Benny Dean Jr. is the Regulatory point-of-contact for this permit application from the City of Eugene for work in Amazon Creek, between Bertelsen Rd. and Royal Ave. in Eugene, Ore.

PUBLIC NOTICE for Permit Application Issue Date: April 23, 2013 Expiration Date: May 22, 2013 US Army Corps of Engineers No: NWP-2013-139 30-Day Notice Oregon Department of State Lands No: APP0053544

Interested parties are hereby notified that an application has been received for a Department of the Army permit for certain work in waters of the United States, as described below and shown on the attached plan.

Comments: Comments on the described work should reference the U.S. Army Corps of Engineers number shown above and reach this office no later than the above expiration date of this Public Notice to become part of the record and be considered in the decision. Comments should be mailed to the following address:

U.S. Army Corps of Engineers Benny A. Dean Jr. <Benny.A.Dean@usace.army.mil> Eugene Field Office 1600 Executive Pkwy., Suite 210 Eugene, OR 97401-2156

Applicant: City of Eugene Public Works and Engineering 99 E. Broadway, Suite 400 Eugene, OR 97401

Location: The project is located along an approximate 3 mile section of Amazon Creek between Bertelsen Rd. and Royal Ave. in Eugene, Lane Co.The site is in Section 33 of Township 17 South, Range 4 West.

Waterway: Amazon Creek

Project Description: Up to 2,595 cubic yards of rip-rap will be discharged in multiple locations along 5,000 linear feet of Amazon Creek in an approximate 3 mile length of project area.The stabilization along the streambank involves placement of geotextile fabric, rock, and installation of vegetation at the toe of the slope and up the bank for slope stabilization. Vegetation plantings along the bank will consist of native willow and/or red-osier dogwood stakes from a local source.Additional plantings may include willow wattles.The vegetation plantings will provide additional bank protection and habitat.

Mitigation: The applicant has proposed to provide plantings of willows and dogwood species above the rocks and in between some rocks to help provide improved slope stabilization and reduce the impacts of the rock to the waterway by providing shade, improved riparian habitat, and sediment stabilization for the waterway. If a permit is issued, the Corps will determine what is appropriate and practicable compensatory mitigation.The amount of compensatory mitigation required shall be commensurate with the anticipated impacts of the project.

Purpose: The project purpose is to stabilize the streambank.

Drawings: Twelve drawings are attached and labeled Corps No. NWP-2013-139 enclosure.

Additional Information: Additional information may be obtained from Benny A. Dean Jr., Project Manager, U.S. Army Corps of Engineers at 541-465-6769 or email Benny.A.Dean@usace.army.mil

Authority: This permit will be issued or denied under the following:

Section 404, Clean Water Act (33 U.S.C. 1344), for discharge of dredged or fill material into waters of the United States.

Water Quality Certification: A permit for the described work will not be issued until certification, as required under Section 401 of the Clean Water Act (P.L. 95‑217), has been received or is waived from the certifying state. Attached is the state's notice advertising the request for certification.

Section 404(b)(1) Evaluation: The impact of the activity on the public interest will be evaluated in accordance with the Environmental Protection Agency guidelines pursuant to Section 404(b)(1) of the Clean Water Act.

Public Hearing: Any person may request in writing within the comment period specified in this notice that a public hearing be held to consider this application.Requests for public hearings shall state with particularity the reasons for holding a public hearing.

Endangered Species: Preliminary determinations indicate that the described activity may affect an endangered or threatened species or its critical habitat.Consultation under Section 7 of the Endangered Species Act of 1973 (87 Stat. 844) will be initiated.A permit for the proposed activity will not be issued until the consultation process is completed.

Cultural Resources: An initial evaluation of the proposed project area indicates the described activity is not located on property registered or eligible for registration in the latest published version of the National Register of Historic Places.The permit area has been extensively modified by modern development that little likelihood exists for the proposed project to affect an undisturbed historic property or any other type of cultural resource.

This notice has been provided to the State Historic Preservation Office, interested Native American Indian tribes, and other interested parties.If you have information pertaining to cultural resources within the permit area, please provide this information to the Corps’ project manager (identifiedabove inthis notice) to assist in a complete evaluation of potential effects.

Evaluation: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the described activity on the public interest.That decision will reflect the national concern for both protection and utilization of important resources.The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments.All factors, which may be relevant to the described activity will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people.

The Corps is soliciting comments from the public; Federal, state, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity.Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal.To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act.Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

Additional Requirements: State law requires that leases, easements, or permits be obtained for certain works or activity in the described waters.These state requirements must be met where applicable, and a Department of the Army permit must be obtained before any work within the applicable Statutory Authority previously indicated may be accomplished. Other local governmental agencies may also have ordinances or requirements, which must be satisfied before the work is accomplished.

Joint Removal-Fill Permit Application for Ciry of Eugene's Amazon Channel Bank Stabilization Project: Royal to Bertelson, Eugene, Lane County, Oregon __ , ·'·t

March 2013

'· !~ ·:; I '

i

·-- --·--.·--·

379

Jl· .

\

.,. '.

-

~--_

___

..

.391

'

,-?

1~17

j _,;

:... .

34

.'

-~I

____ .,.,. J ·:·

Randy Pap<> Bekline

FIGURE 1: Site Location Map Royal Av&

Source: Eugene East USGS Quad Scale: 2.6" = I mile

W l ith Ave

--

~-;;;;"

f'~~·:;

II

' '

1~..

,·

,,

"

,.'·

Joint Removal-Fill Permit Application for Ciry of Eugene's Ama;:;on Channel Bank Stabilization Projecr: Royal co Bertelson, Eugene, Lnne County, Oregon

,· .......... ~----------------------------~~--~~~~;~~w '(" ~·-"::"\

\

ROYAL AVE

\

<. ·... .\. :

,\.. (\,... ~ ~·-\ ~

~

~

p,

\ 1 \\

:'~'

.

I

PROJECT

i I i '

I

h

h ~I

!I]I

'

BOUNDARY~

f~

i· l

(

fJ fI ~I ~I ~I ~I iI !I

i

~I

i

t

I

i i i

A N

100

0 50 100

ry..

SCALE: 1" = 225'

225

r;tJ lI

i

-

-

Project B oundary

........... OHWE Ta' Lot Boundarie,

FIGURE 2A: Project Site Pla n No treatment

PROJECT BOUNDARY

~J

i

i'

LEGEND

March 2013

i

~.,

n

~; f.. ;: : ~:. I i !I w

1..1:

{ 1\ I o ~ I \ ~ h ~· \t!

w

~

I

MATCH LINE

--------------------------------------~---~,----------------------------------· \ See Figure 2B

Joint Removal-Fill Permit Application for City of Eugene's Amazon Channel Bank Stabilization Project: Royal ro Bertelson, Eugene, Lane Counry, Oregon \

See Figure 2A

-

~I

-

-

~

·

March 20 13

·- -- - -

1

-MATcHTINr------------\----~------------------------------------·

\ I

I

('~\

' . ) ....' ,I

\.

Q \,\

~-~ ''·.,

\

··...

\.

X.

'

'

.

' ""a .

'·,,,..

··... '

.

J)j · ·· '

..._...

""-

~.,

'

I,~~

'

·······' .... '

'· , , , '

' '-.376

~

' · , r

...._.., ...

.,. .-

..........

I

._

······' ···.......... -..

.

-

PROJECT BOUNDARY

/.

I

·······~ ····~.,

.~...... ........_

·····' ...'· ······~ "

~.

' I I

---

"

····" ······.... , .... '

.,.,

-

PROJECT BOUNDARY

'I

.,

·······~

., ......

.... ' ·········' .. '

·· · · ' 37·

·····~

--.,.,.,

...._.

······~

I··~

.,,

' . ,, 11 ,

1··

1

· · ·· ··· '

·---..

'

···1

1

,~·.i~ .......

'i~.

.,,

""~

.........

1

l

372

...._.. ·

~ I · ·

'·~.

A N

--- - -

100

0

50 100

,. ·

SCALE: 1" == 225'

w iV

LEGEND 225 1

Project Bo undary ........... OHWE Tax Lot Boundaries

z ·N

::JI ~

:c · ::l

FIGURE 28: Project Site Plan No rrearm en t

v i.Ql ~ · u..

