Dominic Yballe is the Regulatory point-of-contact for this permit application from Nick Testa for work in Yaquina River tributaries in Eddyville, Ore.
PUBLIC NOTICE for Permit Application
Issue Date: October 04, 2012
Expiration Date: November 04, 2012
US Army Corps of Engineers No: NWP-2006-6
30-Day Notice Oregon Department of State Lands No: 35733-RF
Interested parties are hereby notified that an application has been received for a Department of the Army permit for certain work in waters of the United States, as described below and shown on the attached plan.
Comments: Comments on the described work should reference the U.S. Army Corps of Engineers number shown above and reach this office no later than the above expiration date of this Public Notice to become part of the record and be considered in the decision. Comments should be mailed to the following address:
U.S. Army Corps of Engineers
Dominic Yballedominic.p.yballe@usace.army.mil
PO Box 2946
Portland, OR 97208-2946
Applicant: Oregon Department of Transportation – Region 2
Attn: Nick Testa
3700 SW Philomath Blvd.
Corvallis, OR 97330
Location: The project is located on US Hwy. 20, Milepost 14.68 to Milepost 24.67. The site is near the town of Eddyville, Lincoln Co., Ore.
Waterway: The project will impact various tributaries of waters ultimately discharging into the Yaquina River.
Project Description: The US Army Corps of Engineers authorized construction of the 7-mile bypass on US Highway 20 from Pioneer Mountain to Eddyville.Original authorization was issued July 2006 and modified 2008 to address unstable ground movement affecting over-water bridge crossings. Latest analyses of landslide movement indicate the preferred bridge options at four locations involving six drainages, are not feasible and cannot be pursued. Partially constructed bridges will be removed and culvert options will be implemented as initially evaluated in the Federal Highways Administration Final Environmental Impact Statement dated June 2004.
In addition to the aquatic impacts authorized in 2006 and 2008, the following creeks will be placed in culverts and the drainage will be backfilled to highway grade:
Cougar Creek Tributaries 1, 2
Crystal Creek Mainstem and Tributaries 2, 2A, 3, 4, 5, 7, 8
Eddy Creek Tributaries B, C
Unnamed Tributary to Eddy Creek Tributary B
The applicant proposes to use reinforced concrete box culverts measuring approximately six feet wide by eight feet high and installed at the flattest grad practicable to minimize culvert length. Road fill will be placed over the culvert up to highway grade. Total impacts to waters of the U.S. for the newly proposed actions are approximately 0.832 acres below the ordinary high water marks of 3,019 linear feet of tributaries. Past impacts include
Mitigation: The 2008 permit modification required stream restoration over shallow buttressed structures; however, because the bridge options cannot be pursued, these stream restoration areas are no longer capable of being built. Applicable mitigation as required in the 2006 and 2008 permit instruments remain in full force and effect; however, the 2008 Appendix F Stream Re-Creation Plan implementation requirements will be considered for removal in favor of a new Off-site Stream Mitigation Plan (Stream Plan). The goal of the stream plan is to achieve functional uplift through fish passage restoration and riparian enhancement.
If a permit is issued, the Corps will determine what is appropriate and practicable compensatory mitigation. The amount of compensatory mitigation required shall be commensurate with the anticipated impacts of the project.
Purpose: The purpose of the modifications is to complete construction of the highway bypass project.
Drawings: Eighteen drawings are attached and labeled Corp No. NWP-2006-6 enclosure.
Additional Information: Additional information may be obtained fromDominic Yballe, Project Manager, U.S. Army Corps of Engineers at 503-808-4392 or email dominic.p.yballe@usace.army.mil.
Authority: This permit will be issued or denied under the following:
Section 404, Clean Water Act (33 U.S.C. 1344), for discharge of dredged or fill material into waters of the United States.
Water Quality Certification: A permit for the described work will not be issued until certification, as required under Section 401 of the Clean Water Act (P.L. 95‑217), has been received or is waived from the certifying state. Attached is the state's notice advertising the request for certification.
Section 404(b)(1) Evaluation: The impact of the activity on the public interest will be evaluated in accordance with the Environmental Protection Agency guidelines pursuant to Section 404(b)(1) of the Clean Water Act.
Public Hearing: Any person may request in writing within the comment period specified in this notice that a public hearing be held to consider this application. Requests for public hearings shall state with particularity the reasons for holding a public hearing.
Endangered Species: Preliminary determinations indicate that the described activity will not affect endangered species. Consultation under Section 7 of the Endangered Species Act of 1973 (87 Stat. 844) is not required for the described activity; however, the applicant, Federal Highways Administration, and the National Marine Fisheries Service continue to coordinate on this project to ensure the potential for impacts to listed species are minimized to the extent practicable.
Cultural Resources: This notice has been provided to the State Historic Preservation Office, interested Native American Indian tribes, and other interested parties. If you have information pertaining to cultural resources within the permit area, please provide this information to the Corps project manager (identifiedabove inthis notice) to assist in a complete evaluation of potential effects.
Evaluation: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the described activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the described activity will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people.
The Corps is soliciting comments from the public; Federal, state, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
Additional Requirements: State law requires that leases, easements, or permits be obtained for certain works or activity in the described waters. These state requirements must be met where applicable, and a Department of the Army permit must be obtained before any work within the applicable Statutory Authority previously indicated may be accomplished. Other local governmental agencies may also have ordinances or requirements, which must be satisfied before the work is accomplished.
Appendix C
Additional Project Drawings
FFO- US20 PME: UPRR Eddyville Phase II
Corvallis-Newport Highway
Eddyville, Oregon
***( CHANGES FROM APRIL 2008 PERMIT SUBMITTAL)***
Additions
New Table of Contents
Figure 1cc
Riparian Impact Maps Cougar Creek
Figure 2cc
Riparian Impact Maps Crystal Creek
Figure 3cc
Riparian Impact Maps Eddy A &B Creek
Figure 4cc
Riparian Impact Maps Eddy C Creek
Figure 5cc
Project Stream Maps: Cougar Creek
Figure 6cc
Project Stream Maps: Crystal Creek
Figure 7cc
Project Stream Maps: Eddy Creek A &B
Figure 8cc
Project Stream Maps: Eddy Creek C
Figure 9cc
Maps of Impacts To Fish Bearing Creeks (Cougar Creek)
Figure 10cc
Maps of Impacts To Fish Bearing Creeks (Eddy Creek A &B)
Figure 11cc
Maps of Impacts To Fish Bearing Creeks (Eddy Creek C)
Figure 12cc
2012 landslide Stabilization Drawing Cougar Creek
Figure 13cc
2012 landslide Stabilization Drawing Eddy Creek A&B
Figure 14cc
2012 landslide Stabilization Drawing Eddy Creek C
Figure 15cc
2012 landslide Stabilization Drawing Crystal Creek
Omissions
Table of 2008 Contents
Yaquina River Haul Bridge Drawings
Figures: 1, 2p, 3p, 2pc, 3pc, 4p, 4pc, 5p, and 5pc
Oregon Department of Transportation August 2012
NWP-2006-6
Page 1 of 18
Public Notice Enclosure
TABLE OF CONTENTS
2012 Landslide Stabilization Drawings (Cross sections will be prepared as part of the final
design).
Figure 1cc
Figure 2cc
Figure 3cc
Figure 4cc
Figure 5cc
Figure 6cc
Figure 7cc
Figure 8cc
Figure 9cc
Figure 10cc
Figure 11cc
Figure 12cc
Figure 13cc
Figure 14cc
Figure 15cc
NWP-2006-6
Riparian Impact Maps Cougar Creek
Riparian Impact Maps Crystal Creek
Riparian Impact Maps Eddy A &B Creek
Riparian Impact Maps Eddy C Creek
Project Stream Maps: Cougar Creek
Project Stream Maps: Crystal Creek
Project Stream Maps: Eddy Creek A &B
Project Stream Maps: Eddy Creek C
Maps of Impacts To Fish Bearing Creeks (Cougar Creek)
Maps of Impacts To Fish Bearing Creeks (Eddy Creek A &B)
Maps of Impacts To Fish Bearing Creeks (Eddy Creek C)
2012 landslide Stabilization Drawing Cougar Creek
2012 landslide Stabilization Drawing Eddy Creek A&B
2012 landslide Stabilization Drawing Eddy Creek C
2012 landslide Stabilization Drawing Crystal Creek
Page 2 of 18
Public Notice Enclosure
Figure 1cc Riparian Impact Map Cougar Creek (Revised August 2012)
Pioneer Mt. to Eddyville
