Purpose of project is to ensure that the Alaska Railroad Corporation (ARRC) Bridge 252.5 and track
Purpose of projectis to ensure that theAlaska Railroad Corporation (ARRC)Bridge 252.5 and track do not wash out during future storm events. The project would reestablish the stream channel, restore water flow under the ARRC Bridge, maintain sediment transport capacity, and reduce sediment accumulation to maintain the safety and integrity of the railroad. Please contact Janet Post at (907) 753-2831, toll free from within Alaska at (800) 478-2712, by fax at (907) 753-5567, or by email at janet.l.post@usace.army.mil if further information is desired concerning this notice.
POA-2007-488, Skull Creek_PN
US Army Corps
of Engineers
Alaska District
Public Notice
of Application
for Permit
Regulatory Division (1145)
CEPOA-RD
Post Office Box 6898
JBER, Alaska 99506-0898
PUBLIC NOTICE DATE:
JANUARY 29, 2013
EXPIRATION DATE:
FEBRUARY 27, 2013
REFERENCE NUMBER:
POA-2007-488
WATERWAY:
SKULL CREEK
Interested parties are hereby notified that a Department of the Army permit application
has been received for work in waters of the United States as described below and shown on
the enclosed project drawings.
Comments on the described work, with the reference number, should reach this office no
later than the expiration date of this Public Notice to become part of the record and be
considered in the decision.
Please contact Janet Post at (907) 753-2831, toll free from
within Alaska at (800) 478-2712, by fax at (907) 753-5567, or by email at
janet.l.post@usace.army.mil if further information is desired concerning this notice.
APPLICANT:
Alaska Railroad Corporation (ARRC)
LOCATION:
The project site is located within Section 25 , T. 30 N., R. 4 W., Seward
Meridian; USGS Quad Map Talkeetna Mts C-6; Latitude 62.659° N., Longitude 149.9367° W.;
near Talkeetna, Alaska.
PURPOSE:
The applicant's stated purpose is to ensure that the ARRC Bridge 252.5 and
track do not wash out during future storm events.
The project would reestablish the
stream channel, restore water flow under the ARRC Bridge, maintain sediment transport
capacity, and reduce sediment accumulation to maintain the safety and integrity of the
railroad.
PROPOSED WORK:
Use a D-8 Caterpillar bulldozer and excavator to move 9,400 cubic yards
of deposited creek bed material from Skull Creek, a tributary of the Susitna River, to
the upland river banks and haul away excess material; 1,000 foot length upstream of ARRC
Bridge 252.5 and 370 foot length downstream of ARRC Bridge 252.5. All work would be
performed in accordance with the enclosed plan (sheets 1-3), dated January 2013.
APPLICANT PROPOSED MITIGATION: The applicant proposes the following mitigation measures
to avoid, minimize, and compensate for impacts to waters of the United States from
activities involving discharges of dredged or fill material.
a. Avoidance:
The existing location of the railroad, Skull Creek, and ARRC's bridge
over Skull Creek do not allow avoidance of impacts to waters of the U.S. The September
storm event and deposition of aggraded material in the stream nearly resulted in a
washout of the track. Impacts have been avoided to the maximum extent practicable by
limiting the dredging/excavation to the minimum necessary to re-establish the former
creek channel and future high water flows. As is common with this type of stream,
sediment deposition will continue to occur, and maintenance will be needed to maintain
the sediment transport capacity of the stream.
If dredging is not undertaken, the flow
will break out of the current channel and begin the process of eroding new channels.
This will require an even greater response to protect the railroad.
Response actions
would include armoring the railroad embankment with rip rap against flow impingement
and construction of upstream flow training dikes to direct the water beneath the bridge
in addition to the proposed limited scope dredging.
b. Minimization:
Recent past efforts to minimize the need for excavation/dredging at
Skull Creek have included raising the track and bridge, and lengthening the bridge to
provide additional clearance.
However, these measures have not eliminated the need for
continued maintenance dredging/excavation following storm events.
Unavoidable impacts
are minimized, as only minor incidental fill would occur during dredging/excavation.
