Tom Taylor is the Regulatory point-of-contact for this permit application from the Port of Portland for work on the Willamette River's southwest bank at River Mile 10.
Public Notice for Permit Application
Issue Date: August 7, 2012
Expiration Date: September 6, 2012
US Army Corps of Engineers No: NWP-2007-240/2
30-Day NoticeOregon Department of State Lands No: 50468-RP
Interested parties are hereby notified that an application has been received for a Department of the Army permit for certain work in waters of the United States, as described below and shown on the attached plan.
Comments: Comments on the described work should reference the U.S. Army Corps of Engineers number shown above and reach this office no later than the above expiration date of this Public Notice to become part of the record and be considered in the decision. Comments should be mailed to the following address:
U.S. Army Corps of Engineers
Tom Taylor (thomas.j.taylor@usace.army.mil)
P.O. Box 2946
Portland, OR 97208-2946
Applicant: Port of Portland, 7200 NE Airport Way, Portland, OR 97218
Location: All of the proposed project sites are located in Portland, Multnomah Co., OR, as follows:
Dredge Sites:
* Terminal 2 (berths 203, 204, 205, and 206) is located on the southwest bank of the Willamette River at River Mile (RM) 10, within Township (T) 1 North (N), Range (R) 1 East (E), Sections (S) 20, 21, and 28. Terminal 2 is located within the U.S. Environmental Protection Agency-designated Portland Harbor Superfund Study Area on the National Priorities List, pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, as amended (42 U.S.C. § 9601, et seq.).
* Terminal 4 (berths 401, 410, 411, 414, 415, and 416) is located on the east bank of the Willamette River between RM 4 and 5, within T2N, R1W, S35; as well as T1N, R1W, S2. Six of the total berths are included for berth maintenance. Terminal 2 is located within the EPA-designated Portland Harbor Superfund Study Area on the NPL, pursuant to CERCLA.
* Terminal 5 (berths 50, including barge and face sides, 502, and 503) is located on the east bank of the Willamette River between RM 1 and 2, within T2N, R1W, S23.
* Terminal 6 (berths 601, 603, 604, 605, and 607) is located on the south bank of the Columbia River between RM 102 and 104, within T2N, R1W, S24; and within T2N, R1E, S30.
Dredged Material Placement Site Options:
* West Hayden Island Upland Placement Site is located on the northwest side of Hayden Island (RM 104-105).
* Suttle Road Rehandle Facility is located on the south bank of North Portland Harbor near RM 2 (Columbia RM 104.5).
* In-water placement site is located at RM 102.2 on the Oregon side of the Columbia River between the western tip of West Hayden Island and Kelley Point Park.
Waterway: See above under “Location” for each terminal.
Project Description: The Port proposes to continue berth maintenance, as-needed, at the terminals and berths identified above under “Location.” The annual maintenance need at any berth is influenced by flow conditions, sedimentation rates, and economic conditions. The estimated total volume of dredged material removed from all berthing areas would average between 15,000 to 40,000 cubic yards per year over the ten-year permit duration. Maintenance depths, overdepth allowances, maintenance frequencies, etc., for each berth are specified in Table 1.
Advanced maintenance incorporated within the overdepth allowance could reduce the frequency of future berth maintenance. The Port may utilize a variety of berth dredging methods (mechanical clamshell, backhoe dredging, and underwater grading) and placement sites (in-water, upland, or landfill) during the proposed program.
Dredging Methods
Clamshell Dredging Using an “Environmental” Bucket and Transport Barge
The Port proposes to use a clamshell dredge to remove predominantly sandy, silty sediments using a close-lipped bucket (also referred to as an “environmental” bucket) operated either from shore or from a floating crane. A straight edge close-lipped bucket is specifically designed to reduce sediment resuspension into the overlying water column. Clamshell dredges are equipped with a positioning computer system that helps the operator position the bucket at the correct location to remove sediments.
The sediments would be placed in either a flat-deck barge with watertight side boards or a bin-barge with one or multiple cells that can sufficiently contain all dredged material, including decant water. During dredging, the barge is usually held in position by spud piles to resist the digging-induced forces of the boom and bucket swing.
Clamshell Dredging Using a “Digging” Bucket and Transport Barge
When dredging consolidated material, a clamshell dredge with a digging bucket may be used if sediments cannot be easily removed with an environmental bucket. During dredging, a crane is used to raise and lower the digging bucket; the crane can either be operated from shore or from a barge. The hinged bucket is opened and lowered vertically through the water column. The impact of the bucket hitting the river bottom causes the jaws of the bucket to dig into the substrate.
