Dredging is proposed within Spicers Creek, Cape Island Creek, Schellengers Creek, and Devils Reach in the City of Cape May, Cape May County, New Jersey. The dredged material would be disposed within the U.S. Army Corps of Engineers Cape May confined disposal facility (see Enclosure 1 & 2).
The applicant proposes to perform hydraulic maintenance dredging within the aforementioned waterways (see Enclosures 3 - 7). According to the applicant, approximately 79,578 cubic yards of material will be removed from 2,300 linear feet of Spricers Creek, 6,488 cubic yards of material from 945 linear feet of Cape Island Creek, 7,582 cubic yards of material from 2,400 linear feet of Schellengers Creek, and 3,954 cubic yards of material from 615 linear feet of Devils Reach. The material is approximately 25% sand and 75% silts and clay. Composite sediment samples for each waterway were collected and analyzed for bulk sediment chemistry and subject to the modified elutriate procedure. The results indicate that the material is suitable for hydraulic discharge into the CDF and is not anticipated to adversely impact the receiving waterbody.
All material will be disposed within the U.S. Army Corps of Engineers confined disposal facility located adjacent to the Cape May Canal just west of the aforementioned waterways. The hydraulic pipeline carrying dredged material will be located parallel to and floating within the waterways being dredged. Once past the mouth of Spicers Creek, the dredge pipline will run parallel to the shoreline of the Cape May Canal to the Corps CDF.
This office previously approved dredging within the subject waterways and the placement of dredged material at the Corps CDF in 2005 (see file number CENAP-OP-R-200500508-46). Derdeging was last performed in 2006. The applicant has requested a 10 year maintenance provision be included within the Department of the Army permit.