You can copy from here when filling out the rest of the page.
MAINTENANCE DREDGING AND MARSH CREATION IN ST MARY PARISH
Name of Applicant: St. Mary Parish Government,C/O: CB&I, 197 Elysian Drive, ATTN: Charlotte Liner, Houma, LA 70363, Terrebonne Parish.
Location of Work: (N: 29.47764, W: -91.27153) Along the east bank of the Lower Atchafalaya River and Deer Island Pass in St. Mary Parish, Louisiana, HUC 08080101, Atchafalaya River Basin.
Character of Work: Conduct excavation activities to dredge 3,500 linear feet by 206 feet wide of channel bottom to accelerate deltaic land building in the northeast portion of Atchafalaya Bay, by allowing increased water and sediment flow through Deer Island Pass. Dredged sediments will be placed beneficially to a settled elevation of 0.80 to 1.05 feet NAVD 88, all to create 28 acres of marsh in shallow open water, within Deer Island Pass. Project implementation will impact 58 acres of water bottoms only and is not expected to include impacts to vegetated wetlands.
JOINT PUBLIC NOTICE
July 7, 2014
U.S. Army Corps of Engineers
New Orleans District
Regulatory Branch
Post Office Box 60267
New Orleans, LA 70160-0267
State of Louisiana
Department of Environmental Quality
ATTN: Water Quality Certifications
Post Office Box 4313
Baton Rouge, LA 70821-4313
Project Manager: Michael H. Herrmann
(504) 862-1954
Michael.h.herrmann@usace.army.mil
DA Permit Number: MVN-2011-00184-WLL
Project Manager: Elizabeth Johnson
(225) 219-3225
WQC Number: WQC 130919-02
Interested parties are hereby notified that a permit application has been received by the New Orleans
District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and Harbors Act
of March 3, 1899 (30 Stat. 1151; 33 U.S.C. 403); and/or [X] Section 404 of the Clean Water Act (86
Stat. 816; 33 U.S.C. 1344).
Application has also been made to the Louisiana Department of Environmental Quality for a Water
Quality Certification (WQC) in accordance with statutory authority contained in La. R.S. 30:2074(A)(3)
and provisions of Section 401 of the Clean Water Act (P.L. 95-217; 33 U.S.C. 1341).
MAINTENANCE DREDGING AND MARSH CREATION IN ST MARY PARISH
Name of Applicant: St. Mary Parish Government,C/O: CB&I, 197 Elysian Drive, ATTN: Charlotte
Liner, Houma, LA 70363, Terrebonne Parish.
Location of Work: (N: 29.47764, W: -91.27153) Along the east bank of the Lower Atchafalaya River
and Deer Island Pass in St. Mary Parish, Louisiana, HUC 08080101, Atchafalaya River Basin.
Character of Work: Conduct excavation activities to dredge 3,500 linear feet by 206 feet wide of channel
bottom to accelerate deltaic land building in the northeast portion of Atchafalaya Bay, by allowing
increased water and sediment flow through Deer Island Pass. Dredged sediments will be placed
beneficially to a settled elevation of 0.80 to 1.05 feet NAVD 88, all to create 28 acres of marsh in shallow
open water, within Deer Island Pass. Project implementation will impact 58 acres of water bottoms only
and is not expected to include impacts to vegetated wetlands.
The comment period for the Department of the Army (DA) permit application and the Louisiana
Department of Environmental Quality WQC will close 20 days from the date of this joint public notice.
Written comments, including suggestions for modifications or objections to the proposed work, stating
reasons thereof, are being solicited from anyone having interest in this DA permit and WQC request
and must be mailed, so as to be received before or by the last day of the comment period. Letters
concerning the DA permit application must reference the applicant's name and the DA Permit Number,
and be mailed to the U.S. Army Corps of Engineers at the address above.
ATTENTION REGULATORY BRANCH: Similar letters concerning the WQC must reference the
applicant's name and the WQC Number and be mailed to the Louisiana Department of
Environmental Quality at the address above. Individuals or parties may request an extension of time
in which to comment on the proposed work by writing or e-mailing the Project Manager listed above.
Any request must be specific and substantively supportive of the requested extension, and received by
this office prior to the end of the initial comment period. The Section Chief will review the request and
the requestor will be promptly notified of the decision to grant or deny the request. If granted, the time
extension will be continuous to the initial comment period and, inclusive of the initial comment period,
will not exceed a total of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of Environmental
Quality and may be examined weekdays between 8:00 a.m. and 4:30 p.m. Copies may be obtained
upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable impacts,
including cumulative impacts of the proposed activity on the public interest. That decision will reflect the
national concern for both protection and utilization of important resources. The benefit which
reasonably may be expected to accrue from the proposal must be balanced against its reasonably
foreseeable detriments. All factors which may be relevant to the proposal will be considered, including
the cumulative effects thereof; among these being: conservation, economics, aesthetics, general
environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain
values, land use, navigation, shoreline erosion and accretion, recreation, water supply and
conservation, water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local
agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the
impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of
Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make
this decision, comments are used to assess impacts on endangered species, historic properties, water
quality, general environmental effects, and other public interest factors listed above. Comments are
used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement
pursuant to the National Environmental Policy Act. Comments are also used to determine the need for
a public hearing and to determine the overall public interest of the proposed activity.
No properties listed on the National Register of Historic Places are known to be near the proposed
work. The possibility exists that the proposed work may damage or destroy presently unknown
archeological, scientific, prehistoric, or historical sites or data. Issuance of this public notice solicits
input from the State Archeologist and State Historic Preservation Officer regarding potential impacts to
cultural resources.
Our initial finding is that the proposed work would neither affect any species listed as endangered
by the U.S. Departments of Interior or Commerce, nor affect any habitat designated as critical to the
survival and recovery of any endangered species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the
destruction or alteration of 58 acres of EFH utilized by various life stages of red drum and penaeid
shrimp. Our initial determination is that the proposed action would not have a substantial adverse
impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to
project impacts and the need for mitigation measures is subject to review by and coordination with the
National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters, the
evaluation of the probable impacts will include the application of guidelines established by the
Administrator of the U.S. Environmental Protection Agency. Also, a certification that the proposed
activity will not violate applicable water quality standards will be required from the Louisiana
Department of Environmental Quality before a permit is issued.
The applicant has certified that the proposed activity described in the application complies with and
will be conducted in a manner that is consistent with the Louisiana Coastal Resources Program. The
Department of the Army permit will not be issued unless the applicant receives approval or a waiver of
the Coastal Use Permit by the Louisiana Department of Natural Resources.
Any person may request, in writing, within the comment period specified in this notice, that a public
hearing be held to consider this application. Requests for public hearings shall state, with particularity,
the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any other parties
whom you deem likely to have interest in the matter.
Darrell S. Barbara
Chief, Western Evaluation Section
Regulatory Branch
Enclosure