Home

Galveston District

Run scraper

Chevron Phillips Chemical Company

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

The applicant proposes to construct a polyethylene production facility

Project PlansMitigation PlansAlternative AnalysisFull Public Notice The applicant proposes to construct a polyethylene production facility in Old Ocean, adjacent to an existing facility and proposes to fill 38.63 acres of wetlands and 735 linear feet of a perennial stream (Linnville Bayou) for two crossings. The new components will consist of two polyethylene units and associated utilities, rail lines, a storage-in-transit yard, locomotive and rail car maintenance facilities, access roads and detention ponds. Temporary construction support facilities will include laydown areas, contractor service areas, parking and access roads. The applicant’s plans are enclosed in 13 sheets.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas