The U.S. Army Corps of Engineers, Albuquerque District (Corps), is evaluating a permit application from Christi and Isaac Dean to construct a single-family residence in an existing subdivision. The project will result in permanent impacts to approximately 0.04 acre of waters of the United States adjacent to the Conejos River. The purpose of this public notice is to inform interested parties of the project and to solicit comments.
SPA-2013-00433 – Christi and Isaac Dean – Horca Subdivision
Posted: April 14, 2014
Expiration date: April 29, 2014
SUBJECT: Public Notice for the Christi and Isaac Dean Project – Horca Subdivision
SUMMARY: The U.S. Army Corps of Engineers, Albuquerque District (Corps), is evaluating a permit application from Christi and Isaac Dean to construct a single-family residence in an existing subdivision. The project will result in permanent impacts to approximately 0.04 acre of waters of the United States adjacent to the Conejos River. The purpose of this public notice is to inform interested parties of the project and to solicit comments.
AUTHORITY: This application is being evaluated under Section 404 of the Clean Water Act for the discharge of dredged or fill material in waters of the United States (U.S.).
APPLICANT: Christi and Isaac Dean, 121 Vereda de Valencia, Santa Fe, NM 87507-3026
LOCATION: The project site is located in Horca Subdivision, Tract 5, Lot 52, Section 6, Township 33 North, Range 6 East, Latitude 37.1299 North, Longitude -106.3532 West, Conejos County, Colorado
PROJECT DESCRIPTION: The applicant is proposing to construct a cabin with a driveway and septic system in Horca subdivision in southwestern Conejos County, Colorado. The Corps issued a permit for construction of the subdivision in 1986. The permit allowed limited fill for house pads, driveways and roads. All lots in the subdivision have been sold to individuals, and it is partially built-out with six of the twelve lots with wetlands having homes. The permit expired in 1990; therefore, individual lot owners must receive permits for additional impacts to wetlands.
The lot for the proposed project is approximately 0.46 acre, of which approximately 0.25 acre is wetlands. The project would place 21 concrete footers measuring 30 inches by 30 inches each to support concrete piers for construction of a cabin with a deck. The cabin and deck would be elevated 18 inches above ground level and would have skirting around the bottom to enclose the area. The total area of the cabin and deck is 32 feet by 38 feet, with most of the footprint wetlands. A septic vault measuring 8 feet by 8 feet, with no drain field, also would be buried in wetlands. A gravel driveway and parking area would be installed on grade, partially in wetlands.
PURPOSE AND NEED: The purpose of the project is to provide housing. The project is needed to construct a cabin on a lot within the previously permitted Horca Subdivision.
PROPOSED MITIGATION: Since wetland impacts associated with the proposed project are less than 0.10 acres, and there are no anticipated significant secondary or cumulative impacts, no compensatory mitigation is required. The applicant proposes to adhere to best management practices and will avoid future impacts to all remaining wetlands.
OTHER AUTHORIZATIONS: State Water Quality Certification: The applicant is required to obtain water quality certification, under Section 401 of the Clean Water Act, from the Colorado Department of Public Health and Environment. Section 401 requires that any applicant for an individual Section 404 permit provide proof of water quality certification to the Corps of Engineers prior to permit issuance.
ADDITIONAL INFORMATION:
Environmental Setting. The subject building lot is located within the Horca Subdivision. It is a triangular lot with existing gravel roads and ditches on two sides. A long and narrow area of uplands dissects the southern part of the lot. The remaining area is considered to be marginal wetlands with little discernible elevation change from the uplands. The wetlands are dominated by grasses and willows.
Alternatives. The applicant has provided information concerning project alternatives. The applicant considered building the cabin in the uplands, but setback requirements would not accommodate the location.
EVALUATION FACTORS: The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the described activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the described activity will be considered, including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people. The activity's impact on the public interest will include application of the Section 404(b)(1) guidelines promulgated by the Administrator, Environmental Protection Agency (40 CFR Part 230).
The Corps is soliciting comments from the public, Federal, State, and local agencies and officials, Indian tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
HISTORIC PROPERTIES: A cultural resources survey was conducted at the time that the subdivision was originally permitted. The Corps has determined that the project will have no effect to cultural resources.
ENDANGERED SPECIES: The Corps has reviewed the U.S. Fish and Wildlife Service's latest published version of Federally-listed endangered and threatened species located in Conejos County, Colorado, to determine if any listed species or their critical habitat may occur in the proposed project area. The Corps has made a preliminary determination that the proposed project will not affect any Federally-listed endangered or threatened species or their critical habitat that are protected by the Endangered Species Act.
FLOODPLAIN MANAGEMENT: The Corps is sending a copy of this public notice to the local floodplain administrator. In accordance with 44 CFR part 60 (Flood Plain Management Regulations Criteria for Land Management and Use), the floodplain administrators of participating communities are required to review all proposed development to determine if a floodplain development permit is required and maintain records of such review.
CLOSE OF COMMENT PERIOD: All comments pertaining to this Public Notice must reach this office on or before April 29, 2014, which is the close of the comment period. Extensions of the comment period may be granted for valid reasons provided a written request is received by the limiting date. If no comments are received by that date, it will be considered that there are no objections. Anyone may request, in writing, that a public hearing be held to consider this application. Requests shall specifically state, with particularity, the reason(s) for holding a public hearing. If the Corps determines that the information received in response to this notice is inadequate for thorough evaluation, a public hearing may be warranted. If a public hearing is warranted, interested parties will be notified of the time, date, and location. Comments and requests for additional information should be submitted to:
Hildreth Cooper, Project Manager
US Army Corps of Engineers, Albuquerque District
1970 E. Third Avenue, Suite 109
Durango, CO 81301
(970) 259-1582
FAX: (970) 259-1658
E-mail: hildreth.l.cooper@usace.army.mil
Please note that names and addresses of those who submit comments in response to this public notice may be made publically available through the Freedom of Information Act.