Dredging/excavation activities are limited to the minimum necessary to achieve the
project purpose (reestablish the stream channel, restore water flow under the ARRC
bridge, maintain sediment transport capacity, and reduce sediment accumulation to
maintain the safety and integrity of the railroad).
In addition, ARRC would implement
the following measures to avoid and minimize impacts to waters of the U.S.:
·
·
·
·
·
·
·
Minimize surface disturbance to the extent possible.
Construct only during timing windows established in coordination with ADF&G.
Minimize use of equipment in water.
Implement best management practices during construction to minimize temporary
disturbances to the area and the potential for erosion and sedimentation.
Keep fueling and servicing operations a minimum of 100 feet from water
bodies except in the unlikely event of equipment breakdown.
Implement standard spill-prevention measures to minimize or prevent spills or
leakage of hazardous materials
during
construction
and
ensure
spill
clean-up
equipment
is
available
onsite
during construction (e.g., oilabsorbent pads and appropriate response materials).
Monitor construction activities as necessary.
c.
Compensatory Mitigation: No compensatory mitigation is proposed, as the project
would correct storm-related problems.
There would be a net environmental benefit, as
the project would re-establish the stream channel, restore water flow, and maintain the
sediment transport capacity of the stream.
WATER QUALITY CERTIFICATION: A permit for the described work will not be issued until a
certification or waiver of certification, as required under Section 401 of the Clean
Water Act (Public Law 95-217), has been received from the Alaska Department of
Environmental Conservation.
CULTURAL RESOURCES:
The latest published version of the Alaska Heritage Resources Survey
(AHRS) has been consulted for the presence or absence of historic properties, including
those listed in or eligible for inclusion in the National Register of Historic Places.
There is a registered or eligible property in the vicinity of the worksite.
It has been
designated TLM-00278.
Because it has been determined to be outside of the project area,
no further action is required.
ENDANGERED SPECIES:
No threatened or endangered species are known to use the project area.
we have determined the described activity would have no effect on any listed or proposed
threatened or endangered species, and would have no effect on any designated or proposed
critical habitat, under the Endangered Species Act of 1973 (87 Stat. 844).
Therefore, no
consultation with the U.S. Fish and Wildlife Service or the National Marine Fisheries
Service is required.
However, any comments they may have concerning endangered or
threatened wildlife or plants or their critical habitat will be considered in our final
-assessment of the described work.
-2-
ESSENTIAL FISH HABITAT:
The Magnuson-Stevens Fishery Conservation and Management Act
amended by the Sustainable Fisheries Act of 1996, requires all Federal agencies to
'
consult with the NMFS on all actions, or proposed actions, permitted, funded, or
undertaken by the agency, that may adversely affect Essential Fish Habitat (EFH).
as
The project area is within the known range of the Chum Salmon and the Pink Salmon.
We are currently gathering information regarding these species and have yet to make a
determination of effect. Should we find that the described activity may affect the
species listed above, we will follow the appropriate course of action under Section
305(b) (2) of the Magnuson-Stevens Act. Any comments the National Marine Fisheries
Service may have concerning essential fish habitat will be considered in our final
assessment of the described work.
TRIBAL CONSULTATION:
The Alaska District fully supports tribal self-governance and
government-to-government relations between federally recognized Tribes and the Federal
government.
Tribes with protected rights or resources that could be significantly
affected by a proposed Federal action (e.g., a permit decision) have the right to consult
with the Alaska District on a government-to-government basis. Views of each Tribe
regarding protected rights and resources will be accorded due consideration in this
process.
This Public Notice serves as notification to the Tribes within the area
potentially affected by the proposed work and invites their participation in the Federal
decision-making process regarding the protected Tribal right or resource.
Consultation
may be initiated by the affected Tribe upon written request to the District Commander
during the public comment period.
PUBLIC HEARING: Any person may request, in writing, within the comment period specified
in this notice, that a public hearing be held to consider this application.
Requests for
public hearings shall state, with particularity, reasons for holding a public hearing.
EVALUATION:
The decision whether to issue a permit will be based on an evaluation of the
probable impacts, including cumulative impacts of the proposed activity and its intended
use on the public interest. Evaluation of the probable impacts, which the proposed
activity may have on the public interest, requires a careful weighing of all the factors
that become relevant in each particular case. The benefits, which reasonably may be
expected to accrue from the proposal, must be balanced against its reasonably foreseeable
detriments.
The outcome of the general balancing process would determine whether to
authorize a proposal, and if so, the conditions under which it will be allowed to occur.
The decision should reflect the national concern for both protection and utilization of
important resources. All factors, which may be relevant to the proposal, must be
considered including the cumulative effects thereof. Among those are conservation,
economics, aesthetics, general environmental concerns, wetlands, cultural values, fish
and wildlife values, flood hazards, floodplain values, land use, navigation, shore
erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property
ownership, and, in general, the needs and welfare of the people.
For activities
involving 404 discharges, a permit will be denied if the discharge that would be
authorized by such permit would not comply with the Environmental Protection Agency's
404(b) (1) guidelines.
Subject to the preceding sentence and any other applicable
guidelines or criteria (see Sections 320.2 and 320.3), a permit will be granted unless
the District Commander determines that it would be contrary to the public interest.
The Corps of Engineers is soliciting comments from the public; Federal, State, and local
agencies and officials; Indian Tribes; and other interested parties in order to consider
and evaluate the impacts of this proposed activity. Any comments received will be
considered by the Corps of Engineers to determine whether to issue, modify, condition or
deny a permit for this proposal. To make this decision, comments are used to assess
impacts on endangered species, historic properties, water quality, general environmental
effects, and the other public interest factors listed above.
Comments are used in the
preparation of an Environmental Assessment and/or an Environmental Impact Statement
pursuant to the National Environmental Policy Act.
Comments are also used to determine
the need for a public hearing and to determine the overall public interest of the
proposed activity.
-3-
AUTHORITY:
This permit will be issued or denied under the following authority:
(X)
Discharge dredged or fill material into waters of the United States - Section 404
Clean Water Act (33 U.S.C. 1344). Therefore, our public interest review will consider
the guidelines set forth under Section 404(b) of the Clean Water Act (40 CFR 230).
Project drawings and a Notice of Application for State Water Quality Certification are
enclosed with this Public Notice.
District Commander
U.S. Army, Corps of Engineers
Enclosures
-4-
SEAN PARNELL, GOVERNOR
STATE OF ALASKA
DEPT. OF ENVIRONMENTAL CONSERVATION
DIVISION OF WATER
401 Certification Program
Non-Point Source Water Pollution Control Program
DEPARTMENT OF ENVIRONMENTAL CONSERVATION
WQM/401 CERTIFICATION
555 CORDOVA STREET
ANCHORAGE, ALASKA 99501-2617
PHONE: (907) 269-7564/FAX: (907) 334-2415
NOTICE OF APPLICATION
FOR
STATE WATER QUALITY CERTIFICATION
Any applicant for a federal license or permit to conduct an activity that might result in
a discharge into navigable waters, in accordance with Section 401 of the Clean Water Act
of 1977 (PL95-217), also must apply for and obtain certification from the Alaska
Department of Environmental Conservation that the discharge will comply with the Clean
Water Act, the Alaska Water Quality Standards, and other applicable State laws.
By
agreement between the U.S. Army Corps of Engineers and the Department of Environmental
Conservation, application for a Department of the Army permit to discharge dredged or
fill material into navigable waters under Section 404 of the Clean Water Act also may
serve as application for State Water Quality Certification.
Notice is hereby given that the application for a Department of the Army Permit described
in the Corps of Engineers' Public Notice No. POA-2007-488, SKULL CREEK, serves as
application for State Water Quality Certification from the Department of Environmental
Conservation.
After reviewing the application, the Department may certify there is reasonable assurance
the activity, and any discharge that might result, will comply with the Clean Water Act,
the Alaska Water Quality Standards, and other applicable State laws.
The Department also
may deny or waive certification.
