BOATHOUSE ON BAYOU TERRE AUX BOEUFS IN ST. BERNARD PARISH
NAME OF APPLICANT: Delacroix Houseboat Club, LLC c/o Lamulle Construction, LLC at 4978 Pontchartrain Drive, Slidell, Louisiana 70458.
LOCATION OF WORK: Left descending bank of Bayou Terre aux Boeufs, at 5557 Delacroix Highway, in St. Bernard Parish, Louisiana, as shown on the attached drawings.
HUC: 08090203; Eastern Louisiana Coastal
CHARACTER OF WORK: To remove an existing pier and install and maintain a39' x 80' boathouse with five slips adjacent to an existing bulkhead. The structures will extend 39’ into the bayou, which is approximately 220’ wide at this location. All work will be accomplished from the water. This is a modification to an existing permit issued September 13, 2013. No adverse impacts to special aquatic sites are proposed; no compensatory mitigation is anticipated at this time.
DEPARTMENT OF THE ARMY
NEW ORLEANS DISTRICT, CORPS OF ENGINEERS
P.O. BOX 60267
NEW ORLEANS, LOUISIANA 70160-0267
REPLY TO
ATTENTION OF
July 7, 2014
Operations Division
Eastern Evaluation Section
(504) 862-2045
jennifer.e.burkett@usace.army.mil
Project Manager
Jennifer Burkett
SUBJECT: MVN 2013-0997 EBB
PUBLIC NOTICE
Interested parties are hereby notified that a permit application has been received
by the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X]
Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC
403); and/or [ ] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344).
BOAT HOUSE ON BAYOU TERRE AUX BOEUFS IN ST. BERNARD PARISH
NAME OF APPLICANT: Delacroix Houseboat Club, LLC c/o Lamulle Construction,
LLC at 4978 Pontchartrain Drive, Slidell, Louisiana 70458.
LOCATION OF WORK: Left descending bank of Bayou Terre aux Boeufs, at 5557
Delacroix Highway, in St. Bernard Parish, Louisiana, as shown on the attached
drawings.
HUC: 08090203; Eastern Louisiana Coastal
CHARACTER OF WORK: To remove an existing pier and install and maintain a
39' x 80' boat house with five slips adjacent to an existing bulkhead. The structures will
extend 39' into the bayou, which is approximately 220' wide at this location. All work will
be accomplished from the water. This is a modification to an existing permit issued
September 13, 2013. No adverse impacts to special aquatic sites are proposed; no
compensatory mitigation is anticipated at this time.
The comment period for the Department of the Army Permit will close 15 days
from the date of this public notice. Written comments, including suggestions for
modifications or objections to the proposed work, stating reasons therefore, are being
solicited from anyone having interest in this permit request. Letters must reference the
applicant's name and the subject number, be addressed and mailed to the above
address, ATTENTION: REGULATORY BRANCH. Individuals or parties may
request an extension of time in which to comment on the proposed work by
writing or e-mailing the Corps of Engineers Project Manager listed above. Any
request must be specific and substantively supportive of the requested
-2-
extension, and received by this office prior to the end of the initial comment
period. The Section Chief will review the request and the requestor will be
promptly notified of the decision to grant or deny the request. If granted, the time
extension will be continuous to the initial comment period and, inclusive of the
initial comment period, will not exceed a total of 30 calendar days.
The decision whether to issue a permit will be based on an evaluation of the
probable impacts, including cumulative impacts of the proposed activity on the public
interest. That decision will reflect the national concern for both protection and utilization
of important resources. The benefit which reasonably may be expected to accrue from
the proposal must be balanced against its reasonably foreseeable detriments. All
factors which may be relevant to the proposal will be considered including the
cumulative effects thereof; among those are conservation, economics, aesthetics,
general environmental concerns, wetlands, historic properties, fish and wildlife values,
flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food and
fiber production, mineral needs, considerations of property ownership and, in general,
the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public,
federal, state, and local agencies and officials, Indian Tribes, and other interested
parties in order to consider and evaluate the impacts of this proposed activity. Any
comments received will be considered by the U.S. Army Corps of Engineers to
determine whether to make, modify, condition, or deny a permit for this proposal. To
make this decision, comments are used to assess impacts on endangered species,
historic properties, water quality, general environmental effects, and other public interest
factors listed above. Comments are used in the preparation of an Environmental
Assessment and/or an Environmental Impact Statement pursuant to the National
Environmental Policy Act. Comments are also used to determine the need for a public
hearing and to determine the overall public interest of the proposed activity.
The New Orleans District is unaware of properties listed on the National Register
of Historic Places near the proposed work. The possibility exists that the proposed work
may damage or destroy presently unknown archeological, scientific, prehistorical,
historical sites, or data. Issuance of this public notice solicits input from the State
Archeologist and State Historic Preservation Officer regarding potential impacts to
cultural resources.
Our initial finding is that the proposed work would neither affect any species
listed as endangered by the U.S. Departments of Interior or Commerce, nor affect any
habitat designated as critical to the survival and recovery of any endangered species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of
the Magnuson-Stevens Fishery Conservation and Management Act. The applicant's
proposal would result in the destruction or alteration of N/A acre of EFH utilized by
various life stages of red drum and penaeid shrimp. Our initial determination is that the
proposed action would not have a substantial adverse impact on EFH or federally
managed fisheries in the Gulf of Mexico. Our final determination relative to project
impacts and the need for mitigation measures is subject to review by and coordination
with the National Marine Fisheries Service.
-3-
If the proposed work involves deposits of dredged or fill material into navigable
waters, the evaluation of the probable impacts will include the application of guidelines
established by the Administrator of the Environmental Protection Agency. Also, a
certification that the proposed activity will not violate applicable water quality standards
will be required from the Department of Environmental Quality before a permit is issued.
The applicant has certified that the proposed activity described in the application
complies with and will be conducted in a manner that is consistent with the Louisiana
Coastal Resources Program. The Department of the Army permit will not be issued
unless the applicant received approval or a waiver of the Coastal Use Permit by the
Department of Natural Resources.
Any person may request, in writing, within the comment period specified in this
notice, that a public hearing be held to consider this application. Requests for public
hearings shall state, with particularity, the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any
other parties whom you deem likely to have interest in the matter.
Michael V. Farabee
Chief, Eastern Evaluation Section