil, temporary stockpiles of spoil, and contemporaneous backfilling and grading. After mining the applicant proposes to redistribute topsoil, seed, plant and mulch all disturbed areas which would aid in the prevention of sediment entering streams and wetlands. To minimize contact with acid/toxic drainage produced by land disturbance and non-coal waste impacting waters of the U.S. the applicant proposes to implement an approved materials handling plan (approved through SMCRA agency) which may include the burial of acid/toxic spoil and/or treatment of mine drainage. To minimize the potential for acid/toxic drainage from debris during mine development and road construction impacting waters of the U.S., the applicant would insure removal and storage of topsoil and proper construction of access roads. COMPENSATORY MITIGATION PLAN (CMP): The applicant used the Headwater Habitat Evaluation Index (HHEI) as a method to determine an appropriate level of mitigation to compensate for stream impacts. The applicant used the Ohio Rapid Assessment Method (ORAM) to do the same for wetlands. The applicant has submitted a CMP to compensate for the proposed impacts to waters of the U.S. The CMP is available for public review at the Corps address below, by appointment. The applicant has proposed permittee responsible on-site, in-kind mitigation for the permanent and temporary fills of jurisdictional stream channels and wetlands associated with Alternative 3. The applicant has proposed no mitigation for temporal loss of jurisdictional stream channels or wetlands associated with the proposed project. Exhibit 5, Table 5-8 lists streams and stream stations identified for impacts and mitigation associated with Alternative 3. In total, the applicant proposes to restore 9,844 linear feet of stream channel to pre-mining conditions based on a physical habitat assessment score (HHEI) equal to or greater than the premining score achieved by the end of the five year monitoring period. The applicant proposes to reconstruct 0.162 acre of wetland to replace the 0.09 acres of wetland filled under Alternative 3. The wetland mitigation would be required to attain a score equivalent to a mid-Category 2 wetland by the end of the five year monitoring period. The applicant proposes to construct a 100 foot buffer zone along streams reconstructed as intermittent (50 feet on either side of stream) and within a 50 foot buffer along streams reconstructed as ephemeral (25 feet on either side of stream). The buffer zones would be planted with a mixture of native woody and herbaceous vegetation and monitored for a period of five years for survivability and presence of invasive species. The applicant's proposed CMP is open to comment and is subject to change based on comments received. After review of all submitted information, the Corps will make a determination of appropriate mitigation, in the event a decision is made to issue a permit. WATER QUALITY CERTIFICATION (WQC): An individual Section 401 Water Quality Certification is required for this project. It is the applicant's responsibility to obtain certification from the Ohio Environmental Protection Agency, Division of Surface Water. HISTORIC AND CULTURAL RESOURCES: This public notice serves as coordination with the State Historic Preservation Officer (SHPO) concerning any properties that may be eligible for or listed in the National Register of Historic Places (NRHP), in accordance with Section 106 of the National Historic Preservation Act. The applicant conducted a Phase I Resource Management Survey on the 248.7 acre site in June 2012 which the Corps is reviewing at this time. If the SHPO has information regarding any potential effects to listed or eligible properties that would be attributable to the Corps' proposed permitting action, it is requested the SHPO provide any information they may have to the Corps by the close of the public comment period. ENDANGERED/THREATENED SPECIES REVIEW: This public notice serves as coordination with the U.S. Fish and Wildlife Service (USFWS) concerning threatened or endangered species, pursuant to Section 7 of the Endangered Species Act of 1972 (as amended). The proposed project lies within the natural range of the endangered Indiana bat (Myotis soda/is). The applicant conducted a mist net survey for the presence/absence of the Indiana bat survey on August 12 and 13, 2012. Based on the information provided, the Corps has determined the proposed project is not likely to adversely affect the Indiana bat, and would have no effect on other federally listed species. If the USFWS has new information and believes any potential effects to federally listed species would be attributable to the Corps' proposed permitting action, it is requested the Service provide any additional information they may have by close of the public comment period. PUBLIC INTEREST REVIEW AND CUMULATIVE EFFECTS: This application will be reviewed in accordance with 33 CFR 320-332, and other pertinent laws, regulations, and executive orders. Our evaluation will also follow the guidelines published by the U.S. Environmental Protection Agency pursuant to Section 404(b )( 1) of the CW A. The decision whether to issue a permit will be based on an evaluation of the probable impact, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit that reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors that may be relevant to the proposal will be considered including the cumulative effects thereof; of those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. The project lies within the Little Muskingum-Middle Island hydrologic unit watershed (Hydrologic Unit Code 05030201). The Corps is assessing the potential cumulative effects that the proposed fill discharges into jurisdictional waters of the U.S. may have on public interest factors when considered with other activities in that watershed. SOLICITATION OF COMMENTS: The Corps is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Interested parties are invited to state any objections they may have to the proposed work. For accuracy and completeness of the administrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding of the reasons for support or opposition. Any person who has an interest that may be adversely affected by the issuance of a permit may request a public hearing. The request must be submitted in writing to the District Engineer on or before the expiration date of this notice and must clearly set forth the interest which may be adversely affected and the manner in which the interest may be adversely affected by the activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements on these factors received in this office on or before the expiration date of this Public Notice will become a part of the record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest. CLOSE OF COMMENT PERIOD: U.S. Army Corps of Engineers ATTN: CELRH-RD-E; Public Notice No. LRH-2009-988-UT East Fork Duck Creek 4969 Dillon Dam Road Zanesville, Ohio 43701 Please note that names and addresses of those who submit comments in response to this public notice become part of our administrative record and, as such, are available to the public under provisions of the Freedom of Information Act. Thank you for your interest in our nation's water resources. If you have any questions concerning this public notice, please call Sheila Newman of the Energy Resource Branch, at 740-454-2225, ext. 5.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas