Duke Energy Revised General Permit
York, Lancaster, Chester, Fairfield, Kershaw, Oconee and Pickens Counties, South Carolina
Duke Energy Revised General Permit
York, Lancaster, Chester, Fairfield, Kershaw, Oconee andPickens Counties, South Carolina
PUBLIC NOTICE
CHARLESTON DISTRICT, CORPS OF ENGINEERS
69A Hagood Avenue
Charleston, South Carolina 29403-5107
REGULATORY DIVISION
Refer to: General Permit # 2008-00328-6GF
March 18, 2013
Pursuant to Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) and Section 404 of the
Clean Water Act (33 U.S.C. 1341), a General Permit to perform work in or affecting navigable waters of the United
States has been issued by the
District Commander
U.S. Army Corps of Engineers
Charleston District
69A Hagood Avenue
Charleston, South Carolina 29403
to authorize, where such authorizations are required, the construction, repair and maintenance of private noncommercial piers, docks, boat lifts, moorings, boat houses, existing boat ramps, marine railways for dry storage,
boat shelters bulkheads, retainer walls, riprap, bio-engineering for erosion control, heat exchange coils for heat
pumps, minor intake pipes for residential irrigation, and minor excavation by the adjacent shoreline property
owners in the following lakes:
Lake
County
License
Project Boundary
Wylie (SC)
Fishing Creek
Great Falls
Rocky Creek
Wateree
Keowee
Ninety-Nine Island
Gaston Shoals (SC)
Robinson
York
Chester/Lancaster
Chester/Lancaster
Chester/Lancaster/Fairfield
Kershaw/Lancaster/Fairfield
Oconee/Pickens
Cherokee/York
Cherokee
Chesterfield/Darlington
2232
2232
2232
2232
2232
2503
2331
2332
569.4
417.2
355.8
284.4
225.5
varies 800.0 810.0
511.1
605.2
222
The South Carolina Department of Health and Environmental Control has issued a General Permit for
Construction in Navigable Waters, SC GP 87-14-001 (Revised July 2007), authorizing similar work in or affecting
navigable waters of South Carolina, pursuant to regulations and procedures established under R. 19-450, et seq.,
Code of Laws of South Carolina, 1976, as amended. Anyone wishing to conduct work within the above
referenced lakes in accordance with the terms and conditions of Corps' General Permit must also obtain
authorization from Duke Energy. For additional information regarding Duke Energy's Shoreline Management
Plan, please contact their Lake Services Office at 1-800-443-5193.
In order to give all interested parties an opportunity to express their views
NOTICE
is hereby given that written statements regarding the proposed work will be received by the Corps until
15 Days from the Date of this Notice,
and SCDHEC will receive written statements regarding the proposed work until
REGULATORY DIVISION
Refer to: General Permit # 2008-00328-6GF
March 18, 2013
30 Days from the Date of this Notice
from those interested in the activity and whose interests may be affected by the proposed work.
The District Engineer has concluded that the discharges associated with this project, both direct and
indirect, should be reviewed by the South Carolina Department of Health and Environmental Control in
accordance with provisions of Section 401 of the Clean Water Act. As such, this notice constitutes a request, on
behalf of the applicant, for certification that this project will comply with applicable effluent limitations and water
quality standards. The District Engineer will not process this application to a conclusion until such certification is
received. The applicant is hereby advised that supplemental information may be required by the State to facilitate
the review. Persons wishing to comment or object to Water Quality Certification must submit all comments in
writing to the S.C. Department of Health and Environmental Control at the above address within thirty (30) days of
the date of this notice.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. Implementation of the General Permit would impact
freshwater habitat upstream of estuarine substrates and emergent wetlands utilized by various life stages of
species comprising the red drum, shrimp, and snapper-grouper management complexes. Our initial
determination is that the General Permit would not have a substantial individual or cumulative adverse impact
on EFH or fisheries managed by the South Atlantic Fishery Management Council and the National Marine
Fisheries Service (NMFS). Our final determination relative to project impacts and the need for mitigation
measures is subject to review by and coordination with the NMFS.
The District Engineer has consulted the most recently available information and has determined that the
General Permit will have no effect on any Federally endangered, threatened, or proposed species and will not
result in the destruction or adverse modification of designated or proposed critical habitat. Provisions have been
made in the form of general conditions to the General Permit, which should prevent any effect to Federally
endangered, threatened, proposed species, or their critical habitat that the District Engineer is not aware of or may
have overlooked. This public notice serves as a request to the U.S. Fish and Wildlife Service and the National
Marine Fisheries Service for any additional information they may have on whether any listed or proposed
endangered or threatened species or designated or proposed critical habitat may be present in the area which
would be affected by the activity, pursuant to Section 7(c) of the Endangered Species Act of 1973 (as amended).
Pursuant to Section 106 of the National Historic Preservation Act (NHPA), this public notice also
constitutes a request to Indian Tribes to notify the District Engineer of any historic properties of religious and
cultural significance to them that may be affected by the proposed undertaking.
In accordance with the NHPA, the District Engineer has evaluated the proposed General Permit
regarding its potential to affect cultural resources including registered properties or properties listed as being
eligible for inclusion in the National Register. Provisions have been made in the form of general conditions to
the General Permit, which should prevent any adverse effect to cultural resources that the District Engineer is
not aware of are not overlooked; this public notice also serves as request to the State Historic Preservation
Officer to provide any information it may have with regard to impacts this General Permit may have in historic
and cultural resources.
Any person may request, in writing, within the comment period specified in this notice, that a public hearing
be held to consider this General Permit. Requests for a public hearing shall state, with particularity, the reasons
for holding a public hearing.
The decision whether to issue this General Permit will be based on an evaluation of the probable impact
including cumulative impacts of the activity on the public interest and will include application of the guidelines
promulgated by the Administrator, Environmental Protection Agency (EPA), under authority of Section 404(b) of
the Clean Water Act and, as appropriate, the criteria established under authority of Section 102 of the Marine
REGULATORY DIVISION
Refer to: General Permit # 2008-00328-6GF
March 18, 2013
Protection, Research and Sanctuaries Act of 1972, as amended. That decision will reflect the national concern for
both protection and utilization of important resources. The benefit which reasonably may be expected to accrue
from the project must be balanced against its reasonably foreseeable detriments. All factors which may be
relevant to the project will be considered including the cumulative effects thereof; among those are conservation,
economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values,
flood hazards, flood plain values, land use, navigation, shoreline erosion and accretion, recreation, water supply
and conservation, water quality, energy needs, safety, food and fiber production and, in general, the needs and
welfare of the people. A permit will be granted unless the District Engineer determines that it would be contrary to
the public interest. In cases of conflicting property rights, the Corps of Engineers cannot undertake to adjudicate
rival claims.
The Corps of Engineers is soliciting comments from the public; Federal, state, and local agencies and
officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this activity.
Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify,
condition or deny a permit for this project. To make this decision, comments are used to assess impacts on
endangered species, historic properties, water quality, general environmental effects, and the other public interest
factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an
Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the activity.
If there are any questions concerning this public notice, please contact Kristin Riegel at
803-253-3903.
General Permit No.
Name of Applicant:
Effective Date:
Expiration Date:
2008-00328-6GF
DUKE ENERGY AND LAKE FRONT PROPERTY OWNERS
.
.
.
DEPARTMENT OF THE ARMY
GENERAL PERMIT
A General Permit to perform work in or affecting waters of the United States, both navigable and non-navigable,
upon the recommendation of the Chief of Engineers, pursuant to Section 10 of the Rivers and Harbors Act of 1899
(33 U.S.C. 403), and Section 404 of the Clean Water Act (PL 92-500, 33 U.S.C. 1344), is hereby issued by the
authority of the Secretary of the Army by the
District Commander
U. S. Army Corps of Engineers
Charleston District
69A Hagood Avenue
Charleston, South Carolina 29403
to authorize, where such authorizations are required, the construction, repair and maintenance of private noncommercial piers, docks, boat lifts, moorings, boat houses, existing boat ramps, existing marine railways
maintenance for dry storage, boat shelters bulkheads, retainer walls, riprap, bio-engineering for erosion control,
heat exchange coils for heat pumps, minor intake pipes for residential irrigation, and minor excavation by the
adjacent shoreline property owners in the following lakes:
Lake
County
License
Project Boundary
Wylie (SC)
Fishing Creek
Great Falls
Rocky Creek
Wateree
Keowee
Ninety-Nine Island
Gaston Shoals (SC)
Robinson
York
Chester/Lancaster
Chester/Lancaster
Chester/Lancaster/Fairfield
Kershaw/Lancaster/Fairfield
Oconee/Pickens
Cherokee/York
Cherokee
Chesterfield/Darlington
2232
2232
2232
2232
2232
2503
2331
2332
569.4
417.2
355.8
284.4
225.5
varies 800.0 810.0
511.1
605.2
222
subject to the following conditions:
I. Authorized Activities and Special Conditions:
Please note: Activities regulated by the U.S. Army Corps of Engineers on Lake Keowee, Ninety-Nine Island,
Gaston Shoals, and Robinson are regulated under Section 404 of the Clean Water Act only and are not
regulated under Section 10 of the Rivers and Harbors Act.
1. Docks and Boat Lifts
a) Individual: Private docks, whether permanent, floating or a combination of both may not exceed the
square footage or length allowed in the current Shoreline Management Plan (SMP) or extend 1/3 the distance
across the affected waterway, whichever is less provided that they do not interfere with navigation, or ingress or
egress to any adjoining property. In some locations, such as narrow coves, the maximum size may not be
permitted or structures may not be permitted at all. Additionally, no new or expanded facilities will be authorized in
cove areas less than 25 ft. wide.
b) Common use structures between adjacent property owners are encouraged. A copy of the written
agreement between participating property owners must be furnished to Duke Energy.
c) All fixed pier decking (not including handrails) will be built at least one vertical foot above the referenced
full pond of each lake.
d) Hand railings are permissible provided that the sides of docks are not enclosed to obscure crossvision.
e) Structures built within the Project Boundaries must not contain sinks, toilets, showers, spigots, or any
other type of device, which could cause any liquid or solid waste to be discharged into the lake.
f) Flotation for all facilities and boat mooring buoys shall be of materials manufactured for marine use.
Materials must not lose significant buoyancy if punctured, must not generally be subject to damage by animals,
and must resist breaking apart under a broad range of wave energies. The uncoated, beaded polystyrene will
not be permitted for any new construction or as replacement for existing facilities. Reuse of plastic, metal, or
other previously used drums or containers for encasement or flotation purposes is prohibited. Existing
approved flotation is authorized until it has severely deteriorated and is no longer serviceable, at which time it
must be replaced with approved flotation.
g) Docks, boat houses, and boat shelters must be single-story structures. They may be roofed to allow
second story use (e.g. sundecks); however, the second story must not be roofed creating a two-story roofed
structure.
h) Private docks used to moor houseboats for habitation are not allowed by this General Permit.
Watercraft used for habitation shall not be moored at private docks. Permanent mooring must be at marinas
that provide pump-out facilities for marine sanitation devices.
i) Boat lifts and lifts for personal watercraft are permissible provided that they do not block cross-vision.
No more than two (2) jet ski lifts or jet docks per project-front lot will be allowed.
2. Erosion Control
a) All activities must not exceed 500 feet in length along the bank.
b) No material shall be placed in excess of the minimum needed for erosion protection, the activity will not
exceed an average of 1 cubic yard of material per running foot placed along the bank below full pond elevation.
c) Bio-engineering materials, such as vegetation, are encouraged whenever possible for bank stabilization
activities.
d) No materials shall be placed in a manner that would be eroded by normal or expected high flows or
wave action.
2.1 Rip-Rap: Rip-rap for erosion control at or below the full pond contour may be permitted provided the
rip-rap is placed against the existing erosional scarp and landward of any wetland vegetation to prevent the
loss of wetlands in areas compatible with the Duke Energy Shoreline Management Plan (SMP). The
placement of riprap is limited to the minimum necessary to adequately control erosion.
a) Rip-rap for erosion control must consist of clean stone free of all potential sources of pollution.
b) Rip-rap use should be limited to only that necessary to adequately stabilize the existing eroded
bank. Rip-rap must be confined to the area between six feet below the full pond elevation and full pond
elevation except where the entire placement is above the Federal Energy Regulatory Commission (FERC)
Project Boundaries or where severely eroded banks must be sloped back or terraced to provide minimum bank
stability and where permissible based on any local or state buffer requirements.
2.2. Bulkheads or Retainer Walls: Bulkheads or retainer walls must be constructed against the existing
erosional scarp and landward of any wetland vegetation to prevent the loss of wetlands in areas compatible with
the Duke Energy's SMP for stabilization. The recapturing of land by earthen fill will not be permitted.
a) Shoreline areas with an average eroded bank height < 2 foot can only be stabilized utilizing
approved bio-engineering techniques and enhanced riprap; seawalls are not allowed.
b) Bulkheads for erosion control must be constructed from pressure treated wood, metal, concrete,
vinyl, or fiberglass or some other suitable material that has received prior approval by Duke Energy.
c) Bulkhead backfill must consist of clean earthen materials free of all potential sources of pollution.
d) The backfill area must be stabilized with a vegetative cover after construction to minimize erosion.
3. Excavation
a) Only excavation that removes accumulated sediments is authorized under this General Permit.
Excavation below the original lake bed is not authorized by this General Permit.
b) The quantity of material to be excavated shall not exceed 150 cubic yards for each single and complete
project as required for removing accumulated sediments in order to maintain access.
c) All excavation work and equipment setup must be conducted directly in front of the individual's lot and
within the nearest one-third of the cove area and/or within the middle third of the cove area that is controlled by
Duke Energy, unless specific written authorization is given by the affected property owner(s) (typically through
their participation as co-applicants). Access channels must run perpendicular to the shoreline/project boundary
within the one-third of the cove nearest the applicant's property. Access channels and boat basins must not extend
beyond half the cove width in cove areas where the opposing is classified as Environmental (including 50-ft.
Environmental offsets) in Duke Energy's SMP.
d) All displaced soil must be moved above the project boundary in one handling and must be
contoured and seeded to prevent erosion. All disturbed shoreline and excavated material must be stabilized
(e.g. silt fencing, silt barriers, mulching, burlap) to prevent erosion and runoff into the lake. Best Management
Practices as defined by the state must be followed by placing all excavated material a minimum of 50 feet
landward of the full pond contour unless approved in writing by Duke Energy.
e) All excavation must be limited to that work necessary for reasonable access to deep water and may
not be located in or impact areas identified as Environmental, Natural and Impact Minimization Zones in the
Duke Energy's SMP where applicable. Excavation and any disturbance must be limited to that which is
absolutely necessary to achieve the project's stated purpose.
f) Access channels must be limited to a maximum bottom width of 10 feet. Side slopes must be
excavated to a slope of 3 to 1, except where safety requirements may dictate a more gradual slope of the sides
of the channel created.
g) The proposed excavation may not be for the purpose of creating additional shoreline, may not alter
the project boundary or the full pond contour.
h) Dredging activities must not occur during the months of March, April, May and June because of
potential impacts to spawning fish.
i) New excavations are not allowed within the 50-ft Environmental offset associated with an
Environmental classification identified in Duke Energy's SMP.
4. Fish Attractors, Reefs, Fishery Enhancement, and Aquaculture Activities
a) Authorized activities include placement of fish attractors and habitat structures, spawning bed
renovation, benthic barriers for aquatic weed control, and non native aquatic vegetation removal.
b) Only clean material, free of pollutants may be placed in the waterway. Typical structures authorized for
fish habitat include recycled Christmas trees, rip-rap, root wads, gravel and PVC structures.
c) Structures shall not pose a hazard to navigation. Certain clearances, as specified by Duke Energy, may
be required over structures placed on the bottom.
d) Structures may not cause an impact greater than 10 cubic yards.
5. Utility Lines
5.1 Subaqueous Utility Lines. A "utility line" is defined as any pipe or pipeline for the transportation of any
gaseous, liquid, liquefiable, or slurry substance, for any purpose, and any cable, line, or wire for the transmission
for any purpose of electrical energy, telephone and telegraph messages, and radio and television communication.
The term "utility line" does not include activities which drain a water of the United States, such as drainage tile,
however, it does apply to pipes conveying drainage from another area.
a) Utility line crossings, including discharges of material for backfill or bedding, are authorized
provided the land surface is restored to the pre-construction contours.
b) All buried utility lines must be installed a minimum of two (2) feet below the bottom elevation of the
lake.
c) The area of waters of the United States that is disturbed must be limited to the minimum necessary
to construct the utility line.
d)
Any exposed slopes and steambanks must be stabilized immediately upon completion of the utility
e)
Alignments which traverse shallow vegetated coves are not authorized by this General Permit.
line.
5.2 Overhead Powerlines and Communication Lines.
a) For overhead power and communications lines, refer to Department of the Army Regulations ER
1110-2-4401 dated 30 May 97. This regulation defines the minimum vertical clearances to be provided when
relocating or replacing existing power and communication lines or when constructing new power and
communication lines over waters of reservoir projects. Minimum vertical clearances over lake or reservoir
areas, where sailboats are commonly operated, shall be not less than the following.
b) Power line clearances shall be calculated with 15,850mm (52 feet) Reference Vessel Height (see
note C below) substituted for Reference Components in the National Electric Safety Code (NESC), Table A-2a.
c) Low voltage communication lines, as defined in Section 2 of the NESC, shall have a minimum
vertical clearance of 15,850mm (52 feet)
d) For those crossings that are located at the end of a cove or within other areas of the Lake Project
area that may not be suitable for sailboating authorized work may not be required to meet the minimum
clearance requirements if other appropriate clearances and safeguards are determined to be adequate. To
ensure that proposed clearances are determined to be adequate, applicants must notify Duke Energy Lake
Services and the U.S. Army Corps of Engineers and provide detailed plans of the proposed work. Written
approval from the U.S. Army Corps of Engineers must be granted prior to commencement of work.
e) All existing overhead lines that do not comply with this criteria will be required to come into
compliance by meeting the above requirements at such time upgrades are requested by the Utility Company.
Upgrades consist of underbuilds, increased voltage, and general maintenance and repairs.
f) The term Reference Vessel Height, as used in Category 1 above, is the vessels total height above
the water including mast and all appurtenances. It is based upon a vessel height of 14,630mm (48 feet),
including mast plus a 1,220mm (4 foot) antenna or other appurtenances to the mast, and it shall replace each
Water areas-sailboats Reference Component of Rule 232 in Table A-2a of Appendix A of NESC.
g) Copies of all new overhead powerline plans must be sent to the National Oceanic and Atmospheric
Administration (NOAA), National Ocean Service (NOS), for charting the utility line to protect navigation.
6. Debris Removal
a) Authorized debris removal includes the removal of debris such as stumps, tree limbs, appliances,
lumber, and metal objects, from any waterway for navigational, safety or drainage purposes only. Activities
authorized by this General Permit must be approved by Duke Energy.
b)
All debris must be properly disposed.
c) Living vegetation securely attached to the substrate is not considered debris and is not authorized
for removal.
d) Debris removal does not include the dredging or excavation of gravel, sand, silt, or clay. Proposed
excavation must comply with Section 3. above for authorization under this RGP.
7. Dock Anchors
a) Authorized activities include the use of anchors on the lake bottom to secure large docks and
docking facilities for safety purposes.
b) Dock anchors shall not hinder or pose a hazard to navigation.
c) Dock anchors must be constructed of durable materials as specified by Duke Energy.
8. Scientific Measuring Devices and Surveys
a) Authorized activities include use of devices whose purpose is to measure and record scientific data,
water quality monitoring stations, and survey activities including core sampling, bore holes, soil surveys, and
historic research surveys by Federal, state, or local agencies/government bodies or lessees.
b) Authorized activities shall not hinder or pose a hazard to navigation.
9. Mooring Structures
a) Authorized activities include the installation and maintenance of mooring structures.
b) Mooring structures, i.e., dolphins, pilings, or buoys must be placed in association with piers and
docks and shall not be located beyond the allowable distance of the current SMP from the full pond contour nor
extend more than 1/3 the distance across the waterway, whichever is less,. Mooring structures shall not be
located in front of the associated pier or dock nor shall they be located greater than 30' laterally from the pier or
dock.
c) All vessels secured to mooring structures must be moored in a manner which will not create any
hazards to navigation, or block boating access for others. Vessels secured to mooring structures shall not be
located beyond the allowable distance of the current SMP from the full pond contour nor extend more than 1/3
the distance across the waterway.
10. Boat Houses and Boat Shelters
a) Floating boat houses are permitted. Boat houses must be single-story structures. Boat shelters (pilings
with an attached roof) may be permitted provided the sides are not enclosed. Enclosed boat houses are not
permitted.
b) Flotation for all boat houses shall be of materials manufactured for marine use. Materials must not
lose significant buoyancy if punctured, must not generally be subject to damage by animals, and must resist
breaking apart under a broad range of wave energies. The uncoated, beaded polystyrene will not be permitted
for any new construction or as replacement for existing facilities. Reuse of plastic, metal, or other previously
used drums or containers for encasement or flotation purposes is prohibited. Existing approved flotation is
authorized until it has severely deteriorated and is no longer serviceable, at which time it must be replaced with
approved flotation.
c) Structures built within the Project Boundaries must not contain sinks, toilets, showers, spigots, or any
other type of device, which could cause any liquid or solid waste to be discharged into the lake. (Exception: Water
supply lines supporting approved pump-out facilities are exempted from this requirement.)
d) Boat shelters (pilings with an attached roof) are permitted. Boat shelters must be single-story
structures. Enclosed boat shelters or boat houses are not permitted.
11. Marine Railways
a) Maintenance of existing marine railways is authorized by this General Permit.
b) Marine railways extending from on-shore boat houses must not interfere with navigation or ingress or
egress to any adjoining property.
12. Buoys and Signs
a) Buoys and signs for the purpose of public information or safety may be authorized for Federal, state, or
local agencies/government bodies or lessees and must meet the requirements of the current SMP.
b) Buoys and signs shall not hinder or pose a hazard to navigation.
13. Heat Exchange Coils, Intake Pipes, Geothermal use, and Dry Hydrants
a) Intake pipes for irrigation associated with single-family residence and intake pipes associated with dry
hydrants may be placed along the bottom of the lake provided are buried two feet below the land surface of the
lake bottom and they do not interfere with navigation, ingress or egress to adjoining properties, or are in any
manner hazardous.
b) Intake pipes for irrigation and geothermal must be two (2) inches or smaller in diameter and should
be buried two feet below the land surface of the lake bottom or anchored to prevent them from floating to the
surface. The intake pipe should be located greater than three (3) feet below the surface where practicable.
c)
Intake pipes may not be installed in "environmentally sensitive areas" such as vegetated shallows.
d) The heating/coolant medium used within heat exchange coils must be water.
e) All supply and return piping for heat exchange coils must be buried a minimum of two (2) feet below the
lake bed and must comply Duke Energy's requirements for submarine utility lines.
f) Exposed portions of heat exchange coils and intake pipes must be anchored to the lake bottom to
prevent them from floating to the surface.
g) Material excavated to install heat exchange coils or irrigation pipes that is not used as backfill material
within the excavated trench must be disposed properly in uplands.
f) Clean stone free of all potential sources of pollution may be used as backfill within the excavated trench
provided there is no change in preconstruction contours.
II. GENERAL CONDITIONS:
a. This General Permit authorizes only those structures and activities specifically addressed below. The
permittee must obtain Department of the Army authorization, such as the issuance of an individual permit, for all
other activities that are regulated pursuant to Section 10 of the Rivers and Harbors Act or Section 404 of the Clean
Water Act within the waters of the above referenced lakes.
b. All activities identified and authorized herein shall be consistent with the terms and conditions of this
General Permit; any variance not specifically identified and authorized herein shall constitute a violation of the
terms and conditions of this permit which may result in the modification, suspension, or revocation of the
authorization, as set forth more specifically in General Condition h. below and in the institution of such legal
proceedings as the United States Government may consider appropriate.
c. All structures authorized by this General Permit shall be designed, located, and/or operated to allow the
full and free use by the public of all navigable waters.
d. Activities or structures authorized by this General Permit shall not encroach across any adjacent property line or
the imaginary lakeward extension of any adjacent property line without the written permission of the affected
property owner.
e. The permittee must make every reasonable effort to conduct the work authorized herein in a manner so as
to minimize any adverse impact to fish, wildlife, and other environmental resources (e.g. native riparian vegetation).
f. The permittee must make every reasonable effort to conduct the work authorized herein in a manner so
as to minimize any degradation of water quality.
g. The permittee shall allow the District Commander or his authorized representative(s) to make periodic
inspections at any time deemed necessary in order to assure that the activity being performed under authority of
this permit is in accordance with the terms and conditions prescribed herein.