After the bucket is closed, the crane then hoists the full bucket and deposits the dredged material into a barge for transport to a designated placement site (following the same protocol to that described above for the environmental bucket). When a digging bucket is needed for a project, the Port will require its contractor to install top flaps on the bucket to help reduce releases of sediments and resuspended material into the waterway.
Backhoe Dredging
Backhoe dredges may be used to remove sediments adjacent to wharfs, piers, or fender piles at the Port’s berthing areas. Such dredges either would be temporarily secured to a barge deck or permanently attached to a barge deck. Dredged material would be loaded into a material barge (or railcar) for transport to an approved placement site.
Some dredged sediments and decant water are expected to return to the water column during the raising and lowering of the excavator arm. Turbidity increases are expected to be somewhat higher during backhoe dredging than for conventional dredging operations. However, the duration of any turbidity increases may be shorter due to the relatively high precision and efficiency of backhoe dredging.
Underwater Grading
Underwater grading is conducted with the use of a self-propelled barge that either pushes or pulls an approximately 30 foot-long by 12 inch-high steel I-beam along the river bottom to grade uneven areas of sediment deposition. Underwater grading may be performed if all of the following criteria are met: (1) the amount of sediment presenting navigation concerns does not exceed 5,000 cy; (2) the berth contains high spots that can be graded into adjacent low spots; and (3) the sediment evaluation process determines that sediments within the proposed impact area are suitable for unconfined in-water placement.
To minimize the exposure of sediments within the middle and upper water column, lifting of the drag beam during grading will only be exercised when necessary. An advanced computer positioning system will be used to ensure efficiency of operation and to move the correct amount of sediments to the correct location.
Relative to traditional maintenance dredging, grading minimizes sediment disturbances to the lower portion of the water column. Project-related turbidity has been shown to be low and rarely exceeds water quality standards. Underwater grading does not completely replace maintenance dredging, but can reduce the frequency of dredging and the volume of dredged material removed from the berthing areas.
Removal of Navigation Hazards
Any large debris, including submerged logs, root wads, or other large items that can present hazards to navigation, will be removed during berth maintenance. Non-treated wood material either will be relocated downstream and retained within the river system, or be placed on a shoreline or upland area for habitat enhancement. Any other debris removed from the river would be recycled or transported by truck to an appropriate landfill.
Dredged Material Management and Placement
The Federal and State interagency Portland Sediment Evaluation Team will provide specific dredge site management conditions prior to dredging to ensure contaminant effects are properly addressed. Approved dredged material placement sites may include upland, in-water, or landfill facilities, depending on the characterization and suitability of sediments from each individual project.
If the sediments are found to be suitable for placement by the PSET and DEQ, the Port may transport the dredged material by barge, truck, or rail to a USACE-approved upland or in-water placement site.
Additional approved and permitted placement sites may be identified and selected during the course of the proposed permit duration (i.e., 10 years). Alternatively, the Port may elect to transport, or sell to an external buyer for their transport, dredged material offsite to support another beneficial use (e.g., construction fill, cover, or permitted wetland mitigation projects). Any in-water sites used would support long-term placement by retaining sediments within the river system. The upland sites would be used to dewater and stockpile dredged material, either on a permanent or temporary basis. The Port may choose to perform barge dewatering so that sediments can be efficiently transported.
Any sediments determined by the PSET to be unsuitable for in-water or upland placement under SEF guidelines and DEQ solid waste rules will be transported to an approved Resource Conservation and Recovery Act, Subtitle C (hazardous waste) or Subtitle D (non-hazardous waste) landfill. Barge dewatering also would be subject to SEF guidelines and DEQ water quality criteria. All dredged material (and decant water) would either be transported by barge or carefully pumped off the barge (if applicable criteria are met) and transported by rail or truck to an appropriate landfill facility.
Barge and Sediment Dewatering
If dewatering is performed, barge decant water, that meets Oregon DEQ’s Aquatic Life Water Quality Criteria or other approved criteria, would be filtered through hay bales and geotextile fabric and released directly to the waterway. Any release of decant water to surface waters will comply with state and federal water quality criteria.
Alternatively, decant water from a barge could be pumped to the City of Portland’s municipal sanitary sewer system. Any sanitary sewer releases will receive prior approval from the City and meet all applicable rules and regulations.
After the barge is sufficiently dewatered (if applicable), the dredged sediments could be transferred to one of the approved upland placement sites or could be offloaded directly to a haul truck, rail car, or another transport barge. Sediment offloading may be performed by clamshell bucket or excavator arm to a truck, where it would then be delivered to an upland site. Alternatively, the sediments could be placed into a hopper, and a large conveyor belt used to deliver material directly to a haul truck, rail car, or another transport barge.
Upland Placement
The DEQ regulates upland placement of sediments through their beneficial use regulations and, as necessary, will require engineering or institutional controls to minimize risks to human health and the environment. The SCR will be reviewed to determine if sediments are suitable for upland beneficial reuse, as required per DEQ beneficial use regulations.
Upland placement involves relocating dredged material directly to a bermed upland site where it is stockpiled or utilized for beneficial uses. Dredged material would be pumped to an upland placement site directly from a barge or mechanically offloaded to one of the placement sites. After settling, the water would be held at the bermed site, or passed through an outlet weir(s), where it may be released at a shoreline outfall or discharged through submerged pipe(s) back into the adjacent waterway.
The capacities of the upland Suttle Road Rehandle Facility and West Hayden Island Upland Placement Site total approximately 70,000 cy and 5.7 million cy, respectively. Due to the large size and configuration of the West Hayden Island site and the relatively small amount of dredged material that would be placed there during each maintenance event, it is not likely that residual water would be released to the Columbia River. However, over the proposed ten year permit period, it is possible that some return water may be released if either Suttle Road or West Hayden Island are utilized.
When sediments are hydraulically offloaded from a barge, a submersible pump is used to pump sediments with additional “make-up” water, as necessary, directly into the primary storage cell of the upland site. “Make-up” water may be recycled from an upland settling basin, obtained from residual water on the barge, or obtained from the Columbia River. If water is pumped from the river, intake screens will be installed per NMFS screening criteria. At Suttle Road, the dredged material would be dewatered and transferred to a location approved by DEQ.
Turbidity is generally low during upland placement operations, particularly when submerged pipes are used to discharge return water. To avoid impacts to important salmonid shallow water habitat, the installation of submerged pipes at depths greater than -20 ft. CRD has been adopted as a best management practice by the Port.
In-Water Placement
In-water placement will involve the use of a 20 ft. long tremie chute to discharge dredged material directly into an approved deep water site (i.e., sites deeper than -20 ft. Columbia River Datum). This placement method would only be used if the dredged material meets SEF guidelines (e.g. suitable for unconfined in-water placement) and appropriate regulatory approval is received. During this process, dredged material may be placed in a bottom-dump barge or scow and towed to an in-water placement site. Discharged dredged material disperses through the water column and deposits on the river bottom. Dredged material may be placed at the approximately 75 acre Columbia River In-Water Placement Site, whose depths range between -50 ft. and -80 ft. CRD.
Landfill Disposal
Landfill sites used may include the Wasco County landfill (The Dalles, OR), Finley Buttes landfill (Boardman, OR), or other RCRA Subtitle C or D Landfill.
A more detailed description of the proposed project is available upon request. See “Additional Information” section below.
Mitigation: If a permit is issued, the Corps will determine what is appropriate and practicable, compensatory mitigation. The amount of compensatory mitigation required shall be commensurate with the anticipated impacts of the project.
Purpose: The purpose for the proposed project is to provide maintenance of navigational depth clearances required for cargo vessels docking at Port of Portland facilities.
Drawings: Nine drawings are attached and labeled Corp No. NWP-2007-240 enclosure.
Additional Information: Additional information may be obtained from Tom Taylor, Project Manager, U.S. Army Corps of Engineers at 503-808-4386 or e-mail at thomas.j.taylor@usace.army.mil.
Authority: This permit will be issued or denied under the following:
Section 10, Rivers and Harbors Act 1899 (33 U.S.C. 403), for work in or affecting navigable waters of the United States.
Section 404, Clean Water Act (33 U.S.C. 1344), for discharge of dredged or fill material into waters of the United States.
Water Quality Certification: A permit for the described work will not be issued until certification, as required under Section 401 of the Clean Water Act (P.L. 95‑217), has been received or is waived from the certifying state. Attached is the state's notice advertising the request for certification.
Section 404(b)(1) Evaluation: The impact of the activity on the public interest will be evaluated in accordance with the Environmental Protection Agency guidelines pursuant to Section 404(b)(1) of the Clean Water Act.