Any person desiring to comment on the project, with respect to Water Quality
Certification, may submit written comments to the address above by the expiration date of
the Corps of Engineer's Public Notice.
Alaska Railroad Corporation
POA-2007-488
Sheet 1 of3
January 2013
SKULL CREEK:
SEC. 25, T30N, R4W, SM
USGS QUAD: TALKEETNA MTNS C-6
MAP DATE: 1949
PURPOSE: IMPROVE AND MAINTAIN BRIDGE
AND CHANNEL CONVEYANCE
---
0
PERMIT:
SKULL CREEK
VICINITY MAP
2
Miles
1 inch equals 1 miles
DATUM: ALASKA ALBERS NAD 1927
ADJACENT PROPERTY OWNERS:
UPLANDS: N/A
OFFSHORE: N/A
ALASKA RAILROAD CORP.
P.O. BOX 107500
ANCH., AK 99510-7500
IN: ARRC MILEPOST 252.5
AT: CURRY
MATANUSKA SUSITNA BOROUGH
APPLICATION BY:
T.E. BROOKS, CHIEF ENGINEER
ARRC-ENGINEERING SERVICES
SHEET:
1
OF
DATE: 3/30/04
REV.:
'-!CZJ>-t:I;J>
§l~o
I
~~>--~
s-·i";"
«! tvNPl
I
tv08~
0
>-+, .......:J
........_l;.)
w
I
I
e: .
1---1
1000'
I
..j::>."i
ooO
00~
UPSTREA~ DREDG£ LI~ITS
f/
n
0
>80
~
.....
~I
I
~
it
0
i:l
APPROX. POST
~
DREDGI~G BA~K
'
~
!Of
Of
C>
~
Totol Excavation Area - 1.6 Acres
Waters of U.S. Excavation Area - 0.57 Acres
Upland Stockpile Area - 1.2 Acres
'
.
'
~I
'?..
I
~
11\ PLAN
~
scm:r- 2oo·
PURPOSE: 2012 FLOOD REPAIR
PERMIT:
U:\ACAD\eng-projects\COE pcrmita\252·5\2012 Flood Repair\ DR 252.5
Skull Creek
DATUM:
ADJACENT PROPERTY OWNERS:
UPLANDS:
OFFSHORE:
MP 252.5
PLAN
·
ALASKA RAILROAD CORP .
327
W.
Ship Creek Avenue
P.O. Bo· 107500
ANCHORAGE, ALASKA 99510-7500
IN: SKULL CREEK
AT: CURRY
MATANUSKA SUSITNA BOROUGH
APPLICATION BY:
ROY THOMAS, DIRECTOR
ENGINEERING SERVICES
SHEET: 1
OF
2
DATE: 12/05/12
REV.:
APPRox. P0$.1
~- ... ,_
~ ~-=1
=~G~~
,f':
·~
------------------------
--~
- ----.[~-~-----------------------
12\ SECTION A
~
=G~~~
\
-----
SCALEi1"-;26'
2
~APPRO~~CIIIi.L
~~
t70'
APPRox. ORICIIIAL
/BAli~
',,-------------------.------~----------~---?~
''---- .[~~-~~:_- _'.{_----- ~~~E:~- _,. _, _,~i
I
,___ _ _ _ _ _ _ _ uo·
·-qzp-o
2
::>
§P"O-
12\ SECTION B
s::~;p.e5
~ r-+
I
:;.;w N ~
~ SCALE; 1"
«
=
20'
tvOg~
0>-1')......:1~
'·'
I
,_.,
,_.Vool..j:;>.-
w
ood
PURPOSE: 2012 FLOOD REPAIR
00~
n
0
>80
U:\:\CAD\cng·projecu\COE
Sku!! Creek
g
o·
i=l
PERMIT:
-5\2012 f'!ood Rtpair\BR 252.5
DATUM:
ADJACENT PROPERTY OWNER~
UPLANDS:
OFFSHORE:
MP 252.5
SECTIONS
·
ALASKA RAILROAD CORP .
327 W. Ship Creek Avenue
P.O. Box 107500
ANCHORAGE, ALASKA 99510-7500
IN: SKULL CREEK
AT: CURRY
MATANUSKA SUSITNA BOROUGH
APPLICATION BY:
ROY THOMAS, DIRECTOR
ENGINEERING SERVICES
SHEET: 2
OF
2
DATE: 12/05/12
REV.:
US Army Corps
of Engineers
Alaska District
Public Notice
of Application
for Permit
Regulatory Division (1145)
CEPOA-RD
Post Office Box 6898
JBER, Alaska 99506-0898
PUBLIC NOTICE DATE:
JANUARY 29, 2013
EXPIRATION DATE:
FEBRUARY 27, 2013
REFERENCE NUMBER:
POA-2007-488
WATERWAY:
SKULL CREEK
Interested parties are hereby notified that a Department of the Army permit application
has been received for work in waters of the United States as described below and shown on
the enclosed project drawings.
Comments on the described work, with the reference number, should reach this office no
later than the expiration date of this Public Notice to become part of the record and be
considered in the decision.
Please contact Janet Post at (907) 753-2831, toll free from
within Alaska at (800) 478-2712, by fax at (907) 753-5567, or by email at
janet.l.post@usace.army.mil if further information is desired concerning this notice.
APPLICANT:
Alaska Railroad Corporation (ARRC)
LOCATION:
The project site is located within Section 25 , T. 30 N., R. 4 W., Seward
Meridian; USGS Quad Map Talkeetna Mts C-6; Latitude 62.659° N., Longitude 149.9367° W.;
near Talkeetna, Alaska.
PURPOSE:
The applicant's stated purpose is to ensure that the ARRC Bridge 252.5 and
track do not wash out during future storm events.
The project would reestablish the
stream channel, restore water flow under the ARRC Bridge, maintain sediment transport
capacity, and reduce sediment accumulation to maintain the safety and integrity of the
railroad.
PROPOSED WORK:
Use a D-8 Caterpillar bulldozer and excavator to move 9,400 cubic yards
of deposited creek bed material from Skull Creek, a tributary of the Susitna River, to
the upland river banks and haul away excess material; 1,000 foot length upstream of ARRC
Bridge 252.5 and 370 foot length downstream of ARRC Bridge 252.5. All work would be
performed in accordance with the enclosed plan (sheets 1-3), dated January 2013.
APPLICANT PROPOSED MITIGATION: The applicant proposes the following mitigation measures
to avoid, minimize, and compensate for impacts to waters of the United States from
activities involving discharges of dredged or fill material.
a. Avoidance:
The existing location of the railroad, Skull Creek, and ARRC's bridge
over Skull Creek do not allow avoidance of impacts to waters of the U.S. The September
storm event and deposition of aggraded material in the stream nearly resulted in a
washout of the track. Impacts have been avoided to the maximum extent practicable by
limiting the dredging/excavation to the minimum necessary to re-establish the former
creek channel and future high water flows. As is common with this type of stream,
sediment deposition will continue to occur, and maintenance will be needed to maintain
the sediment transport capacity of the stream.
If dredging is not undertaken, the flow
will break out of the current channel and begin the process of eroding new channels.
This will require an even greater response to protect the railroad.
Response actions
would include armoring the railroad embankment with rip rap against flow impingement
and construction of upstream flow training dikes to direct the water beneath the bridge
in addition to the proposed limited scope dredging.
b. Minimization:
Recent past efforts to minimize the need for excavation/dredging at
Skull Creek have included raising the track and bridge, and lengthening the bridge to
provide additional clearance.
However, these measures have not eliminated the need for
continued maintenance dredging/excavation following storm events.
Unavoidable impacts
are minimized, as only minor incidental fill would occur during dredging/excavation.
Dredging/excavation activities are limited to the minimum necessary to achieve the
project purpose (reestablish the stream channel, restore water flow under the ARRC
bridge, maintain sediment transport capacity, and reduce sediment accumulation to
maintain the safety and integrity of the railroad).
In addition, ARRC would implement
the following measures to avoid and minimize impacts to waters of the U.S.:
·
·
·
·
·
·
·
Minimize surface disturbance to the extent possible.
Construct only during timing windows established in coordination with ADF&G.
Minimize use of equipment in water.
Implement best management practices during construction to minimize temporary
disturbances to the area and the potential for erosion and sedimentation.
Keep fueling and servicing operations a minimum of 100 feet from water
bodies except in the unlikely event of equipment breakdown.
Implement standard spill-prevention measures to minimize or prevent spills or
leakage of hazardous materials
during
construction
and
ensure
spill
clean-up
equipment
is
available
onsite
during construction (e.g., oilabsorbent pads and appropriate response materials).
Monitor construction activities as necessary.
c.
Compensatory Mitigation: No compensatory mitigation is proposed, as the project
would correct storm-related problems.
There would be a net environmental benefit, as
the project would re-establish the stream channel, restore water flow, and maintain the
sediment transport capacity of the stream.
WATER QUALITY CERTIFICATION: A permit for the described work will not be issued until a
certification or waiver of certification, as required under Section 401 of the Clean
Water Act (Public Law 95-217), has been received from the Alaska Department of
Environmental Conservation.
CULTURAL RESOURCES:
The latest published version of the Alaska Heritage Resources Survey
(AHRS) has been consulted for the presence or absence of historic properties, including
those listed in or eligible for inclusion in the National Register of Historic Places.
There is a registered or eligible property in the vicinity of the worksite.
It has been
designated TLM-00278.
Because it has been determined to be outside of the project area,
no further action is required.
ENDANGERED SPECIES:
No threatened or endangered species are known to use the project area.
we have determined the described activity would have no effect on any listed or proposed
threatened or endangered species, and would have no effect on any designated or proposed
critical habitat, under the Endangered Species Act of 1973 (87 Stat. 844).
Therefore, no
consultation with the U.S. Fish and Wildlife Service or the National Marine Fisheries
Service is required.
However, any comments they may have concerning endangered or
threatened wildlife or plants or their critical habitat will be considered in our final
-assessment of the described work.
-2-
ESSENTIAL FISH HABITAT:
The Magnuson-Stevens Fishery Conservation and Management Act
amended by the Sustainable Fisheries Act of 1996, requires all Federal agencies to
'
consult with the NMFS on all actions, or proposed actions, permitted, funded, or
undertaken by the agency, that may adversely affect Essential Fish Habitat (EFH).
as
The project area is within the known range of the Chum Salmon and the Pink Salmon.
We are currently gathering information regarding these species and have yet to make a
determination of effect. Should we find that the described activity may affect the
species listed above, we will follow the appropriate course of action under Section
305(b) (2) of the Magnuson-Stevens Act. Any comments the National Marine Fisheries
Service may have concerning essential fish habitat will be considered in our final
assessment of the described work.
TRIBAL CONSULTATION:
The Alaska District fully supports tribal self-governance and
government-to-government relations between federally recognized Tribes and the Federal
government.
Tribes with protected rights or resources that could be significantly
affected by a proposed Federal action (e.g., a permit decision) have the right to consult
with the Alaska District on a government-to-government basis. Views of each Tribe
regarding protected rights and resources will be accorded due consideration in this
process.
This Public Notice serves as notification to the Tribes within the area
potentially affected by the proposed work and invites their participation in the Federal
decision-making process regarding the protected Tribal right or resource.
Consultation
may be initiated by the affected Tribe upon written request to the District Commander
during the public comment period.
PUBLIC HEARING: Any person may request, in writing, within the comment period specified
in this notice, that a public hearing be held to consider this application.
Requests for
public hearings shall state, with particularity, reasons for holding a public hearing.
EVALUATION:
The decision whether to issue a permit will be based on an evaluation of the
probable impacts, including cumulative impacts of the proposed activity and its intended
use on the public interest. Evaluation of the probable impacts, which the proposed
activity may have on the public interest, requires a careful weighing of all the factors
that become relevant in each particular case. The benefits, which reasonably may be
expected to accrue from the proposal, must be balanced against its reasonably foreseeable
detriments.