Riparian Impacts
Cougar Creek
ODOT August 2012
NWP-2006-6
Total Riparian Impacts
Cougar Creek
5.74 acres
Page 3 of 18
Public Notice Enclosure
Figure 2cc Riparian Impact Map Crystal Creek (Revised August 2012)
Pioneer Mt. to Eddyville
Riparian Impacts
Crystal Creek
ODOT August 2012
NWP-2006-6
Total Riparian Impacts
Crystal Creek
20.55 acres
Page 4 of 18
Public Notice Enclosure
Figure 3cc Riparian Impact Map Eddy Creek A & B (Revised August 2012)
Pioneer Mt. to Eddyville
Riparian Impacts
Eddy Creek B
ODOT August 2012
NWP-2006-6
Total Riparian Impacts
Eddy Creek A: 3.12 acres
Eddy Creek B: 5.77 acres
(Total: 8.89 acres)
Page 5 of 18
Public Notice Enclosure
Figure 4cc Riparian Impact Map Eddy Creek C (Revised August 2012)
Pioneer Mt. to Eddyville
Riparian Impacts
Eddy Creek C
ODOT August 2012
NWP-2006-6
Total Riparian Impacts
Eddy Creek C
6.42 acres
Page 6 of 18
Public Notice Enclosure
Figure 5cc Project Stream Map: Cougar Creek Drainage
Pioneer Mt. to Eddyville: Cougar Creek Drainage
ODOT August 2012
NWP-2006-6
Page 7 of 18
Public Notice Enclosure
Figure 6cc Project Stream Map: Crystal Creek Drainage
Pioneer Mt. to Eddyville: Crystal Creek Drainage
ODOT August 2012
NWP-2006-6
Page 8 of 18
Public Notice Enclosure
Figure 7cc Project Stream Map: Eddy Creek A & B Drainages
Pioneer Mt. to Eddyville: Eddy Creek A & B Drainages
ODOT August 2012
NWP-2006-6
Page 9 of 18
Public Notice Enclosure
Figure 8cc Project Stream Map: Eddy Creek C Drainage
Pioneer Mt. to Eddyville: Eddy Creek C Drainage
ODOT August 2012
NWP-2006-6
Page 10 of 18
Public Notice Enclosure
Figure 9cc Maps of Impacts To Fish Bearing Creeks: Cougar Creek (Revised August 2012)
Pioneer Mt. to Eddyville
Impacts to Fish Bearing Creeks
Cougar Creek
ODOT August 2012
NWP-2006-6
Total Fish Bearing Impact
Cougar Creek
309-Feet
Page 11 of 18
Public Notice Enclosure
Figure 10cc Maps of Impacts To Fish Bearing Creeks: Eddy Creek A & B (Revised August 2012)
Fish Bearing
Impacts: 472'
Pioneer Mt. to Eddyville
Impacts to Fish Bearing Creeks
Eddy Creek A & B
ODOT August 2012
NWP-2006-6
Total Fish Bearing Impact
Eddy Creek A: 472 Feet
Eddy Creek B: 1,724-Feet
Page 12 of 18
Public Notice Enclosure
Figure 11cc Maps of Impacts To Fish Bearing Creeks: Eddy Creek C (Revised August 2012)
Pioneer Mt. to Eddyville
Impacts to Fish Bearing Creeks
Eddy Creek C
ODOT August 2012
NWP-2006-6
Total Fish Bearing Impact
Eddy Creek C
1,282-Feet
Page 13 of 18
Public Notice Enclosure
Figure 12cc 2012 landslide Stabilization Drawing Cougar Creek
Pioneer Mt. to Eddyville
2012 Landslide Stabilization Cougar Creek
Impacted Creeks Shown
ODOT August 2012
NWP-2006-6
Page 14 of 18
Public Notice Enclosure
Figure 13cc 2012 landslide Stabilization Drawing Eddy Creek A & B
Pioneer Mt. to Eddyville
2012 Landslide Stabilization Eddy Creek A & B
Impacted Creeks Shown
ODOT August 2012
NWP-2006-6
Page 15 of 18
Public Notice Enclosure
Figure 14cc 2012 landslide Stabilization Drawing Eddy Creek C
Pioneer Mt. to Eddyville
2012 Landslide Stabilization Eddy Creek C
Impacted Creeks Shown
ODOT August 2012
NWP-2006-6
Page 16 of 18
Public Notice Enclosure
404 Joint Removal/Fill Permit Modification August 2012 FFO- US20 PME: UPRR Eddyville Phase II Corvallis Newport Highway Lincoln County, Oregon Key # 18095. Appendix
C
Figure 15cc 2012 landslide Stabilization Drawing Crystal Creek
Pioneer Mt. to Eddyville
2012 Landslide Stabilization Crystal Creek
Impacted Creeks Shown
ODOT August 2012
NWP-2006-6
Page 17 of 18
Public Notice Enclosure
NWP-2006-6
Page 18 of 18
Public Notice Enclosure