Sediment Evaluation Framework for the Pacific Northwest: A Sediment Characterization Report has been submitted to the interagency Portland Sediment Evaluation Team for review to ensure compliance with the SEF and to determine the approved fate of the dredged materials (i.e., upland, in-water, or approved landfill) and appropriate management of the post-dredge or leave surfaces. Dredge prisms and leave surfaces will be managed to ensure that berth maintenance does not result in adverse effects to aquatic organisms and their habitat.
Public Hearing: Any person may request in writing within the comment period specified in this notice that a public hearing be held to consider this application. Requests for public hearings shall state with particularity the reasons for holding a public hearing.
Endangered Species: Preliminary determinations indicate that the described activity may affect an endangered or threatened species or its critical habitat. Consultation under Section 7 of the Endangered Species Act of 1973 (87 Stat. 844) has been initiated. A permit for the proposed activity will not be issued until the consultation process is completed.
Cultural Resources: An initial evaluation of the proposed project area indicates that to the best of our knowledge, the described activity is not located on property registered or eligible for registration in the latest published version of the National Register of Historic Places. At this time the Corps is unaware of any cultural resource surveys of the project area.
This notice has been provided to the State Historic Preservation Office, interested Native American Indian tribes, and other interested parties. If you have information pertaining to cultural resources within the permit area, please provide this information to the Corps project manager (identified on page 1 of this notice) to assist in a complete evaluation of potential effects.
Evaluation: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the described activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the described activity will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people.
The Corps is soliciting comments from the public; Federal, state, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
Additional Requirements: State law requires that leases, easements, or permits be obtained for certain works or activity in the described waters. These State requirements must be met where applicable, and a Department of the Army permit must be obtained before any work within the applicable Statutory Authority previously indicated may be accomplished. Other local governmental agencies may also have ordinances or requirements, which must be satisfied before the work is accomplished.
PUBLIC NOTICE
for Permit Application
30-Day Notice
Issue Date: August 7, 2012
Expiration Date: September 6, 2012
US Army Corps of Engineers No: NWP-2007-240/2
Oregon Department of State Lands No: 50468-RP
Interested parties are hereby notified that an application has been received for a Department of the
Army permit for certain work in waters of the United States, as described below and shown on the
attached plan.
Comments: Comments on the described work should reference the U.S. Army Corps of Engineers
(Corps) number shown above and reach this office no later than the above expiration date of this
Public Notice to become part of the record and be considered in the decision. Comments should be
mailed to the following address:
U.S. Army Corps of Engineers
Tom Taylor (thomas.j.taylor@usace.army.mil)
PO Box 2946
Portland, OR 97208-2946
Applicant: Port of Portland, 7200 NE Airport Way, Portland, Oregon 97218
Location: All of the proposed project sites are located in Portland, Multnomah County, Oregon, as
follows:
Dredge Sites:
* Terminal 2 (berths 203, 204, 205, and 206) is located on the southwest bank of the Willamette River
at River Mile (RM) 10, within Township (T) 1 North (N), Range (R) 1 East (E), Sections (S) 20, 21,
and 28. Terminal 2 is located within the U.S. Environmental Protection Agency (EPA) designated
Portland Harbor Superfund Study Area on the National Priorities List (NPL), pursuant to the
Comprehensive Environmental Response, Compensation, and Liability Act of 1980, as amended (42
U.S.C. § 9601, et seq.) (CERCLA).
* Terminal 4 (berths 401, 410, 411, 414, 415, and 416) is located on the east bank of the Willamette
River between RM 4 and 5, within T2N, R1W, S35; as well as T1N, R1W, S2. Six of the total berths
are included for berth maintenance. Terminal 2 is located within the EPA designated Portland Harbor
Superfund Study Area on the NPL, pursuant to CERCLA.
* Terminal 5 (berths 50, including barge and face sides, 502, and 503) is located on the east bank of
the Willamette River between RM 1 and 2, within T2N, R1W, S23.
Corps No. NWP-2007-240
Page 1 of 10
* Terminal 6 (berths 601, 603, 604, 605, and 607) is located on the south bank of the Columbia River
between RM 102 and 104, within T2N, R1W, S24; and within T2N, R1E, S30.
Dredged Material Placement Site Options:
* West Hayden Island Upland Placement Site is located on the northwest side of Hayden Island (RM
104-105).
* Suttle Road Rehandle Facility is located on the south bank of North Portland Harbor near RM 2
(Columbia RM 104.5).
* In-water placement site is located at RM 102.2 on the Oregon side of the Columbia River between
the western tip of West Hayden Island and Kelley Point Park.