~ lVI · ·I

<:: . cv cv

Joint Removal-Fill Permit Application f or City of Eugene :~ Amazon Channel Bank Stabilization Project: Royal to Bertelson , Eugene , Lane County, Oregon

March 2013

A N

100 ~

0

.,.

··

so

SCA LE: 1"

FIGURE 2C: Project Site Plan

100

225

Ill!

LEGEND

= 225'

- - Project Boundary ........... OHWE Tax Lot Boundmies 0----@ Cross Section \ See Figure 13)

·~ I ......... __

I

., I

~."-.

t·....._'·....... ~...... o~~~·-....... ·....._~....._

1 '"-·-._

I

'

I

i'

~........-.....

J?e

'""''·, "· ·-....,

''·-·~

·-.......

"'·-.....,....

~,. ·'~~-~ ! ~-~~~

;:,..

··

~···'-!·, ..

~·

PROJECTY BOUNDAR

~,_·+·;,

··· . ...''' ,.,./ .h ~-~ ~~

········

."

··... ... ' ...

~

·,

<.._

··

··...··-,. ······

. , .,

~·...

CD·w

N lz CIJ I '-I_J

~.:r:

u: lg C1J 1<(

CIJ I~

V)l

II I

~

····· ,

O..y~

~,

~

···· ··

··... ~ '"··... ' ··. ,.._,, ··...·.. '"~' -".;:'" o' ·.···· \ ~ .....·. ·. ..·.. ··.·.. ·..·. ·.··.. ·.·.

'

I

PROJECT BOUNDARY

q,

...._,,

''

'

'

···..·

. \

\

\\

I -. 'I '· J

\ \ ; ·r1 I ~~\

...

STONE & VEGETATION TREATMENT

\1

t( ~ \\

-----~~If.!:il-LI'!§ ___,_________________________ _____~~ -~ __ J..\--------------------------see Figure 20 :: \ . .

Joint Removal-Fill PermiT Application for Ciry of Eugene's Amazon Channel Bank StabilizaTion ProjecT: Royal ro Bertelson, Eugene, Lane Counry, Oregon

March 2013

A N

100

0

so

100

··SCALE: 1"= 225' ~--

225

LEGEND

-

-

Project Boundary

··········· OHWE Tax Lot Boundaries ®----® Cross Section

~PROJECT

J

BOUNDARY

j J

\ \.

J

i I

\ \

z 0..

0 0 _J

~,

...

~\W.

z 3: w

~ ~~

(\,

\~

0

\ \ i \\

FIGURE 20: Project Site Plan Entire reach: Slone & vegelation treatment

I----------------~AI£.~~L- d.--~--------------

t!:::::==== = == == == ======:!J

\

See Fig ure 2E

\

\

rn

~

~

\\

:

!\

Joinr Removal-Fill Perm it Application for City of Eugene's Amazon Channel Bank Stabilization Project: Royal to Berre!son , Eugene , Lane County , Oregon

See Fig u~_2.Q.

~ --------tt\··--r \ l:\ _______M-ATCH LINE ·

:

,'

\

\

March 2013

FIGURE 2E: Project Site Plan Entire reach: Stone & vegetation treatment

\~

\. \,'··... ··.

'·..·..·. ~--··....·. ' ·....) .··..·. "'

LEGEND

~

··

0

-...;,:·.. .

.

~

~-",,

··

··· 'I!

',

Project Boundary ........... OHWE Tax Lot Boundaries 0-----Q Cross Section (s,.· Figutel 3> ~ P1 Photo Point

~ ~

~- "-t o>·..... ~

,...

,..... ··....·.. ~.s>,·.. '.~-.. .··.... '·..··.. ··.. ..... .·.·:..-·,..... ·············· ......__ ········· .............

, '

.........._.

........_

._.....

A

...

, ...........:··...

100

/

IV)

PROJECT BOUNDARY

I

f-

~

?; 0 0:: cr:

~

'··,·..... .. ',··.....··..... ' '"' ··...··..

L.Uiu..

,('~~

zi N ::i· ~ :d:::l

IV-9;, OG'~

.:...··

u ·.Ql

l'-9-

1-JU..

2t~

~

'- ······ '- ······

'

'-..

·

~~·

I'I·

·

.·.·

' ' ..···....

<(

I

SCALE: 1"= 225'

·...

225

50 100

I..

··.. "' ··..

......

0

N

I I

........"t··............ OHw~; } ··.

39ll'4

I

.

~

!!'!!!&._--;, I

_______ _

·... ················ .....,!!········ ..... '' ........ ....... ....... ·................ ....... 390J~ .. ~ ···· '·· ·· ,

@ W 11th AVE

March 20 13

Joinr Remoml-Fi/1 Permir Applicario11for City ofEugene:\ Ama:on Channei/Ja11k Stabilization Project: Royal to Bertelson, Eugene, Lane Counry, Oregon

LEGEN D Project Boundary ........... OHWE Tax Lot Boundaries @)------@ Cross Sectton (S«Figurc 131

w

z

-1

tJ w

w

co w

~

c..

0

<(

co

LU

z

<(

0

z

STONE & VEGETATION

-- n -

o.. >z0

+

- 388 lr.;;;;, ~ ············'Itt''''··· ..... ·····"(··I

., . " "' . · . . . . . . ... . ~

<(

oc

' ·

.-

----- -

-

...................

-~ ······\

----

,..~

:4 ···/

.······· """"".,.,... .,... --- ············· ...~

··

........·;:.:.:".::.. -

.······..·· ..· ····;;... .,..,.. ...::;;. (ci)

1

_!!2 -

~.········ ········

/

~-··

-;;··· ····· ····························· ........ ·······/ / ~~

- -

~ OHio'.

··

I

~~'. ~ - -J- I

VEGETATIONTREATMENT~ / ~ .. ······.......··········::....--

TREATMENT

FERN RIDGE TRAIL

, ·· ··''

/

...·· -.,..,.. .,..,..\ fll"

/

PROJECT BOUNDARY I

... NO TREATMENT

""'--@ W 11th AVE

A

w (w

~ l:::i ::I I I

.~lu u..,~ Q) , , Q) ' """' Vll

w l l.? z , r-~

N

r-~ ,z

100

0

50 100

~--··SCALE: 1'' = 225'

=:il ~

::z:: t ::l

225

~

u l .~

F JGURE 2F: Project Site Plan

!:(·u.. -<:::1 Q)

IV)

""" · Q)

Joint Removal-Fill Permit Application for City of Eugene's Amazon Channel Bank Stabilization ProJect: Royal to Berrelson, Eugene . Lane Counry, Oregon

LEGEND

W7th AVE

I-

I-

V)

z

-

V)

....J

:5

0

z

IV)

~

PROJECT

LU

s 0

0

u

Proj ect B oundary

Tax Lot Boundaries

a::

~

-

........... OHWE

V)

LU

BOUNDARY

March 20}]

Cl..

------=---- - .- _j 390

·····r·····~l!1··········'t································· LoHWE

1

I

J

·········..~....

NO TREATMENT ._

~

. . ............. .... ~~l·······. .············ ········· ·········

- + ----------390

······

...........

·····

....··.

........

· · ·-··

··.....

......._

"'

......._

..·.. ···...

··....··.. .····...... ' ' ···.··... ········... ' '····..··.. ···....... ..........- ·····....,-·· / ········· ······· /

~

C'o4?.

c,

I

't11£;ro,

,-sr

!

:]-

. _ ... . . . . .-. ,

STONE &VEGETATION --I~ TREATMENT ~Z

...__-

LU

V)

....J LU

PROJECT

1--

a:::

BOUNDARY

LU

co

&

eI

V)

$

@ W 11th AVE LL 1

A

w

r-~ lz <1.1-

N

' - I_J

&,II

·-IU

~·!;;: <1.1 12 l/)1 I

I

100

0

50 100

~-SCALE: 1" = 225'

2 25

~

F IGURE 2G : Project Site Plan

March2013

Joinr Remo11ai- Fi/L Permit Application for City of Eugene's Amazon Channel Bank Stabili:;:ation Project: Royal to Bertelson, Eugene , Lane County, Oregon

I~

...

WATTLE TREATfv'ENT (TYP )

~;;: ~

WATTLE TREATMEN T - - - - - 5' ·9' TYPICAL

2

- - - --1 ~

18' MAX

~

I

>.

a:"'

;.::

~I

~I

EXISTI NG 2:1

~I 21

S~ OPE

C>

(TYP.)

~-y

lL

0

1-

~ _J

~~

w

0

0

0:::

w

· ·j

~·I

lL

0

w

U> _J

z z <( I

~0a:: o~~~ . · · UJ

0

I· .

z

0

oc

I

w EXISTING 2·1

~TYP)

~ ~

<(

UJ

TYPICAL · DR IVE OR PLANT WILLOW STAKES THROlJGH OPENINGS IN RIPRAP. ALONG EDGES AND ABOVE

I~

ROCK.

I~ 12

~O" OC

2' · 4' TYPICAL

NO"a e";

n:

"' ~

;:..:

iil cr .Q a:

CD

1-

i'"AVOID DISTURBANCE OF SLOPE 2. ONLY INST All Wil LOW STAKES AND WATTLES IN AREAS DIRECTED BYTHE ENGINEER 3 VEGETATION. STAKES AND WATTLES MAY BE INSTAllED AT ALL LOCATIONS O F PROJECT SITE. AND IN ANY COMBINATIONS OF STABILIZATION TECHNIQUES AT THE DIRECTION OF THE ENGINEER

a:

0

INSTALL GEOTEXTILE FABRIC PLACE AND COMPACT CLASS 50· 100RIP/RAPAT TOEOF SANKAS DIRE CTED

a

cr:w

(j)

0

0

!::

w w

<

'QOO

f?~

/ 7

) 7

N.T.S.

Q

w

z z z w 0 Cl z a= w :::> w 0. w en lL ~ 0 ;:..: 0 rx CD >- 0 0

t:: ~ w 1-

Oo

STONE TREAT MENT DETAIL N.T.S.

~

w Cl z

z

I ~ BANK STABILIZATION PLAN VIEW

>< 0

0

0

::; ::; w

lL

co C? 0

-'

:::>

0.. ui

r.:

:i II

w

...J

<(

0

(j)

~

~C> c

e~

0

.,~ a.

cg

.. N

..

:5 (ij

"' "' .,"'0

c .c

(,) N

~

"'r.:: ~

"'is Q;

~

l ,:,;

-- ~ · ·- . z:::_

-

/ ·.[.

.

WATTLE TREATMeNT -;==r

·~

OHW

:::z--

-=z.·· STON E TREATMEN T

BANK STAB ILIZATION ELEVATION VIEW

FIGURE 4: Stabil ization. Proj ect Detail Source: City or Eugene

Joim Removal-Fill Permit Application for City of Eugene's Amaz.on Channel Bank Stabilization Project: Royal to Bertelson, Eugene, Lane County, Oregon

March 2013 ~

~-

~

r

<>

Q

':: U r OP o:: STt\KE SQU;l.RE

~

~

"-

~

!;.

"

cr: ·J }

1...

_I S: WlllO\'\' S ....A.KE'S

INSTALL vVA Tf .. f. ::'t GuF.E WI] H 1".4" DIA WIU 0 W -

SfAKt S 3'·6 LC'N::; ~r ::,>REC·

'--...-.

(l: Ul

::!!

J.I~MO

T RI ~ I

0

0

z

\lAKE AN:3LED CUl AT BUTT·END " LANT B'J I f.END DOWN NOTES

3 MAKE (: LEII N CUTS AN D 0 0 lj Q 'f DAMAGe STAKES OR SPLIT ENOS DURING INSTALL!o TION USE A PILOT SARIN ciRMSOilS 4 SOAK CUTTINGS FOR 24 HOUR S ~~~ I N ) P RIOR TO IN$ 11\cLAriON. TAMP TrtE SOil AROUND THe STAKE.

NT S

!'I T S

z

Q cJ>

(f) <.> :'£ )..

cr

CD

>- 0

Q

Ou =:;

((

~ ~ w 1CD

LIVE STAKE TREATMENT

w

w w w w 0 z z w 0 ((z 0 z w ::> w 0. w u.. 0

1 HARVEST AND PLAN I STAKES DURING l'HE OORMA"' l SEASON 2 tJSE HEALfHY ST R,\IGHT ANO LIVE WOOD AT LEAST ' YE.t.R OLO

WATTLE TREATMENT

0'

>= CD

URANC ..:E CLOSE

((

/

()

0.

Wll H CO·R Fl\ERI·: :

,-/

::!! .,.

0

PLANT ao·. OF STAKE LENGTH JN f O T'-lE G HOUND

~~

X

::>

0...

LL. <{

0

!,1,}

?.

'?

%\'

>

~

0

;;; ~

~)

"'' t

.:.<" (

~ 0

~

n.

c 9

~

i5

"' ,;;

~

i'l

)

i\

cJ>

g

r:

.'(

II

..

z

w ;J

u

cJ>

~ ~

f ~ (:)

.,

o~

~ h

r. ::w 1 ··ABR·C J ' . 12 LENGTH

r"IC,. ·'\= CC f\

~

1c 5 'NtLLC'N

I= AA~ ·~

s~·rv< ~S J

r.:: '.'\'IT "1

1

· 1'0 IN

LENGT~·

\'\'i-H

: 0 1R i 'NINE AND INSTA ...l WITH liVES< AKES liS Y.OVJN OR :J,RECTED

WATTLE DETAIL N· s

FIGURE 5: Vegetation Detail Source : City of Eugene

Joint Removal-Fill Permit Application for City of Eugene :S Amazon Channel Bank Stabilization Project: Royal ro Berrelson , Eugene, Lane County. Oregon

March 2013

VARYING t ENGTiiS

,

VARYING WIDTHS LOCATED IN FIELD

TURN AROUND DETAIL

DO NOT DISTIJRB STREAM SANK ~----l

GEDTEXTILE FABRIC

RElEASE ROCK AT GRADE TO AVOID SEDIMENT OISTIJRBANCE THEN COMPf

ROCK REPLACEMENT DETAIL CITY OF EUGENE P UBLIC INORKS ENGINEERING SCAlE: N.T.S

ORAFTEO OV· TBF DESIGNED BY· TRC

FIGURE 6: Rock Placement and Turn Around Detail Source: City of Eugene

Joint Removal-Fill Permit Application for City of Eugene's Amazon Channel Bank Stabilization Project: Royal to Berrelson, Eugene, Lane County, Oregon

March 2013

-~~-~,~~~~~~

TYPE II SEDIMENT CURTAIN SI·IAi..i. t,;I.)NTACT THE

BOPOM OF THE CHANNEL WHEN SUSPENDED IN W·\TER

r

WORK I ACCESS ZONE NO PARKING EQUIPMENT S TAGING OR STOCKPILING 1$ ALLOWED BEYOND WORK/ACCESS ZONE

SEDIMENT CUflT AIN

~

w 10

~I , ;

1.,

i

',.:/;

I ff;

M:

~'/

'

.

I

PRIOR TO A NY IN WATER WORK INSTALl A MINIMUM OF 200' OF SEDIMENT CURTAIN TO MANUFACTURES RECOMMENDATION CURT"-IN SHAL L ISOLATE THE.WORK'-REA HWM fNE ACTivE f l ( >W5 IN OROtfi TO CAPTURC SEDIMENT CAUSE'O llY H ll:: WORK C0N1'R AC T0 R SHI-Ll WORK WIT H THE ENGINEER 10 DE1ERMINE THE LENGTH Of THE CUK IAIN NECESSARY TO EFF+CIENTL Y PROCEEDWJ;'H ; HE WORK O NCE WORK l S COMPL!;TEO. MOVE CURTAiN SO AS NQ'r 1'0 DISTURB OR RELEASe SEDIMENT

~

I

'

~ L·-~ _r~ ; i l I

!

I

h

"'~

/'

o - - -- - - - -- -..1. I I

CITY OF EUGENE PUBLIC WORKS ENGINEERING

:

SCAlE =NT S . DRAFTED BY: C . PERINI DESIGNED BY· P COX - · ·:w:r:r; r·l;'· "- "'- Arf'l,tflr\

.t\MI'Iri Sl··iJ·I·i'iliJ?I'!

~ Eugen

Prrrr-,,· D·aw""?i.,.j7fe-C.~-'P0ell't!ls..p;g Ftf! J,1M fRS-R.:I)".'~~~ · n(l l 39 59 4·,i

FIGURE 7: Sediment Curtain Detail Source: City of Eugene

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas