SB & RBLI Land Company has applied for a permit to place fill material in approximately 2.67 acres of waters of the United States to construct housing, parks and schools, and to place fill material in 0.52 acres of waters of the U.S. to construct off-site infrastructure. The proposed project is located at the north-west intersection of Bilby Road and the future proposed Big Horn Boulevard, south of Poppy Ridge Road and east of Bruceville Road, in Section 10, Township 6 N, Range 5 E, Mount Diablo Meridian, Latitude 38.38336° North, Longitude 121.40383° West, in the City of Elk Grove, Sacramento County, California, and can be seen on the CA-FLORIN USGS Topographic Quadrangle.
SUBJECT: The U.S. Army Corps of Engineers, Sacramento District, (Corps) is evaluating a permit application to construct the Arbor Ranch project, which would result in impacts to approximately 3.19 acres of waters of the United States, including wetlands, draining to an unnamed tributary of Stone Lake. This notice is to inform interested parties of the proposed activity and to solicit comments. This notice may also be viewed at the Corps web site at http://www.spk.usace.army.mil/regulatory.html.
AUTHORITY: This application is being evaluated under Section 404 of the Clean Water Act for the discharge of dredged or fill material in waters of the United States.
APPLICANT: SB & RBLI Land Company
Attn: Mr. Steven Pilch c/o Mr. Alan Hyden
4 Embarcadero Center, Suite 3300
San Francisco, California 94111
Phone: 415-905-5300
AGENT:Gibson & Skordal, LLC.
Attn: Ms. Ginger Fodge
2617 K Street, Suite 175
Sacramento, California 95816
Phone: 916-822-3230
LOCATION: The approximately 162-acre site is located at the north-west intersection of Bilby Road and the future proposed Big Horn Boulevard, south of Poppy Ridge Road and east of Bruceville Road, in Section 10, Township 6 N, Range 5 E, Mount Diablo Meridian, Latitude 38.38336° North, Longitude 121.40383° West, in the City of Elk Grove, Sacramento County, California, and can be seen on the CA-FLORIN USGS Topographic Quadrangle.
PROJECT DESCRIPTION: The proposed project consists of development of the Arbor Ranch site, as well as infrastructure improvements necessary for the development of the proposed project site. The infrastructure improvements are part of the Laguna Ridge South Infrastructure (off-site infrastructure) application. The proposed development of the Arbor Ranch site would include:
- the construction of 810 single-family residential lots,
- the construction of a 3.3 acre park site and a 1 acre park site,
- the construction of a 10-acre elementary school site,
- the construction of on-site roadways and associated infrastructure.
Development of the proposed project site would result in the placement of fill material into approximately 2.67 acres of waters of the U.S.
The infrastructure improvements would include:
- The extension of Big Horn Boulevard from Poppy Ridge Road south to Bilby Road. The proposed road would be 27-feet wide, with curb and gutter on the west side and an earthen v-ditch on the east side. A 7-foot wide sidewalk is proposed to be constructed within a 25-foot landscape corridor on the west side of the road.
- Widening of Bilby Road to a two-lane improved roadway from a point approximately 600-feet east of Bruceville Road to the extension of Big Horn Boulevard. Bilby Road would be 26-feet wide, with curb and gutter on the north side, and an earthen drainage swale on the south side. A 4-foot wide sidewalk is proposed to be constructed within a 31-foot landscape corridor on the north side of the road.
- Installation of sewer lines, water lines, and storm drain lines beneath Big Horn Boulevard and Bilby Road.
- Construction of a sewer lift station east of Bruceville Road and north of Elefa Avenue.
- Installation of a sewer line from the Arbor Ranch project site to the sewer lift station;
- Construction of a stormwater detention basin off the southwest corner of the Arbor Ranch site; and
- Constructing a storm water drainage channel south of Bilby Road. The channel would originate south of Bilby Road at the southwest corner of the Arbor Ranch site and would extend approximately 1,000 feet to the south.
The proposed infrastructure improvements would result in the discharge of fill material into approximately 0.52 acres of waters of the U.S. Approximately 0.30 acre of waters of the U.S. proposed to be filled for the off-site infrastructure are located on the 162-acre proposed project site, with the remaining 0.22 acre of impacts occurring off-site.
The applicant’s stated purpose is to provide housing, parks and a school. The applicant believes there is a need for this project. The attached drawings provide additional project details.