The outcome of the general balancing process would determine whether to
authorize a proposal, and if so, the conditions under which it will be allowed to occur.
The decision should reflect the national concern for both protection and utilization of
important resources. All factors, which may be relevant to the proposal, must be
considered including the cumulative effects thereof. Among those are conservation,
economics, aesthetics, general environmental concerns, wetlands, cultural values, fish
and wildlife values, flood hazards, floodplain values, land use, navigation, shore
erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property
ownership, and, in general, the needs and welfare of the people.
For activities
involving 404 discharges, a permit will be denied if the discharge that would be
authorized by such permit would not comply with the Environmental Protection Agency's
404(b) (1) guidelines.
Subject to the preceding sentence and any other applicable
guidelines or criteria (see Sections 320.2 and 320.3), a permit will be granted unless
the District Commander determines that it would be contrary to the public interest.
The Corps of Engineers is soliciting comments from the public; Federal, State, and local
agencies and officials; Indian Tribes; and other interested parties in order to consider
and evaluate the impacts of this proposed activity. Any comments received will be
considered by the Corps of Engineers to determine whether to issue, modify, condition or
deny a permit for this proposal. To make this decision, comments are used to assess
impacts on endangered species, historic properties, water quality, general environmental
effects, and the other public interest factors listed above.
Comments are used in the
preparation of an Environmental Assessment and/or an Environmental Impact Statement
pursuant to the National Environmental Policy Act.
Comments are also used to determine
the need for a public hearing and to determine the overall public interest of the
proposed activity.
-3-
AUTHORITY:
This permit will be issued or denied under the following authority:
(X)
Discharge dredged or fill material into waters of the United States - Section 404
Clean Water Act (33 U.S.C. 1344). Therefore, our public interest review will consider
the guidelines set forth under Section 404(b) of the Clean Water Act (40 CFR 230).
Project drawings and a Notice of Application for State Water Quality Certification are
enclosed with this Public Notice.
District Commander
U.S. Army, Corps of Engineers
Enclosures
-4-
SEAN PARNELL, GOVERNOR
STATE OF ALASKA
DEPT. OF ENVIRONMENTAL CONSERVATION
DIVISION OF WATER
401 Certification Program
Non-Point Source Water Pollution Control Program
DEPARTMENT OF ENVIRONMENTAL CONSERVATION
WQM/401 CERTIFICATION
555 CORDOVA STREET
ANCHORAGE, ALASKA 99501-2617
PHONE: (907) 269-7564/FAX: (907) 334-2415
NOTICE OF APPLICATION
FOR
STATE WATER QUALITY CERTIFICATION
Any applicant for a federal license or permit to conduct an activity that might result in
a discharge into navigable waters, in accordance with Section 401 of the Clean Water Act
of 1977 (PL95-217), also must apply for and obtain certification from the Alaska
Department of Environmental Conservation that the discharge will comply with the Clean
Water Act, the Alaska Water Quality Standards, and other applicable State laws.
By
agreement between the U.S. Army Corps of Engineers and the Department of Environmental
Conservation, application for a Department of the Army permit to discharge dredged or
fill material into navigable waters under Section 404 of the Clean Water Act also may
serve as application for State Water Quality Certification.
Notice is hereby given that the application for a Department of the Army Permit described
in the Corps of Engineers' Public Notice No. POA-2007-488, SKULL CREEK, serves as
application for State Water Quality Certification from the Department of Environmental
Conservation.
After reviewing the application, the Department may certify there is reasonable assurance
the activity, and any discharge that might result, will comply with the Clean Water Act,
the Alaska Water Quality Standards, and other applicable State laws.
The Department also
may deny or waive certification.
Any person desiring to comment on the project, with respect to Water Quality
Certification, may submit written comments to the address above by the expiration date of
the Corps of Engineer's Public Notice.
Alaska Railroad Corporation
POA-2007-488
Sheet 1 of3
January 2013
SKULL CREEK:
SEC. 25, T30N, R4W, SM
USGS QUAD: TALKEETNA MTNS C-6
MAP DATE: 1949
PURPOSE: IMPROVE AND MAINTAIN BRIDGE
AND CHANNEL CONVEYANCE
---
0
PERMIT:
SKULL CREEK
VICINITY MAP
2
Miles
1 inch equals 1 miles
DATUM: ALASKA ALBERS NAD 1927
ADJACENT PROPERTY OWNERS:
UPLANDS: N/A
OFFSHORE: N/A
ALASKA RAILROAD CORP.
P.O. BOX 107500
ANCH., AK 99510-7500
IN: ARRC MILEPOST 252.5
AT: CURRY
MATANUSKA SUSITNA BOROUGH
APPLICATION BY:
T.E. BROOKS, CHIEF ENGINEER
ARRC-ENGINEERING SERVICES
SHEET:
1
OF
DATE: 3/30/04
REV.:
'-!CZJ>-t:I;J>
§l~o
I
~~>--~
s-·i";"
«! tvNPl
I
tv08~
0
>-+, .......:J
........_l;.)
w
I
I
e: .
1---1
1000'
I
..j::>."i
ooO
00~
UPSTREA~ DREDG£ LI~ITS
f/
n
0
>80
~
.....
~I
I
~
it
0
i:l
APPROX. POST
~
DREDGI~G BA~K
'
~
!Of
Of
C>
~
Totol Excavation Area - 1.6 Acres
Waters of U.S. Excavation Area - 0.57 Acres
Upland Stockpile Area - 1.2 Acres
'
.
'
~I
'?..
I
~
11\ PLAN
~
scm:r- 2oo·
PURPOSE: 2012 FLOOD REPAIR
PERMIT:
U:\ACAD\eng-projects\COE pcrmita\252·5\2012 Flood Repair\ DR 252.5
Skull Creek
DATUM:
ADJACENT PROPERTY OWNERS:
UPLANDS:
OFFSHORE:
MP 252.5
PLAN
·
ALASKA RAILROAD CORP .
327
W.
Ship Creek Avenue
P.O. Bo· 107500
ANCHORAGE, ALASKA 99510-7500
IN: SKULL CREEK
AT: CURRY
MATANUSKA SUSITNA BOROUGH
APPLICATION BY:
ROY THOMAS, DIRECTOR
ENGINEERING SERVICES
SHEET: 1
OF
2
DATE: 12/05/12
REV.:
APPRox. P0$.1
~- ... ,_
~ ~-=1
=~G~~
,f':
·~
------------------------
--~
- ----.[~-~-----------------------
12\ SECTION A
~
=G~~~
\
-----
SCALEi1"-;26'
2
~APPRO~~CIIIi.L
~~
t70'
APPRox. ORICIIIAL
/BAli~
',,-------------------.------~----------~---?~
''---- .[~~-~~:_- _'.{_----- ~~~E:~- _,. _, _,~i
I
,___ _ _ _ _ _ _ _ uo·
·-qzp-o
2
::>
§P"O-
12\ SECTION B
s::~;p.e5
~ r-+
I
:;.;w N ~
~ SCALE; 1"
«
=
20'
tvOg~
0>-1')......:1~
'·'
I
,_.,
,_.Vool..j:;>.-
w
ood
PURPOSE: 2012 FLOOD REPAIR
00~
n
0
>80
U:\:\CAD\cng·projecu\COE
Sku!! Creek
g
o·
i=l
PERMIT:
-5\2012 f'!ood Rtpair\BR 252.5
DATUM:
ADJACENT PROPERTY OWNER~
UPLANDS:
OFFSHORE:
MP 252.5
SECTIONS
·
ALASKA RAILROAD CORP .
327 W. Ship Creek Avenue
P.O. Box 107500
ANCHORAGE, ALASKA 99510-7500
IN: SKULL CREEK
AT: CURRY
MATANUSKA SUSITNA BOROUGH
APPLICATION BY:
ROY THOMAS, DIRECTOR
ENGINEERING SERVICES
SHEET: 2
OF
2
DATE: 12/05/12