h. Authorization of a specific work or structure authorized herein may be summarily suspended in whole or
in part upon a finding by the District Commander that immediate suspension would be in the general public interest
or there has been a violation of any terms and conditions of this permit. Such suspension shall be effective upon
receipt by the permittee of a written notice thereof which shall indicate (1) the extent of the suspension, (2) the
reasons for this action, and (3) any corrective or preventative measures to be taken by a permittee which are
deemed necessary by the District Commander to abate imminent hazards to the general public interest. A
permittee shall take immediate action to comply with the provisions of this notice. Within ten (10) days following
the receipt of this notice of suspension, the permittee may request a meeting with the District Commander or a
public hearing to present information relevant to a decision whether their permit should be reinstated, modified, or
revoked. If a public hearing is requested it shall be conducted pursuant to procedures prescribed by the Chief of
Engineers. After completion of the public hearing or within a reasonable time after issuance of the suspension
notice to the permittee if no hearing is requested, the authorization of the specific work or structure will be
reinstated, modified, or revoked. Any modification, suspension, or revocation of authorization under this General
Permit shall not be the basis for any claim for damages against the United States.
i. That the permittee, upon receipt of a notice from the District Commander for failure to comply with the
terms, conditions, or standards of this General Permit shall, within 60 days without expense to the United States
and in such manner as directed by the District Commander or his authorized representative(s), effect compliance
with the terms, conditions, and standards or remove the previously authorized structure.
j. This General Permit does not convey any property rights, either in real estate or material, or any
exclusive privileges; and it does not authorize any injury to property or invasion of rights or any infringement of
Federal, State, or local laws or regulations or Federal Energy Regulatory Commission regulations, nor does it
obviate the requirement to obtain other Federal, State, local or Duke Energy assent or to comply with any
applicable standards required by ordinance for the activities authorized herein. Other Federal, State, or local
agencies and/or Duke Energy are not limited by this document and may impose more stringent requirements than
those identified in this document.
k. This General Permit does not authorize work or structures within areas that are mapped as Environmental in
the Duke Energy's SMP.
l. That the permittee recognizes the possibility that works or structures authorized herein may be subject to
damage by wave wash from passing vessels and wind-driven waves. The issuance of this General Permit does not
relieve the permittee from taking all proper steps to ensure the integrity of works permitted herein and the safety of
boats moored thereto from damage by wave wash and the permittee shall not hold the United States liable for any
such damage.
m. That the permittee shall maintain the work or structure authorized herein in good condition. If and when
a permittee desires to abandon an authorized structure, unless such abandonment is part of a transfer procedure
by which the individual is transferring ownership of the structure, the permittee may be required to remove the
structure.
n. That if the display of lights and signals on any structure authorized herein is not otherwise provided for
by law, such lights and signals as may be prescribed by the United States Coast Guard shall be installed and
maintained by and at the expense of the permittee.
o. That the term "permittee" means the individual authorized by the District Commander to accomplish work
under this General Permit. The activities authorized under this permit are for private, non-commercial use. Work
will not be considered private if its planned or ultimate purpose is commercial or industrial in nature, it is in support
of operations that charge for the production, distribution, or sale of goods or service, or it will be for the use of the
general public.
p. The prospective permittee must notify the District Commander if the activity authorized by this General
Permit may affect any federally listed threatened or endangered species, a species proposed for listing, or
designated critical habitat. The activity is not authorized until the District Commander determines that the
requirements of the Endangered Species Act have been satisfied.
q. The prospective permittee must notify the District Commander if the activity authorized by this General
Permit may affect any historic properties listed, or which may be eligible for listing on the National Register of Historic
Places. The activity is not authorized until the procedures for the protection of cultural resources (Appendix C to 33
CFR 325) have been completed on the eligible property or structure.
r. If the permittee, prior to or during the performance of the work authorized herein, encounters previously
unidentified archeological remains or cultural resources within the area subject to Department of the Army
authorization, the permittee agrees to cease work and contact the District Commander, so that further coordination
with the South Carolina Institute of Archaeology and Anthropology, the South Carolina Department of Archives and
History or the appropriate Tribal Historic Preservation Office may be conducted.
s. This general permit relates only to activities authorized herein and does not convey the right to place any
structures for any nonwater-related commercial use on or adjacent to any pier, dock, moorings, boat houses,
marine railways for dry storage, bulkheads, retainer walls, and/or riprap without the prior approval of the District
Commander.
t. The permitee understands and agrees that, if future operations by the United States require the removal,
relocation, or other alteration, of the structure or work herein authorized, or if, in the opinion of the Secretary of the
Army or his authorized representative, said structure or work shall cause unreasonable obstruction to the free
navigation of the navigable waters, the permittee will be required, upon due notice from the Corps of Engineers, to
remove, relocate, or alter the structural work or obstructions caused thereby, without expense to the United States.
No claim shall be made against the United States on account of any such removal or alteration.
III. PROHIBITED ACTIVITIES:
All work that exceeds the terms and conditions specified herein is prohibited unless an Individual or
Nationwide Department of the Army Permit has been obtained from the Corps of Engineers. All work for purposes
other than those specified herein is expressly not authorized by this document.
IV. REQUIRED AUTHORIZATIONS:
(a) Prior to performing the work authorized herein within the prescribed geographical limits of this General
Permit, the permittee must obtain written authorization from Duke Energy's Lake Services Office. Applicants may
contact Lake Services at 1-800-443-5193.
(b) All lakes within the Catawba-Wateree basin and Lake Keowee are also subject to the current SMP that
has been developed by Duke Energy and approved by the FERC. The SMP is administered by Duke Energy.
(c) Prior to performing any of the work authorized herein that entails discharges of dredged or fill
material into navigable waters, the permittee will either confirm that the proposed project complies with the
attached South Carolina General Permit # 87-14-001 (Revised 2007) or obtain a Permit to
Construct in Navigable Waters from the South Carolina Department of Health and Environmental Control
pursuant to R. 19-450. et. eq., 1976 S.C. Code of Laws, as amended.
V. PENALTIES FOR VIOLATIONS:
Authorization obtained under this General Permit limits the size, length and use of structures. Any deviation
from the specifications, or other terms or conditions of the General Permit shall constitute a violation of the Section
10 of the Rivers and Harbors Act and/or Section 404 of the Clean Water Act, and may result in the District
Commander seeking judicial relief to have the permittee remove the structure or work and/or restore the project
area to its former condition, as well as the imposition of penalties as provided by law.
VI. REVOCATION OF THE GENERAL PERMIT:
This permit may be revoked by issuance of a public notice at any time the District Commander determines that
the cumulative effects of the activities authorized herein have an adverse effect on the public interest. Following
such revocation, any future activities in areas covered by this General Permit will be processed as Individual or
Nationwide Permits.
VII. REPORTING OF ACTIVITIES AUTHORIZED BY THE GENERAL PERMIT
Duke Energy Company has agreed to furnish the Corps of Engineers with a monthly tabulation and pertinent
information on all work or activities authorized under this General Permit, including the location and type of
construction. The report is due by the 25th day of the following month.
VII. DURATION OF THE GENERAL PERMIT.
This General Permit will cover activities started within five (5) years and completed within six (6) years after the
date of issuance unless this permit is revoked in the interim. Revoking the General Permit will not affect work
performed in accordance with the conditions stated herein. At the end of the first year and every succeeding year,
the Corps of Engineers and the Federal and State regulatory and resource agencies will jointly review activities
authorized by this General Permit to determine if significant cumulative impacts have resulted. If the District
Commander determines revocation of this permit, in whole or in part, may be in order
due to cumulative impacts, a public notice of the intention will be issued and after a review of all additional data
submitted, action will be taken to amend, modify or revoke this permit as appropriate. Revocation of the General
Permit will not affect the work that had been authorized when the General Permit was in effect if such work is in
accordance with the provisions contained herein.
This permit becomes effective when the Federal official, designated to act for the Secretary of the Army, has
signed below.
This permit shall become effective on the date of the District Commander's signature.
BY AUTHORITY OF THE SECRETARY OF THE ARMY:
__________________________________
Edward P. Chamberlayne, P.E.
Lieutenant Colonel, EN
Commander, U.S. Army Engineer District, Charleston
or his Designee
Tina B. Hadden
Chief, Regulatory Division
________________________
Date