Final Environmental Impact Statement for Coastal Water Authority’s Luce Bayou Inter-basin Transfer Project in Liberty and Harris Counties, Texas
Special Public NoticeFEIS
U.S. Army Corps of Engineers, Galveston District (SWG), is issuing a notice to advise the public that a Final Environmental Impact Statement (FEIS), for which you might be interested, has been completed and is available for review.
Review period has been extended to Novermber 18, 2013.
Special Public Notice
Final Environmental Impact Statement
Luce Bayou Inter-basin Transfer Project
October 9, 2013
Galveston District
Regulatory Branch
Final Environmental Impact Statement for Coastal Water
Authority's Luce Bayou Inter-basin Transfer Project in
Liberty and Harris Counties, Texas
PURPOSE OF PUBLIC NOTICE: To inform you that the U.S. Army Corps of
Engineers, Galveston District (SWG), is issuing a notice to advise the public that a Final
Environmental Impact Statement (FEIS), for which you might be interested, has been
completed and is available for review
FINAL ENVIRONMENTAL IMPACT STATEMENT:
A Notice of Availability for the FEIS was published in the Federal Register on October 4,
2013.
The FEIS is available online at the EPA Environmental Impact Statement (EIS)
Database web site. This site may be accessed at:
http://www.epa.gov/compliance/nepa/eisdata.html
or through a link via the SWG Special Projects web site at:
http://www.swg.usace.army.mil/BusinessWithUs/RegulatoryBranch/SpecialProjectsEnvi
ronmentalImpactStatements.aspx
INFORMATION: The Coastal Water Authority proposes to construct a 26.5 mile water
supply conveyance consisting of subsurface pipeline and surface canal within a 300 ft.
wide right of way from the Trinity River in Liberty County, TX to Lake Houston in Harris
County, TX. The proposed project would transfer water from the Trinity River basin to
the San Jacinto River basin. The Coastal Water Authority is the applicant for the
Department of Army permit (DA) SWG-2009-00188. A pump station would be
constructed on the Trinity River at Capers Ridge approximately 10 miles north of
Dayton, Texas. Water from the river would be conveyed by pipeline to a sedimentation
basin and then conveyed by earthen canal to Lake Houston to a discharge point in the
lake. The canal right of way would include canal side berms, a maintenance access
roadway, drainage ditches, and perimeter fencing surrounding the canal. Other
elements of the project proposal include the following:
a. Dual 108 inch diameter pipelines constructed to convey water 3.5
miles to a 20 acre sedimentation/settling basin.
b. A 23.5 mile clay lined earthen canal with 4:1 side lopes within a 300 ft.
wide right of way (ROW) which would include a maintenance roadway,
access roads, chain link perimeter fencing, flow control and metering
facilities.
c. Other facilities include box culverts at roadway and canal crossings,
and multiple below ground siphons constructed to maintain existing
drainage patterns along the length of the conveyance.
d. A maintenance facility is proposed 6 miles north of Dayton, Texas.
e. A discharge structure is proposed along the southeast shoreline of
Lake Houston.
The proposed inter-basin transfer of water from the Trinity River basin to the San
Jacinto River basin is an effort by the City of Houston to continue replacing groundwater
use with previously secured water resources stored in Lake Livingston. The Applicant
has indicated that groundwater reduction is a statutory requirement and is critical to
managing the damaging consequences of subsidence throughout the Houston/Harris
County area. In addition, water demand projections developed by the City of Houston
and State of Texas regional water plan analysis indicate substantial new demand from
residential, commercial, industrial, and other water users over the next 50 years. In
order to both reduce reliance on groundwater and to continue to meet existing and
projected demand with surface water supplies, the Applicant proposes to use the
previously secured surface water resources in the Trinity River basin. Up to 400 million
gallons per day is proposed to be conveyed in accordance with existing water rights.
A Public Notice for Permit Application SWG-2009-00188 was published in 2010 and
comments were requested and compiled for evaluation. A Notice of Intent (NOI) to
prepare an EIS was published on May 25, 2011 in the Federal Register, and a scoping
meeting was held on July 21, 2011 in Dayton, Texas at the Dayton Community Center.
The Scoping Notice and NOI were published on the SWG District webpage, and
notices were published in local newspapers, and mailed to current stakeholder lists
requesting input and comments concerning issues and resources that should be
addressed in the DEIS.
A Notice of Availability for the Draft Environmental Impact Statement (DEIS) was
published in the Federal Register on October 26, 2012. A public hearing on the DEIS
was held on November 28, 2012 at the Dayton Community Center, Dayton, Texas. The
purpose of the hearing was to provide the public an opportunity to comment on the
DEIS. Comments on the DEIS were accepted for 45 days.
DISTRICT ENGINEER
GALVESTON DISTRICT
CORPS OF ENGINEERS
Special Public Notice: SWG-2009-00188