Supplemental Environmental Assessment (SEA) that has been prepared
for the Seven Oaks Dam (SOD) Updated Water Control Plan To Include Regulation for Water
Quality (May 2014), San Bernardino County, California.
The U.S. Army Corps of Engineers (Corps), in coordination with the non-Federal sponsors,
San Bernardino County Flood Control District (SBCFCD), Orange County Flood Control
District (OCFCD), and Riverside County Flood Control and Water Conservation District
(RCFC&WCD), proposes to update the original SOD Water Control Plan (WCP) contained in
the Water Control Manual (Sep 2003) to include regulation for water quality. The main change
from the 2003 WCP introduced in the Updated Water Control Plan (May 2014) “2014 WCP” of
the Water Control Manual (WCM) is with respect to the debris pool operation only. The 2014
WCP requires that the debris pool be built only during a significant runoff event, and then
released completely down to the top of sediment pool elevation as soon as the runoff event
passes during the flood seasons. The original WCP required that flows be restricted to 3 cubic
feet per second (cfs) beginning 1 October to start the building of the seasonal debris pool. This
requirement will no longer apply in the 2014 WCP. No other modifications are necessary to the
existing physical components of Seven Oaks Dam and Reservoir in order to implement the 2014
WCP for water quality improvements.