ADDITIONAL INFORMATION:
Environmental Setting. The proposed project area consists of the approximately 162-acre site, as well as the off-site infrastructure area. The proposed project site and off-site infrastructure area is surrounded by agricultural activities, including ranchettes, farmland and grazing pasture. The proposed project site has historically been irrigated and disked on an annual basis for grazing, irrigated crops and dry crops. Topography of the area consists of generally flat to partially leveled terrain that slopes and drains to the southwest corner. The proposed 162-acre project site contains approximately 2.97 acres of waters of the U.S., consisting of approximately 2.21 acres of vernal pools and 0.76 acres of seasonal wetland swale. The jurisdictional determination was verified on July 30, 2010. The dominant vegetation on the site consists of perennial rye (Lolium pernne), oats (Avena sp.), winter vetch (Vicia villosa), canarygrass (Phalaris sp.), little quaking grass (Briza minor), loosestrife (Lythrum hyssopifolia), blow-wives (Achyrachaena mollis), smooth cats tongue (Hypochaeria glabra) and toad rush (Juncus bufonius). The dominant vegetation within the wetland on the site consists of ornate downingia (Downingia ornitissima), loosestrife, Mediterranean barley (Hordeum histrix), toad rush, perennial rye, wild oats (Avena fatua), and blow-wives.
The proposed off-site infrastructure area is part of the Laguna Ridge South planning area (SPK-2007-01824). This approximately 15-acre area contains approximately 1.67 acres of waters of the U.S., including 1.21 acres of jurisdictional ditches, and 0.46 acre of seasonal wetlands. The proposed off-site infrastructure area is dominated by soft chess (Bromus mollis), orchard grass (Dactylis glomerata), perennial rye, Mediterranean barley, winter vetch, barley (Hordeum leporinum), and wild oats.
Alternatives. The applicant has not provided information concerning project alternatives. Additional information concerning project alternatives may be available from the applicant or their agent. Other alternatives may develop during the review process for this permit application. All reasonable project alternatives, in particular those which may be less damaging to the aquatic environment, will be considered.
Mitigation. The Corps requires that applicants consider and use all reasonable and practical measures to avoid and minimize impacts to aquatic resources. If the applicant is unable to avoid or minimize all impacts, the Corps may require compensatory mitigation. The applicant has not proposed to avoid any waters of the U.S. within the permit area. The applicant has proposed to mitigate for impacts to 2.21 acres of vernal pools and 0.76 acres of seasonal wetland swales associated with development of the 162-acre site through the purchase of 2.21 vernal pool creation credits and 0.76 seasonal wetland creation credits at a Corps approved mitigation bank. In order to mitigate for impacts to 0.31 acre of vernal pools and 0.17 acre of seasonal wetlands and seasonal wetland swales from the proposed off-site infrastructure, the applicant has proposed to purchase 0.31 vernal pool creation credits and 0.17 seasonal wetland creation credits. The applicant has not proposed compensatory mitigation for the 0.035 acre of jurisdictional ditches that would be impacted by the proposed off-site infrastructure.
OTHER GOVERNMENTAL AUTHORIZATIONS: Water quality certification or a waiver, as required under Section 401 of the Clean Water Act from the Central Valley Regional Water Quality Control Board is not required for this project. The applicant has not indicated they have applied for certification.
HISTORIC PROPERTIES: Based on the available information no cultural resources were identified within the project's area of potential effect. The Corps will initiate consultation with the State Historic Preservation Officer under Section 106 of the National Historic Preservation Act, as appropriate.
ENDANGERED SPECIES: The proposed activity may affect Federally-listed endangered or threatened species or their critical habitat. The Corps will initiate consultation with the U.S. Fish and Wildlife Service pursuant to Section 7 of the Endangered Species Act, as appropriate.
ESSENTIAL FISH HABITAT: The proposed project will not adversely affect Essential Fish Habitat (EFH) as defined in the Magnuson-Stevens Fishery Conservation and Management Act.
The above determinations are based on information provided by the applicant and our preliminary review.
EVALUATION FACTORS: The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the described activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the described activity will be considered, including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people. The activity's impact on the public interest will include application of the Section 404(b)(1) guidelines promulgated by the Administrator, Environmental Protection Agency (40 CFR Part 230).
The Corps is soliciting comments from the public, Federal, State, and local agencies and officials, Indian tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
SUBMITTING COMMENTS: Written comments, referencing Public Notice SPK-2004-00038 must be submitted to the office listed below on or before June 7, 2012
Lisa Gibson, Project Manager
US Army Corps of Engineers, Sacramento District
1325 J Street, Room 1350
Sacramento, California 95814-2922
Email: Lisa.M.Gibson2@usace.army.mil
The Corps is particularly interested in receiving comments related to the proposal's probable impacts on the affected aquatic environment and the secondary and cumulative effects. Anyone may request, in writing, that a public hearing be held to consider this application. Requests shall specifically state, with particularity, the reason(s) for holding a public hearing. If the Corps determines that the information received in response to this notice is inadequate for thorough evaluation, a public hearing may be warranted. If a public hearing is warranted, interested parties will be notified of the time, date, and location. Please note that all comment letters received are subject to release to the public through the Freedom of Information Act. If you have questions or need additional information please contact the applicant or the Corps' project manager Lisa Gibson, 916-557-5288, Lisa.M.Gibson2@usace.army.mil.
Attachments: 7 drawings