Waterway: See above under "Location" for each terminal.
Project Description: The Port proposes to continue berth maintenance, as-needed, at the terminals
and berths identified above under "Location." The annual maintenance need at any berth is influenced
by flow conditions, sedimentation rates, and economic conditions. The estimated total volume of
dredged material removed from all berthing areas would average between 15,000 to 40,000 cubic yards
(cy) per year (yr.) over the ten-year permit duration. Maintenance depths, overdepth allowances,
maintenance frequencies, etc., for each berth are specified in Table 1.
Advanced maintenance incorporated within the overdepth allowance could reduce the frequency of
future berth maintenance. The Port may utilize a variety of berth dredging methods (mechanical
clamshell, backhoe dredging, and underwater grading) and placement sites (in-water, upland, or
landfill) during the proposed program.
Dredging Methods
Clamshell Dredging Using an "Environmental" Bucket and Transport Barge
The Port proposes to use a clamshell dredge to remove predominantly sandy, silty sediments using a
close-lipped bucket (also referred to as an "environmental" bucket) operated either from shore or from
a floating crane. A straight edge close-lipped bucket is specifically designed to reduce sediment
resuspension into the overlying water column. Clamshell dredges are equipped with a positioning
computer system that helps the operator position the bucket at the correct location to remove
sediments.
The sediments would be placed in either a flat-deck barge with watertight side boards or a bin-barge
with one or multiple cells that can sufficiently contain all dredged material, including decant water.
During dredging, the barge is usually held in position by spud piles to resist the digging-induced forces
of the boom and bucket swing.
Corps No. NWP-2007-240
Page 2 of 10
Corps No. NWP-2007-240
Page 3 of 10
Clamshell Dredging Using a "Digging" Bucket and Transport Barge
When dredging consolidated material, a clamshell dredge with a digging bucket may be used if
sediments cannot be easily removed with an environmental bucket. During dredging, a crane is used to
raise and lower the digging bucket; the crane can either be operated from shore or from a barge. The
hinged bucket is opened and lowered vertically through the water column. The impact of the bucket
hitting the river bottom causes the jaws of the bucket to dig into the substrate.
After the bucket is closed, the crane then hoists the full bucket and deposits the dredged material into a
barge for transport to a designated placement site (following the same protocol to that described above
for the environmental bucket). When a digging bucket is needed for a project, the Port will require its
contractor to install top flaps on the bucket to help reduce releases of sediments and resuspended
material into the waterway.
Backhoe Dredging
Backhoe dredges may be used to remove sediments adjacent to wharfs, piers, or fender piles at the
Port's berthing areas. Such dredges either would be temporarily secured to a barge deck or
permanently attached to a barge deck. Dredged material would be loaded into a material barge (or
railcar) for transport to an approved placement site.
Some dredged sediments and decant water are expected to return to the water column during the
raising and lowering of the excavator arm. Turbidity increases are expected to be somewhat higher
during backhoe dredging than for conventional dredging operations. However, the duration of any
turbidity increases may be shorter due to the relatively high precision and efficiency of backhoe
dredging.
Underwater Grading
Underwater grading is conducted with the use of a self-propelled barge that either pushes or pulls an
approximately 30 foot-long by 12 inch-high steel I-beam along the river bottom to grade uneven areas
of sediment deposition. Underwater grading may be performed if all of the following criteria are met:
(1) the amount of sediment presenting navigation concerns does not exceed 5,000 cy; (2) the berth
contains high spots that can be graded into adjacent low spots; and (3) the sediment evaluation process
determines that sediments within the proposed impact area are suitable for unconfined in-water
placement.
To minimize the exposure of sediments within the middle and upper water column, lifting of the drag
beam during grading will only be exercised when necessary. An advanced computer positioning
system will be used to ensure efficiency of operation and to move the correct amount of sediments to
the correct location.
Relative to traditional maintenance dredging, grading minimizes sediment disturbances to the lower
portion of the water column. Project-related turbidity has been shown to be low and rarely exceeds
water quality standards. Underwater grading does not completely replace maintenance dredging, but
can reduce the frequency of dredging and the volume of dredged material removed from the berthing
areas.
Corps No. NWP-2007-240
Page 4 of 10
Removal of Navigation Hazards
Any large debris, including submerged logs, root wads, or other large items that can present hazards to
navigation, will be removed during berth maintenance. Non-treated wood material either will be
relocated downstream and retained within the river system, or be placed on a shoreline or upland area
for habitat enhancement. Any other debris removed from the river would be recycled or transported by
truck to an appropriate landfill.
