Dominic Yballe is the Regulatory point-of-contact for this permit application from Nick Testa for work in Yaquina River tributaries in Eddyville, Ore.

PUBLIC NOTICE for Permit Application

Issue Date: October 04, 2012 Expiration Date: November 04, 2012 US Army Corps of Engineers No: NWP-2006-6 30-Day Notice Oregon Department of State Lands No: 35733-RF

Interested parties are hereby notified that an application has been received for a Department of the Army permit for certain work in waters of the United States, as described below and shown on the attached plan.

Comments: Comments on the described work should reference the U.S. Army Corps of Engineers number shown above and reach this office no later than the above expiration date of this Public Notice to become part of the record and be considered in the decision. Comments should be mailed to the following address:

U.S. Army Corps of Engineers Dominic Yballedominic.p.yballe@usace.army.mil PO Box 2946 Portland, OR 97208-2946

Applicant: Oregon Department of Transportation – Region 2 Attn: Nick Testa 3700 SW Philomath Blvd. Corvallis, OR 97330

Location: The project is located on US Hwy. 20, Milepost 14.68 to Milepost 24.67. The site is near the town of Eddyville, Lincoln Co., Ore.

Waterway: The project will impact various tributaries of waters ultimately discharging into the Yaquina River.

Project Description: The US Army Corps of Engineers authorized construction of the 7-mile bypass on US Highway 20 from Pioneer Mountain to Eddyville.Original authorization was issued July 2006 and modified 2008 to address unstable ground movement affecting over-water bridge crossings. Latest analyses of landslide movement indicate the preferred bridge options at four locations involving six drainages, are not feasible and cannot be pursued. Partially constructed bridges will be removed and culvert options will be implemented as initially evaluated in the Federal Highways Administration Final Environmental Impact Statement dated June 2004.

In addition to the aquatic impacts authorized in 2006 and 2008, the following creeks will be placed in culverts and the drainage will be backfilled to highway grade:

Cougar Creek Tributaries 1, 2 Crystal Creek Mainstem and Tributaries 2, 2A, 3, 4, 5, 7, 8 Eddy Creek Tributaries B, C Unnamed Tributary to Eddy Creek Tributary B

The applicant proposes to use reinforced concrete box culverts measuring approximately six feet wide by eight feet high and installed at the flattest grad practicable to minimize culvert length. Road fill will be placed over the culvert up to highway grade. Total impacts to waters of the U.S. for the newly proposed actions are approximately 0.832 acres below the ordinary high water marks of 3,019 linear feet of tributaries. Past impacts include

Mitigation: The 2008 permit modification required stream restoration over shallow buttressed structures; however, because the bridge options cannot be pursued, these stream restoration areas are no longer capable of being built. Applicable mitigation as required in the 2006 and 2008 permit instruments remain in full force and effect; however, the 2008 Appendix F Stream Re-Creation Plan implementation requirements will be considered for removal in favor of a new Off-site Stream Mitigation Plan (Stream Plan). The goal of the stream plan is to achieve functional uplift through fish passage restoration and riparian enhancement.

If a permit is issued, the Corps will determine what is appropriate and practicable compensatory mitigation. The amount of compensatory mitigation required shall be commensurate with the anticipated impacts of the project.

Purpose: The purpose of the modifications is to complete construction of the highway bypass project.

Drawings: Eighteen drawings are attached and labeled Corp No. NWP-2006-6 enclosure.

Additional Information: Additional information may be obtained fromDominic Yballe, Project Manager, U.S. Army Corps of Engineers at 503-808-4392 or email dominic.p.yballe@usace.army.mil.

Authority: This permit will be issued or denied under the following:

Section 404, Clean Water Act (33 U.S.C. 1344), for discharge of dredged or fill material into waters of the United States.

Water Quality Certification: A permit for the described work will not be issued until certification, as required under Section 401 of the Clean Water Act (P.L. 95‑217), has been received or is waived from the certifying state. Attached is the state's notice advertising the request for certification.

Section 404(b)(1) Evaluation: The impact of the activity on the public interest will be evaluated in accordance with the Environmental Protection Agency guidelines pursuant to Section 404(b)(1) of the Clean Water Act.

Public Hearing: Any person may request in writing within the comment period specified in this notice that a public hearing be held to consider this application. Requests for public hearings shall state with particularity the reasons for holding a public hearing.