Dredged Material Management and Placement
The Federal and State interagency Portland Sediment Evaluation Team (PSET) will provide specific
dredge site management conditions prior to dredging to ensure contaminant effects are properly
addressed. Approved dredged material placement sites may include upland, in-water, or landfill
facilities, depending on the characterization and suitability of sediments from each individual project.
If the sediments are found to be suitable for placement by the PSET and DEQ, the Port may transport
the dredged material by barge, truck, or rail to a USACE-approved upland or in-water placement site.
Additional approved and permitted placement sites may be identified and selected during the course of
the proposed permit duration (i.e., 10 years). Alternatively, the Port may elect to transport, or sell to an
external buyer for their transport, dredged material offsite to support another beneficial use (e.g.,
construction fill, cover, or permitted wetland mitigation projects). Any in-water sites used would
support long-term placement by retaining sediments within the river system. The upland sites would
be used to dewater and stockpile dredged material, either on a permanent or temporary basis. The Port
may choose to perform barge dewatering so that sediments can be efficiently transported.
Any sediments determined by the PSET to be unsuitable for in-water or upland placement under SEF
guidelines and DEQ solid waste rules will be transported to an approved Resource Conservation and
Recovery Act (RCRA) Subtitle C (hazardous waste) or Subtitle D (non-hazardous waste) landfill.
Barge dewatering also would be subject to SEF guidelines and DEQ water quality criteria. All
dredged material (and decant water) would either be transported by barge or carefully pumped off the
barge (if applicable criteria are met) and transported by rail or truck to an appropriate landfill facility.
Barge and Sediment Dewatering
If dewatering is performed, barge decant water, that meets Oregon DEQ's Aquatic Life Water Quality
Criteria or other approved criteria, would be filtered through hay bales and geotextile fabric and
released directly to the waterway. Any release of decant water to surface waters will comply with state
and federal water quality criteria.
Alternatively, decant water from a barge could be pumped to the City of Portland's municipal sanitary
sewer system. Any sanitary sewer releases will receive prior approval from the City and meet all
applicable rules and regulations.
After the barge is sufficiently dewatered (if applicable), the dredged sediments could be transferred to
one of the approved upland placement sites or could be offloaded directly to a haul truck, rail car, or
Corps No. NWP-2007-240
Page 5 of 10
another transport barge. Sediment offloading may be performed by clamshell bucket or excavator arm
to a truck, where it would then be delivered to an upland site. Alternatively, the sediments could be
placed into a hopper, and a large conveyor belt used to deliver material directly to a haul truck, rail car,
or another transport barge.
Upland Placement
The DEQ regulates upland placement of sediments through their beneficial use regulations and, as
necessary, will require engineering or institutional controls to minimize risks to human health and the
environment. The SCR will be reviewed to determine if sediments are suitable for upland beneficial
reuse, as required per DEQ beneficial use regulations.
Upland placement involves relocating dredged material directly to a bermed upland site where it is
stockpiled or utilized for beneficial uses. Dredged material would be pumped to an upland placement
site directly from a barge or mechanically offloaded to one of the placement sites. After settling, the
water would be held at the bermed site, or passed through an outlet weir(s), where it may be released at
a shoreline outfall or discharged through submerged pipe(s) back into the adjacent waterway.
The capacities of the upland Suttle Road Rehandle Facility and West Hayden Island Upland Placement
Site total approximately 70,000 cy and 5.7 million cy, respectively. Due to the large size and
configuration of the West Hayden Island site and the relatively small amount of dredged material that
would be placed there during each maintenance event, it is not likely that residual water would be
released to the Columbia River. However, over the proposed ten year permit period, it is possible that
some return water may be released if either Suttle Road or West Hayden Island are utilized.
When sediments are hydraulically offloaded from a barge, a submersible pump is used to pump
sediments with additional "make-up" water, as necessary, directly into the primary storage cell of the
upland site. "Make-up" water may be recycled from an upland settling basin, obtained from residual
water on the barge, or obtained from the Columbia River. If water is pumped from the river, intake
screens will be installed per NMFS screening criteria. At Suttle Road, the dredged material would be
dewatered and transferred to a location approved by DEQ.
Turbidity is generally low during upland placement operations, particularly when submerged pipes are
used to discharge return water. To avoid impacts to important salmonid shallow water habitat, the
installation of submerged pipes at depths greater than -20 ft. CRD has been adopted as a best
management practice by the Port.
In-Water Placement
In-water placement will involve the use of a 20 ft. long tremie chute to discharge dredged material
directly into an approved deep water site (i.e., sites deeper than -20 ft. Columbia River Datum or
CRD). This placement method would only be used if the dredged material meets SEF guidelines (e.g.
suitable for unconfined in-water placement) and appropriate regulatory approval is received. During
this process, dredged material may be placed in a bottom-dump barge or scow and towed to an inwater placement site. Discharged dredged material disperses through the water column and deposits
on the river bottom. Dredged material may be placed at the approximately 75 acre Columbia River InWater Placement Site, whose depths range between -50 ft. and -80 ft. CRD.
Corps No. NWP-2007-240
Page 6 of 10
Landfill Disposal
Landfill sites used may include the Wasco County landfill (The Dalles, OR), Finley Buttes landfill
(Boardman, OR), or other RCRA Subtitle C or D Landfill.
A more detailed description of the proposed project is available upon request. See "Additional
Information" section below.
Mitigation: If a permit is issued, the Corps will determine what is appropriate and practicable,
compensatory mitigation. The amount of compensatory mitigation required shall be commensurate
with the anticipated impacts of the project.
Purpose: The purpose for the proposed project is to provide maintenance of navigational depth
clearances required for cargo vessels docking at Port of Portland facilities.
Drawing(s): Nine (9) drawings are attached and labeled Corp No. NWP-2007-240.
Additional Information: Additional information may be obtained from Tom Taylor, Project
Manager, U.S. Army Corps of Engineers at (503) 808-4386 or e-mail at
thomas.j.taylor@usace.army.mil.
Authority: This permit will be issued or denied under the following:
Section 10, Rivers and Harbors Act 1899 (33 U.S.C. 403), for work in or affecting navigable
waters of the United States.
Section 404, Clean Water Act (33 U.S.C. 1344), for discharge of dredged or fill material into
waters of the United States.
Water Quality Certification: A permit for the described work will not be issued until certification, as
required under Section 401 of the Clean Water Act (P.L. 95-217), has been received or is waived from
the certifying state. Attached is the state's notice advertising the request for certification.
Section 404(b)(1) Evaluation: The impact of the activity on the public interest will be evaluated in
accordance with the Environmental Protection Agency guidelines pursuant to Section 404(b)(1) of the
Clean Water Act.
Sediment Evaluation Framework (SEF) for the Pacific Northwest: A Sediment Characterization
Report has been submitted to the interagency Portland Sediment Evaluation Team (PSET) for review
to ensure compliance with the SEF and to determine the approved fate of the dredged materials
(i.e., upland, in-water, or approved landfill) and appropriate management of the post-dredge or leave
surfaces. Dredge prisms and leave surfaces will be managed to ensure that berth maintenance does not
result in adverse effects to aquatic organisms and their habitat.
Public Hearing: Any person may request in writing within the comment period specified in this
notice that a public hearing be held to consider this application. Requests for public hearings shall
state with particularity the reasons for holding a public hearing.
Corps No. NWP-2007-240
Page 7 of 10
Endangered Species: Preliminary determinations indicate that the described activity may affect an
endangered or threatened species or its critical habitat. Consultation under Section 7 of the
Endangered Species Act of 1973 (87 Stat. 844) has been initiated. A permit for the proposed activity
will not be issued until the consultation process is completed.
Cultural Resources: An initial evaluation of the proposed project area indicates that to the best of our
knowledge, the described activity is not located on property registered or eligible for registration in the
latest published version of the National Register of Historic Places. At this time the Corps is unaware
of any cultural resource surveys of the project area.
This notice has been provided to the State Historic Preservation Office (SHPO), interested Native
American Indian Tribes, and other interested parties. If you have information pertaining to cultural
resources within the permit area, please provide this information to the Corps project manager
(identified on page 1 of this notice) to assist in a complete evaluation of potential effects.
Evaluation: The decision whether to issue a permit will be based on an evaluation of the probable
impact including cumulative impacts of the described activity on the public interest. That decision will
reflect the national concern for both protection and utilization of important resources. The benefit,
which reasonably may be expected to accrue from the described activity, must be balanced against its
reasonably foreseeable detriments. All factors, which may be relevant to the described activity will be
considered including the cumulative effects thereof; among those are conservation, economics,
aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values,
flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation,
water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral
needs, consideration of property ownership and, in general, the needs and welfare of the people.
The Corps is soliciting comments from the public; Federal, state, and local agencies and officials;
Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this
proposed activity. Any comments received will be considered by the Corps to determine whether to
issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used
to assess impacts on endangered species, historic properties, water quality, general environmental
effects, and the other public interest factors listed above. Comments are used in the preparation of an
Environmental Assessment and/or an Environmental Impact Statement pursuant to the National
Environmental Policy Act. Comments are also used to determine the need for a public hearing and to
determine the overall public interest of the proposed activity.
Additional Requirements: State law requires that leases, easements, or permits be obtained for
certain works or activity in the described waters. These State requirements must be met where
applicable, and a Department of the Army permit must be obtained before any work within the
applicable Statutory Authority previously indicated may be accomplished. Other local governmental
agencies may also have ordinances or requirements, which must be satisfied before the work is
accomplished.
Corps No. NWP-2007-240
Page 8 of 10
PUBLIC NOTICE
Oregon Department of Environmental Quality (DEQ)
Water Quality 401 Certification
Corps of Engineers No: NWP-2007-240
Notice Issued: August 7, 2012
Oregon Department of State Lands No: 50468-RP Written Comments Due: September 6, 2012
WHO IS THE APPLICANT: Port of Portland, 7200 NE Airport Way, Portland, Oregon 97218
LOCATION OF CERTIFICATION ACTIVITY: See attached U.S. Army Corps of Engineers
public notice.
WHAT IS PROPOSED: See attached U.S. Army Corps of Engineers public notice on the proposed
project.
NEED FOR CERTIFICATION: Section 401 of the Federal Clean Water Act requires applicants for
Federal permits or licenses to provide the Federal agency a water quality certification from the State of
Oregon if the proposed activity may result in a discharge to waters of the state.
DESCRIPTION OF DISCHARGES: See attached U.S. Army Corps of Engineers public notice on
the proposed project.
WHERE TO FIND DOCUMENTS: Documents and materials related to water quality issues as a
result of the proposal are available for examination and copying at Oregon Department of
Environmental Quality, 401 Water Quality Certification Coordinator, Northwest Region, 2020 S.W.
4th Avenue, Suite 400, Portland, Oregon 97201-4953. Other project materials are available by
contacting the Corps per the attached public notice.
While not required, scheduling an appointment will ensure that water quality documents are readily
accessible during your visit. To schedule an appointment please call DEQ Water Quality at Northwest
Region at (503) 229-5552.
Any questions on the water quality certification process may be addressed to the 401 Program
Coordinator at (503) 229-6030 or toll free within Oregon at (800) 452-4011. People with hearing
impairments may call the Oregon Telecommunications Relay Service at 1-800-735-2900.
PUBLIC PARTICIPATION:
Public Hearing: Oregon Administrative Rule (OAR) 340-48-0032 (2) states that "The Corps provides
public notice of and opportunity to comment on the applications, including the application for
certification, provided that the department (DEQ), in its discretion, may provide additional opportunity
for public comment, including public hearing."
Corps No. NWP-2007-240
Page 9 of 10
Written comments: Written comments on project elements related to water quality must be received
at the Oregon Department of Environmental Quality by 5 p.m. on the date specified in the upper right
section on page one of this notice. Written comments may be emailed, mailed or faxed as described
below:
E-mail - 401publiccomments@deq.state.or.us
Mail - Oregon Department of Environmental Quality, Northwest Region
2020 S.W. 4th Avenue, Suite 400
Portland, Oregon 97201-4953
Attn: 401 Water Quality Certification Coordinator
Fax - (503) 229-6957
People wishing to send comments via e-mail should send them in Microsoft Word (through version
7.0), WordPerfect (through version 6.x), or plain text format. Otherwise, due to conversion difficulties,
DEQ recommends that comments be mailed in hard copy.
WHAT HAPPENS NEXT: DEQ will review and consider all comments received during the public
comment period. Following this review, certification of the proposal may be issued as proposed,
issued with conditions, or denied. You will be notified of DEQ's final decision if you submit
comments during the comment period. Otherwise, if you wish to receive notification, please call or
write DEQ at the above address.
ACCESSIBILITY INFORMATION: This publication is available in alternate format (e.g. large
print, Braille) upon request. Please contact DEQ Office of Communications and Outreach at
(503) 229-5317 or toll free within Oregon at 1-800-452-4011 to request an alternate format. People
with a hearing impairment can receive help by calling the Oregon Telecommunications Relay Service
at 1-800-735-2900.
Corps No. NWP-2007-240
Page 10 of 10