Endangered Species: Preliminary determinations indicate that the described activity will not affect endangered species. Consultation under Section 7 of the Endangered Species Act of 1973 (87 Stat. 844) is not required for the described activity; however, the applicant, Federal Highways Administration, and the National Marine Fisheries Service continue to coordinate on this project to ensure the potential for impacts to listed species are minimized to the extent practicable.

Cultural Resources: This notice has been provided to the State Historic Preservation Office, interested Native American Indian tribes, and other interested parties. If you have information pertaining to cultural resources within the permit area, please provide this information to the Corps project manager (identifiedabove inthis notice) to assist in a complete evaluation of potential effects.

Evaluation: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the described activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the described activity will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people.

The Corps is soliciting comments from the public; Federal, state, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

Additional Requirements: State law requires that leases, easements, or permits be obtained for certain works or activity in the described waters. These state requirements must be met where applicable, and a Department of the Army permit must be obtained before any work within the applicable Statutory Authority previously indicated may be accomplished. Other local governmental agencies may also have ordinances or requirements, which must be satisfied before the work is accomplished.

Appendix C Additional Project Drawings FFO- US20 PME: UPRR ­ Eddyville Phase II Corvallis-Newport Highway Eddyville, Oregon

***( CHANGES FROM APRIL 2008 PERMIT SUBMITTAL)*** Additions New Table of Contents Figure 1cc Riparian Impact Maps Cougar Creek Figure 2cc Riparian Impact Maps Crystal Creek Figure 3cc Riparian Impact Maps Eddy A &B Creek Figure 4cc Riparian Impact Maps Eddy C Creek Figure 5cc Project Stream Maps: Cougar Creek Figure 6cc Project Stream Maps: Crystal Creek Figure 7cc Project Stream Maps: Eddy Creek A &B Figure 8cc Project Stream Maps: Eddy Creek C Figure 9cc Maps of Impacts To Fish Bearing Creeks (Cougar Creek) Figure 10cc Maps of Impacts To Fish Bearing Creeks (Eddy Creek A &B) Figure 11cc Maps of Impacts To Fish Bearing Creeks (Eddy Creek C) Figure 12cc 2012 landslide Stabilization Drawing Cougar Creek Figure 13cc 2012 landslide Stabilization Drawing Eddy Creek A&B Figure 14cc 2012 landslide Stabilization Drawing Eddy Creek C Figure 15cc 2012 landslide Stabilization Drawing Crystal Creek Omissions

Table of 2008 Contents Yaquina River Haul Bridge Drawings Figures: 1, 2p, 3p, 2pc, 3pc, 4p, 4pc, 5p, and 5pc Oregon Department of Transportation August 2012

NWP-2006-6

Page 1 of 18

Public Notice Enclosure

TABLE OF CONTENTS 2012 Landslide Stabilization Drawings (Cross sections will be prepared as part of the final design). Figure 1cc Figure 2cc Figure 3cc Figure 4cc Figure 5cc Figure 6cc Figure 7cc Figure 8cc Figure 9cc Figure 10cc Figure 11cc Figure 12cc Figure 13cc Figure 14cc Figure 15cc

NWP-2006-6

Riparian Impact Maps Cougar Creek Riparian Impact Maps Crystal Creek Riparian Impact Maps Eddy A &B Creek Riparian Impact Maps Eddy C Creek Project Stream Maps: Cougar Creek Project Stream Maps: Crystal Creek Project Stream Maps: Eddy Creek A &B Project Stream Maps: Eddy Creek C Maps of Impacts To Fish Bearing Creeks (Cougar Creek) Maps of Impacts To Fish Bearing Creeks (Eddy Creek A &B) Maps of Impacts To Fish Bearing Creeks (Eddy Creek C) 2012 landslide Stabilization Drawing Cougar Creek 2012 landslide Stabilization Drawing Eddy Creek A&B 2012 landslide Stabilization Drawing Eddy Creek C 2012 landslide Stabilization Drawing Crystal Creek

Page 2 of 18

Public Notice Enclosure

Figure 1cc Riparian Impact Map Cougar Creek (Revised August 2012)

Pioneer Mt. to Eddyville Riparian Impacts Cougar Creek ODOT August 2012

NWP-2006-6

Total Riparian Impacts Cougar Creek 5.74 acres

Page 3 of 18

Public Notice Enclosure

Figure 2cc Riparian Impact Map Crystal Creek (Revised August 2012)

Pioneer Mt. to Eddyville Riparian Impacts Crystal Creek ODOT August 2012

NWP-2006-6

Total Riparian Impacts Crystal Creek 20.55 acres

Page 4 of 18

Public Notice Enclosure

Figure 3cc Riparian Impact Map Eddy Creek A & B (Revised August 2012)

Pioneer Mt. to Eddyville Riparian Impacts Eddy Creek B ODOT August 2012

NWP-2006-6

Total Riparian Impacts Eddy Creek A: 3.12 acres Eddy Creek B: 5.77 acres (Total: 8.89 acres)

Page 5 of 18

Public Notice Enclosure

Figure 4cc Riparian Impact Map Eddy Creek C (Revised August 2012)

Pioneer Mt. to Eddyville Riparian Impacts Eddy Creek C ODOT August 2012

NWP-2006-6

Total Riparian Impacts Eddy Creek C 6.42 acres

Page 6 of 18

Public Notice Enclosure

Figure 5cc Project Stream Map: Cougar Creek Drainage

Pioneer Mt. to Eddyville: Cougar Creek Drainage ODOT August 2012

NWP-2006-6

Page 7 of 18

Public Notice Enclosure

Figure 6cc Project Stream Map: Crystal Creek Drainage

Pioneer Mt. to Eddyville: Crystal Creek Drainage ODOT August 2012

NWP-2006-6

Page 8 of 18

Public Notice Enclosure

Figure 7cc Project Stream Map: Eddy Creek A & B Drainages

Pioneer Mt. to Eddyville: Eddy Creek A & B Drainages ODOT August 2012

NWP-2006-6

Page 9 of 18

Public Notice Enclosure

Figure 8cc Project Stream Map: Eddy Creek C Drainage

Pioneer Mt. to Eddyville: Eddy Creek C Drainage ODOT August 2012

NWP-2006-6

Page 10 of 18

Public Notice Enclosure

Figure 9cc Maps of Impacts To Fish Bearing Creeks: Cougar Creek (Revised August 2012)

Pioneer Mt. to Eddyville Impacts to Fish Bearing Creeks Cougar Creek ODOT August 2012

NWP-2006-6

Total Fish Bearing Impact Cougar Creek 309-Feet

Page 11 of 18

Public Notice Enclosure

Figure 10cc Maps of Impacts To Fish Bearing Creeks: Eddy Creek A & B (Revised August 2012) Fish Bearing Impacts: 472'

Pioneer Mt. to Eddyville Impacts to Fish Bearing Creeks Eddy Creek A & B ODOT August 2012

NWP-2006-6

Total Fish Bearing Impact Eddy Creek A: 472 Feet Eddy Creek B: 1,724-Feet

Page 12 of 18

Public Notice Enclosure

Figure 11cc Maps of Impacts To Fish Bearing Creeks: Eddy Creek C (Revised August 2012)

Pioneer Mt. to Eddyville Impacts to Fish Bearing Creeks Eddy Creek C ODOT August 2012

NWP-2006-6

Total Fish Bearing Impact Eddy Creek C 1,282-Feet

Page 13 of 18

Public Notice Enclosure

Figure 12cc 2012 landslide Stabilization Drawing Cougar Creek

Pioneer Mt. to Eddyville 2012 Landslide Stabilization Cougar Creek Impacted Creeks Shown ODOT August 2012

NWP-2006-6

Page 14 of 18

Public Notice Enclosure

Figure 13cc 2012 landslide Stabilization Drawing Eddy Creek A & B

Pioneer Mt. to Eddyville 2012 Landslide Stabilization Eddy Creek A & B Impacted Creeks Shown ODOT August 2012

NWP-2006-6

Page 15 of 18

Public Notice Enclosure

Figure 14cc 2012 landslide Stabilization Drawing Eddy Creek C

Pioneer Mt. to Eddyville 2012 Landslide Stabilization Eddy Creek C Impacted Creeks Shown ODOT August 2012

NWP-2006-6

Page 16 of 18

Public Notice Enclosure

404 Joint Removal/Fill Permit Modification August 2012 FFO- US20 PME: UPRR ­ Eddyville Phase II Corvallis ­ Newport Highway Lincoln County, Oregon Key # 18095. Appendix C

Figure 15cc 2012 landslide Stabilization Drawing Crystal Creek

Pioneer Mt. to Eddyville 2012 Landslide Stabilization Crystal Creek Impacted Creeks Shown ODOT August 2012

NWP-2006-6

Page 17 of 18

Public Notice Enclosure

NWP-2006-6

Page 18 of 18

Public Notice Enclosure

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas