You can copy from here when filling out the rest of the page.
Dominic Yballe is the Regulatory point-of-contact for this Public Notice Addendum to the proposed Columbia River Crossing Project (originally proposed in the Public Notice of Feb. 11, 2013).
Corps of Engineers No: NWP-2008-414 Notice Issued: June 7, 2013
Oregon Department of State Lands No: NA Written Comments Due: June 21, 2013
Interested parties are hereby notified that an application has been received for a Department of the Army permit for certain work in waters of the United States, as described below and shown on the attached plan.
Comments: Comments on the described work should reference the U.S. Army Corps of Engineers number shown above and reach this office no later than the above expiration date of this Public Notice to become part of the record and be considered in the decision. Comments should be mailed to the following address:
U.S. Army Corps of Engineers
Attention: Dominic Yballe
P.O. Box 2946
Portland, OR 97208-2946
Applicant: Oregon Dept. of Transportation and Washington Dept. of Transportation, 700 Washington St., Suite 300, Vancouver, WA 98660
Location: The project is located on Interstate 5 across the Columbia River between the cities of Portland, Ore. and Vancouver, Wash. (Center coordinates Lat/Long: 45.6167, -122.6750).
Waterway: Columbia River, Mile 106.5
Project Description:
CHANGES TO PROPOSED DESIGN
This Public Notice Addendum describes changes to the proposed Columbia River Crossing Project as originally proposed in the Public Notice of Feb. 11, 2013. The bridges across North Portland Harbor have been re-designed to address seismic safety concerns. The drilled shafts will transition to square columns from approximately six feet below the streambed to the top of mud line. Geotechnical samples will be taken to ensure the design is appropriate.
Each support will be isolated from flowing water using a cofferdam or oversized casing seated with a vibratory hammer. Each isolated area will measure approximately 19 feet in diameter for 285 square feet. These isolation measures will result in approximately 0.24 acre of additional in-water impacts over the original project proposal. The cofferdams will require approximately 5 days for installation, 30 days for in-place duration, and 1 day for removal. A maximum of 16 of 36 total isolated areas will be in place at any given time in the North Portland Harbor. Use of the temporary isolation is not expected to restrict recreational boating beyond original considerations, provided boats maintain safe distance from construction. Larger vessels may require special arrangement for passage during peak construction activity or during heavy river use.
Once an area is dewatered, sediment will be removed from around the drilled shaft casings down to a depth of six feet below mud line. Rebar or other reinforcing structures will be installed and concrete will be poured to mud line. The drilled shaft casing will then be cut to concrete level and the square columns will built from the drilled shafts up to the bridge superstructure level.
CLARIFICATION OF ORIGINAL PUBLIC NOTICE
In addition to the described project activities, the project will have temporary obstructions to navigation during construction. On the mainstem Columbia River, impacts include approximately two years of height restrictions limited to 100-feet vertical clearance above CRD (currently scheduled for January 2017 through April 2019). A tentative schedule of height and width restrictions are included with this notice.
The temporary height restrictions may affect the Corps ability to maintain upstream navigation channels. The Corps is coordinating with CRC to ensure channel maintenance is unaffected by the project activities.
Mitigation: Proposed mitigation remains unchanged since the original Public Notice from Feb. 11 through April 15, 2013. Please contact Dominic Yballe for details regarding compensatory mitigation for adverse aquatic impacts.
Purpose: The purpose of the project is to improve safety and vulnerability issues, improve commercial and general traffic mobility, and provide multimodal transit options between Vancouver, Wash. and Portland, Ore.
Enclosuress: There are thirteen pages attached and labeled Public Notice Addendum, Corp No. NWP-2008-414, dated June 7, 2013.
Additional Information: Additional information may be obtained from Dominic Yballe, Project Manager, U.S. Army Corps of Engineers, at 503-808-4392 or e-mail: dominic.p.yballe@usace.army.mil.
Authority: This permit will be issued or denied under the following:
Section 404, Clean Water Act of 1972 (33 U.S.C. 1344), for discharge of dredged or fill material into waters of the United States. Activities subject to this authority include discharges that change the bottom elevation of waters of the U.S. including but not limited to concrete poured into sealed forms, sand bag cofferdams, and approach fills in wetlands or below the ordinary highwater mark of water courses.
Section 10, Rivers and Harbors Act of 1899 (33 U.S.C 403), for activities that may affect the course capacity, condition, or location of navigable waters of the U.S. Activities subject to this authority include but are not limited to relocation or removal of in-water structures such as houseboats or supporting infrastructure. Activities related to construction, operation or maintenance of bridges or causeways in Navigable waterways is subject to separate authority by the U.S. Coast Guard. Fill associated with these activities may be captured under Section 404 of the Clean Water Act, Section 14, Rivers and Harbors Act of 1899 (33 U.S.C. 408): Taking possession of, use of, or injury to harbor or river improvements. Activities subject to this authority include those actions that would modify or affect the intended uses of federally authorized levees, navigation channels, or other federal projects.
Water Quality Certification: A permit for the described work will not be issued until certification, as required under Section 401 of the Clean Water Act (P.L. 95‑217), has been received or is waived from the certifying states.
Section 404(b)(1) Evaluation: The impact of the activity on the public interest will be evaluated in accordance with the Environmental Protection Agency guidelines pursuant to Section 404(b)(1) of the Clean Water Act.
Public Hearing: Any person may request in writing within the comment period specified in this notice that a public hearing be held to consider this application. Requests for public hearings shall state with particularity the reasons for holding a public hearing.
Endangered Species: Preliminary determinations indicate that the described activity may affect an endangered or threatened species or its critical habitat. The National Marine Fisheries Service issued a biological opinion to FHWA and FTA on January 18, 2011 for impacts to migratory aquatic species including sturgeon, salmon, steelhead, eulachon, and marine mammals. In a letter dated August 27, 2010, the US Fish and Wildlife Service indicated concurrence with FHWA and FTA that the project would not adversely affect Bull Trout. A permit decision will not be finalized until the lead Federal Agency has demonstrated compliance under the Endangered Species Act.
Cultural Resources: This notice has been provided to the State Historic Preservation Office, interested Native American Indian tribes, and other interested parties. If you have information pertaining to cultural resources within the permit area, please provide this information to the Corps project manager (identified above in this notice) to assist in a complete evaluation of potential effects.
The Corps entered into a Memorandum of Agreement on September 8, 2011 with the FHWA, FTA, the Washington Department of Historic Preservation, the Oregon State Historic Preservation Office, and with interested tribes. The Memorandum details the undertakings to be implemented in a manner that would minimize potential adverse impacts to known and undiscovered resources of concern.
Navigation: The project may affect navigation both temporarily and permanently. Issues such as bridge height and obstruction to navigation are considered by the Coast Guard under their authority under the General Bridge Act of 1946 and other related laws. The Corps will coordinate and provide comments to the Coast Guard through their evaluation of a bridge permit. The Corps will not authorize impacts that result in unacceptable impacts to navigation or that would preclude the Corps’ ability to maintain federally authorized projects.
Flood Risk: The North Portland Harbor crossings will affect federally authorized levees constructed for flood risk reduction. The Corps will assess potential impacts to flood protection and flood fighting capability. The Corps cannot authorize impacts that would reduce the protection provided by the federally authorized levees without Congressional re-authorization or de-authorization of the levees. The Corps will coordinate with the Multnomah County Drainage District for any potential affects to their ability to maintain the levees or to respond to flood risk events.
Evaluation: The decision to issue a permit will be based on an evaluation of probable impacts including cumulative impacts of the described activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the described activity, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the described activity will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and, in general, the needs and welfare of the people.
The Corps is soliciting comments from the public; Federal, state, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
Additional Requirements: State law requires that leases, easements, or permits be obtained for certain works or activity in the described waters. These requirements must be met where applicable, and a Department of the Army permit must be obtained before any work within the applicable Statutory Authority previously indicated may be accomplished. Other local governmental agencies may also have ordinances or requirements, which must be satisfied before the work is accomplished.
Memorandum
May 16, 2013
TO:
Dominic Yballe
FROM:
Steve Morrow
NWP-2008-414 Proposed Project Amendment
SUBJECT:
Introduction
The Columbia River Crossing team is currently developing advanced design of the roadway
improvements and bridge crossings over the Columbia River and North Portland Harbor,
including those for light rail and pedestrian/bicycle access. In the period between submittal
of the U.S. Army Corps of Engineers (USACE) Section 404 Clean Water Act Joint Permit
Application (404 JPA) (November 2012) and the present, the project design team conducted
additional calculations to ensure the proposed structures would meet seismic standards.
For all the North Portland Harbor bridges identified in the initial construction package and
the Hayden Island to I-5 south bridge (Figure 1 and Plan Sheets 1, 2, and 3), the use of
cofferdams and concrete seals is now proposed to allow for connection of drilled shafts to
columns below water level. Below is a summary of changes involving the use of cofferdams
within North Portland Harbor during construction activities.
North Portland Harbor
As a result of further refinement in design, one change involving the use of cofferdams within
NPH will occur, as follows:
·
The construction of each column will require the installation of an over-sized casing (small
diameter cofferdam).
Cofferdams/Oversized Casings
The conceptual designs of the bridges crossing the North Portland Harbor used for the
determination of impacts in the 404 JPA assumed a single shaft/single column substructure
configuration where each column was supported by a single drilled shaft. This resulted in 28
drilled shafts for the bridges in the ICP and an additional 8 drilled shafts for the Hayden Island to
I-5 South bridge. Additionally, it was assumed that the transition between the shaft and the
column would occur above the waterline present at the time of construction allowing for
column construction to occur above the water. The primary benefit of this design approach was
that this substructure could be constructed without the use of a cofferdam. The refined designs
for the bridges across the North Portland Harbor that have been performed since the submittal
of the 404 JPA have highlighted some seismic concerns regarding this approach, thus the need
for a change in design resulting in the required use of cofferdams.
The current designs for the bridges across the North Portland Harbor include lowering of the
shaft-to column transition to approximately the mudline and maintaining the single shaft-to
single-column approach. The construction of the column-to-drilled shaft transition would require
isolating the work area in the water to allow the work to be performed in the dry. This
360/737-2726
503/256-2726
06/07/2013 (Page 1 of 13)
1
WWW.COLUMBIARIVERCROSSING.ORG
700 WASHINGTON STREET, SUITE 300, VANCOUVER, WA 98660
Public Notice Addendum (Corps #NWP-2008-414)
NWP-2008-414 PROPOSED PROJECT AMENDMENT
construction method will be implemented by installing either an oversized circular casing or a
circular cofferdam. Tables 1, 2, and 3 below summarize the dimensions and timing of these
cofferdams, the approximate area for each cofferdam, and the total areas anticipated for all the
cofferdams in the North Portland Harbor. Casings/cofferdams will be seated into the sediment
with a vibratory driver. Fish salvage would occur during and after isolation. The first six feet of
sediment will be removed to provide a stable foundation for a concrete seal, and the drilled shaft
casing will be installed. The top of the drilled shaft casing will extend above the top of
casing/cofferdam to allow construction of the drilled shaft prior to dewatering. The drilled shaft
will be constructed within the drilled shaft casing, and the excavated material from the drilling
will be removed. Removed sediments will be disposed of in accordance with relevant permits.
As presented in the Oregon JPA, a reinforcement cage and concrete will be placed within the
drilled shaft casing up to the shaft/column transition zone. A concrete seal will be poured in the
annular space around the drilled shaft casing within each casing/cofferdam at the mudline to
prevent water from entering the cofferdam through hydraulic pressure. The top of the seal will
be at or within one foot of the existing mudline, resulting in a concrete seal that is six feet in
depth. Rebar or other reinforcing structure will likely not be needed in the seal concrete. Water
from within the casing/cofferdam will be pumped to a holding tank and disposed of in
accordance with permit requirements to provide a dry work area. Once the casing/cofferdam is
pumped dry, the drilled shaft casing will be cut off at the elevation of the bottom of the column
(approximately the top of the seal), and the column of the bridge will be constructed. As many
as 16 of the 36 total over-sized casings/cofferdams will be in place at any one time.
Due to safety concerns and the potential that seal removal would require extensive disturbance
of sediments, the seal is not able to be removed after construction is completed. After
construction of the shaft and supported substructure, the casing/cofferdam will be filled with
water to equalize the hydraulic pressure and then be vibrated out.
The presence of the casings/cofferdams in North Portland Harbor will result in the temporary
loss of approximately 285 square feet and 316 cubic yards of habitat per casing/cofferdam. For
the North Portland Harbor Bridges ICP this total equals 7,980 square feet and 8,837 cubic
yards (Table 1). For the Hayden Island to I-5 South bridge this total equals 2,280 square feet
and 2,525 cubic yards (Table 2). This habitat will not be accessible to fish for the duration of
casing/cofferdam use a period of approximately 30-36 days per casing/cofferdam (Table 3).
2
06/07/2013 (Page 2 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
NWP-2008-414 PROPOSED PROJECT AMENDMENT
TABLE 1. DIMENSIONS OF TEMPORARY COFFERDAMS USED IN NORTH PORTLAND BRIDGES ICP
CONSTRUCTION
a
DIAMETER (FT)
HEIGHT (FT)A
AREA PER
COFFERDAM
(SQ. FT.)
19
29.9
285
TOTAL
COFFERDAMS
TOTAL AREA
OF
COFFERDAMS
(SQ. FT.)
TOTAL VOLUME
OF
COFFERDAMSA
(CY)
28
7,980
8,837
Values are for between approximate average depth of mudline at -14 feet CRD and OHW of 15.9 feet CRD.
TABLE 2. DIMENSIONS OF TEMPORARY COFFERDAMS USED IN HAYDEN ISLAND TO I-5 SOUTH BRIDGE
CONSTRUCTION
a
DIAMETER (FT)
HEIGHT (FT)A
AREA PER
COFFERDAM
(SQ. FT.)
19
29.9
285
TOTAL
COFFERDAMS
TOTAL AREA
OF
COFFERDAMS
(SQ. FT.)
TOTAL VOLUME
OF
COFFERDAMSA
(CY)
8
2,280
2,525
Values are for between approximate average depth of mudline at -14 feet CRD and OHW of 15.9 feet CRD.
TABLE 3. CONSTRUCTION SUMMARY FOR COFFERDAMS IN NORTH PORTLAND HARBOR
DAYS
a
LOCATION
DURATION TO INSTALLA
DURATION OF
CONSTRUCTION
DURATION TO REMOVE
Each column
5
30
1
Days are calendar days.
For permanent impacts, resulting from the concrete seals being left in place, each concrete seal
represents an additional permanent substrate impact of 206 square feet and 46 cubic yards of
fill per casing/cofferdam. This value is in addition to the approximately 79 square feet of
permanent impact related to each bridge shaft already described in the November 2012 404
JPA. Therefore an additional permanent impact to waters of the US of 7,416 square feet (0.17
acre) and 1,647 cubic yards fill for all cofferdam/casing locations will occur.
Impact Tables and Sequencing
In the November 2012 404 JPA, the project proposed to permanently fill approximately 1.62
acres with 50,486 cubic yards in jurisdictional waters of the Columbia River and North Portland
Harbor within Oregon with structure.1 The project also proposed to permanently remove 0.639
1 The USACE, Oregon Department of State Lands, Washington Department of Ecology, and Washington Department of Fish and
Wildlife regulate material placed in or removed from subject jurisdictional waters in different ways. For USACE, structures consist of
that material that acts as a structure that could affect hydrologic characteristics. Temporary piles, wharf piles, barges, and other
floating structures are not considered structure under this definition.
3
06/07/2013 (Page 3 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
NWP-2008-414 PROPOSED PROJECT AMENDMENT
acre of and 43,928 cubic yards of existing structures (fill) in the Columbia River.2 The project
proposed to temporarily fill up to 0.646 acres with 40,047 cubic yards of material, and remove
an equal amount when these temporary structures are removed after use.
This amendment proposes the addition of the 7,416 square feet (0.17 acres) and 1,648 cubic
yards of new permanent concrete seals at 36 column sites in North Portland Harbor (Table 4).
No additional permanent removal is proposed at this time. Temporary impacts related to the
proposed cofferdams/casings would include an additional 11,362 cubic yards of fill, with an
equal amount of removal when these structures are removed (Table 5).
As stated in the November 2012 404 JPA, no jurisdictional wetlands will be impacted within
Oregon during construction or operation of the project.
For the purposes of this 404 Removal-Fill application, fill below the ordinary high water (OHW)
level on the mainstem Columbia River continues to consist of the following structures:
·
geotechnical borings,
·
temporary cofferdams,
·
permanent steel casings for bridge supports, and
·
permanent shaft caps.
Fill below the OHW level in North Portland Harbor consists of the following structures:
·
geotechnical borings,
·
temporary steel sheet piles or oversized casing
·
permanent concrete seals, and
·
permanent steel casings and columns for bridge supports.
Removal of structures below the OHW level on the mainstem Columbia River consists of the
following structures:
·
existing bridge piers.
No removal of USACE-defined permanent structures below the OHW level in North Portland
Harbor is proposed.
The project will have a net areal increase of permanent structure below the OHW level of
1.1509 acres and a slight increase in volume of 8,205 cubic yards (compared to the previously
calculated values of approximately 0.9819 acres and 6,558 cubic yards respectively) after the
existing bridge piers are removed.
2 Volume calculations do not include the material that would be removed from within the casings for the drilled shafts from the
mudline to tip elevation in the Troutdale Formation; likewise fill calculations do not include the fill material that would be placed
within the casings from mudline to tip elevation in the Troutdale Formation.
4
06/07/2013 (Page 4 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
NWP-2008-414 PROPOSED PROJECT AMENDMENT
TABLE 4. PROJECT FILL (APPROXIMATE VALUES)
TEMPORARY FILL TOTALS
PERMANENT FILL TOTALS
AREA (AC)
VOLUME (CY)
AREA (AC)
VOLUME (CY)
0.9471
60,348
1.5554
46,375
North Portland Harbor ICP
0.0
0.0
0.0505
3,444
Hayden Island to I-5 South Bridge
0.0
0.0
0.014
667
North Portland Harbor ICP Cofferdams
0.183
8,837
0.132
1,281
Hayden Island to I-5 South Bridge Cofferdams
0.052
2,525
0.038
366
Geotechnical Borings
<0.001
60
0
0
1.1827
71,770
1.7903
52,133
ELEMENT TYPE/LOCATION
Mainstem Columbia River ICP
Total Fill
TABLE 5. PROJECT REMOVAL
TEMPORARY REMOVAL TOTALS
PERMANENT REMOVAL
TOTALS
TOTAL
VOLUME
(CY)
TOTAL AREA (AC)
TOTAL VOLUME (CY)
TOTAL
AREA (AC)
0.9471
60,348
0.6394
43,868
North Portland Harbor ICP
0
0
0
0
Hayden Island to I-5 South Bridge
0
0
0
0
North Portland Harbor ICP Cofferdams
0.183
8,837
0
0
Hayden Island to I-5 South Bridge Cofferdams
0.052
2,525
0
0
Geotechnical Borings
<0.001
60
<0.001
60
1.1827
71,770
0.6394
43,928
ELEMENT TYPE/LOCATION
Mainstem Columbia River ICP
Total Removal
Other project elements will be placed below ordinary high water but are not considered fill by
USACE. For the purposes of this 404 JPA application, the following elements are not
considered structure or fill below the OHW level:
·
Mainstem Columbia River
·
·
·
temporary steel piles for work platforms and barge moorings, and
barges.
North Portland Harbor
·
temporary steel piles for work platforms and barge moorings.
For the purposes of this 404 JPA, the following elements are not considered removed structure
or removed fill below the OHW level:
·
Mainstem Columbia River
5
06/07/2013 (Page 5 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
NWP-2008-414 PROPOSED PROJECT AMENDMENT
·
·
·
portions of the wharf for the Red Lion at the Quay hotel, and
a dock and ship on the southern shore near the former Thunderbird Hotel.
North Portland Harbor
·
·
floating homes at Jantzen Beach moorage, and
docks and boathouses immediately upstream and downstream of the existing bridge.
Work barges will cover approximately 0.69 acres of water surface (proposed exclusively in the
mainstem Columbia River). Removal of floating homes, boathouses, and docks encompass
another 3.1 acres of area at the water surface. With the removal of these on-water elements
(i.e., floating homes, docks, and quay) less water surface will be impacted after the project than
is currently impacted.
Alternatives Considered but not Advanced
Other methods of construction were considered but were not feasible or resulted in additional
impacts to aquatic resources. Among these methods was increasing the number of drilled shafts
at each pier and incorporating a shaft cap above the water line. The current seismic design
criteria for this type of earthquake resisting system require the foundation elements to remain
undamaged (elastic) while the supported column sustains some controlled damage (plasticity)
to most efficiently and safely dissipate the energy imparted by the earthquake. The magnitude
of the lateral force that the foundation is subjected to is inversely proportional to the height of
the column. Further, the bending forces the foundation is subjected to is directly proportional to
the distance the foundation extends above the mudline. Constructing a shaft cap above the
water line would not only result in significantly shorter columns and higher lateral forces, but
also would dramatically increase the maximum bending forces in the foundation due to the
extension of the drilled shaft above the mudline. It's anticipated that these increased forces
would require approximately twice the number of shafts at each pier to maintain stability of the
bridge. Constructing twice the number of drilled shafts and constructing the shaft cap would
result in more hydroacoustic impacts for driven temporary piles to support the temporary work
bridges and drilling equipment platforms, increased permanent footprint in the bed of the river,
and higher project cost. Due to the small width and flow capacity of the North Portland Harbor
relative to the Columbia River, the waterline shaft cap would have an noticeable impact on the
safe width available for recreational watercraft, would increase the volume of fill in the
floodplain, and would prohibitively restrict hydraulic flows and lead to an unacceptable rise in the
water surface elevation.
Analysis of Potential Impacts
The incorporation of the over-sized casings or circular cell cofferdams will result in an increase
in impacts to water quality from turbidity, impacts to substrate, temporary loss of shallow-water
habitat, direct effects to fish from work area isolation and fish salvage, and hydroacoustic
impacts.
Elevated turbidity from installation of casings/cofferdams using vibratory methods, as well as
removal of casings/cofferdams using direct pull or vibratory methods, is expected to extend to
no more than 25 feet from the casings/cofferdams. It is likely that turbidity generated by
casing/cofferdam use will cause fish avoidance of the work area, may affect fish foraging
success, may impact eulachon spawning, and may cause physiological stress to fish. Turbidity
is not expected to cause mortality to any fish species.
6
06/07/2013 (Page 6 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
NWP-2008-414 PROPOSED PROJECT AMENDMENT
Installation of the casings/cofferdams is likely to generate low level noise and visual
disturbance. For this reason, fish are likely to actively avoid the work area during the
construction of casings/cofferdams. However, it is impossible to guarantee that no fish will
become trapped inside a casing/cofferdam. To minimize impacts to fish, the project will perform
measures to remove fish from the work area during and after the installation of the
casings/cofferdams.
Use of casings/cofferdams is not anticipated to restrict recreational boating beyond what was
already considered. Casings/cofferdams would be adjacent to work bridges supported by
temporary piles and under an oscillator for at least several days. Recreational craft should not
be using the area next to the work bridges or within the 4.5 feet between the highly active drilled
shaft/column construction zone and the edge of the proposed casing/cofferdam even if the
casing/cofferdam was not present.
The project will have a net areal increase of permanent structure below the OHW level of
1.1509 acres and a slight increase in volume of 8,205 cubic yards. Design of the compensatory
mitigation sites at the Lewis River confluence in Washington and Dabney State Recreation Area
on the Sandy River in Oregon continues with agency coordination. At this time, the CRC project
team feels additional mitigation actions or areas are not required to mitigate for the impacts
presented in the 404 JPA and this amendment.
Revisions to Section 3 Proposed Project Information of the JPA are attached, accounting for
the increased area and volume of cofferdams/casings in the temporary fill and removal sections.
Likewise, the value for total cubic yards for the project has been updated to account for the
increased volume associated with the casings/cofferdams. The values also reflect clarifications
to the temporary fill and removal values, so that all temporary fill is balanced by temporary
removals.
7
06/07/2013 (Page 7 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
(2) PROJECT LOCATION
Street, Road or Other Descriptive Location
Legal Description (attach tax lot map*)
The CRC project includes portions of the I-5 corridor
between Victory Boulevard on the north side of Portland,
Oregon to SR-500 in Vancouver, Washington. The project
includes the replacement of the current I-5 bridge over the
mainstem Columbia River, the expansion of the I-5 bridge
over North Portland Harbor, and extension of light rail into
the City of Vancouver with a terminus at Clark College.
Township
Range
1N
1N
2N
2N
2N
2N
2N
2N
1E
1E
1E
1E
1E
1E
1E
1E
Section
3
4
33
34
27
26
22
23
Quarter/Quarter
NE, SE, NW, SW
NE, SE
NE, SE
NE, NW, SW
NE, SE, NW, SW
NW
SE
SW
In or near (City or Town)
County
Tax Map # (Oregon only)
Tax Lot #2
City of Portland, OR
City of Vancouver, WA
Multnomah County, OR
Clark County, WA
1N1E03, 1N04A, 1N1E04, 2N1E33,
1N1E04AA, 1N1E03BB, 2N1E34CA,
2N1E34C, 2N1E34, 2N1E33A,
1N1E03B, 1N1E03, 1N1E03C,
1N1E03D, 1N1E03AC, 1N1E03CC
See Appendix B of Attachment A.
Wetland/Waterway (pick one)
River Mile (if known)
Latitude (in DD.DDDD format)
Longitude (in DD.DDDD format)
Columbia River
RM 106.5
45.6167
-122.6750
Directions to the site
I-5 Corridor from Portland, OR at Victory Boulevard to SR-500 in Vancouver, WA.
(3) PROPOSED PROJECT INFORMATION
Type:
Fill
Excavation (removal)
Brief Description:
In-Water Structure
Maintain/Repair an Existing Structure
The CRC project will entail both fill and removal below the OHW line of the Columbia River Mainstem and North Portland
Harbor. A new crossing will be constructed over the Columbia River Mainstem. Over North Portland Harbor a new mainland
connector structure and up to three connector structures associated with I-5 will be constructed The existing crossing over the
Columbia River Mainstem will be demolished and removed after the new structures over the river are complete.
Fill (See Section 2 of Attachment A for a full impact analysis)
Rock
Riprap
Wetlands
Waters below OHW
Gravel
Organics
Sand
Silt
Clay
Other:
Permanent (cy)
Temporary (cy)
0
0
Total cubic yards for
project
Impact Area in Acres
Dimensions (feet)
(including outside
OHW/wetlands)
0
L'
0
W'
0
H'
Permanent (cy)
Temporary (cy)
71,770
Total cubic yards for
project
Impact Area in Acres
Dimensions (feet)
(including outside
OHW/wetlands)
1.7903 perm(1.1827tmp)
L'
W'
varies
H'
0
0
52,133
varies
Steel/concrete
533,009
varies
Removal (See Section 2 of Attachment A for a full impact analysis)
Wetlands
Waters below OHW
2
Permanent (cy)
Temporary (cy)
0
0
Total cubic yards for
project
Impact Area in Acres
Dimensions (feet)
(including outside
OHW/wetlands)
0
L'
Permanent (cy)
Temporary (cy)
43,928
71,770
Total cubic yards for
project
Impact Area in Acres
Dimensions (feet)
(including outside
OHW/wetlands)
0.6394perm(1.1827tmp)
L'
0
W'
varies
W'
0
varies
H'
H'
0
0
311,770
varies
Attach a copy of all tax maps with the project area highlighted.
·
Italicized areas are not required by the Corps for a complete application, but may be necessary prior to final permit decision by the Corps.
2
06/07/2013 (Page 8 of 13)
v. 07-07-09
Public Notice Addendum (Corps #NWP-2008-414)
Jr.
Blv
d.
r
oI
5
er
K
ing
cto
arti
n
eD
r. e
a
st t
Lu
th
dC
on
ne
lan
Ma
in
2-I5
3-
sout
h
Mar
in
to M
1-
²
0
0.025
ICP Project Footprint
Figure 1
Bridge numbers correspond to
Plan Sheets 1 - 3.
0.05
Miles
Date: 5/10/2013 Path: P:\GIS\CRC\GIS\PH_404_Permits\Ph_404_Oregon_InWater.mxd
06/07/2013 (Page 9 of 13)
Public Notice Addendum (Corps #NWP-2008-414)
SEC. 33 & 34. T. 2N .. R1 E.. W.M.
CITY OF PORTLAND
PLAN
llEARING OF PIER 1 IS S 6-4" ~9'04-" E
ElEMIING OF PIEIIS 2, "· 4-, 5, liND 6 15 S 65"Z)7'2El" E
llEII~ING OF PIU 7 IS N 71"29'0Z)'' W
~ PIER 5
MC STII. Z)1+15.1l0
~ PIERZ)
IMC STII. 26+65.55
PIH 1
IMC
STA. 2"+15.91)
-.., __ ------- --rv....,.~:-·--·--·--·--·--·
"
~ P/1"11?
7
_,;TOP OF DECK
~--·--·--·--·--·--·--·--·--·
\,
;.,-sGilJIIRE COWMN
H
________Qti.~.s~~~::..~r.2 2
. ./""DRILLED SHIIFT
~
+··--·--·--·--;r, -'
, ..
- ------------------ -----·· - -··-J,,,.,EXTCi. CiROUND
c....
Ill:·,
DEVELOPED ELEVATION
DATUM
NAVD Ill!>
FOR PERMITTING PURPOSES ONLY
NOT FOR CONSTRUCTION
,·,
H
--·--·--·--·- . -·--·--·--·--·--·--·--·--·--
~------:.~. ------------------------ . - : : - - - - - - - - - - - - - - - - - - - - - - - - - -
06/07/2013 (Page 10 of 13)
{ PIER 6
-
-
-----------\_RET!liNING
Wll/./.
MC LINE
STEEL PLATE GIRDERS
LOADING HL-93
~ Waahington State
...,., Department of Transportation
LRT(NPH) PLAN AND ELEVATION
;7,1F Oregon Deparlment
IJ/£ of rransportatlon
Plan Sheet
-1
Columbia River
·CROSSING
Public Notice Addendum (Corps #NWP-2008-414)
SEC. 34. T. 2N .. R1 E.. W.M.
CITY OF PORTLAND
6!58'-5" NPH PIE1e5
MEJ\BUitEO ;t~N~ 55-MLK LINE
PLAN
IJEII~ING OF NP~S S 65"37'28' E
5"·Mll( S A. 13><+ IID.51
55-MLK ST A 129+84.87
55-MLK 5TA 12t>+02.!57
,_ ·- - - - - - - - - - - - - -
·-··-··-··-··-··-··-··-··-··-··-··
E
n
H
~~! -.~:~_· ·-··-··-··-··-··-··-··-··-··
~ PIEII. 7
55-MLK ST A 1:54+30.7t>
~PIE~ 6
~ f"/EII. 5
~ PIEII. 4
·-··-··o~~i~~V..?J·l~--··-··- ··- ··- ··- ··- ··- · ··- ··- ··- ··- ··- ··- ··E:I~T~~~ :;a:~~-
F'
· ,-··-··-··-··-
,, ... -
·-.~~=-~···
~-~-r~~~~~~~ -~~~:._r_----------.------- .. - ~-:~ ----- ·... -----------------------.--- .. ----------. - .-.---------- .. --- /_~ -~~-~~~. ~~~~-. ----. - ... ----------_/·~'
C~J
DEVELOPED ELEVA T/ON
STEEL PLATE GIRDERS
LOADING HL-93
DATUM
~ Waahington State
...,, Department of Transportation
5S-MLK(NPHJ PLAN AND ELEVATION
NIIVD 88
FOR PERMITTING PURPOSES ONLY
NOT FOR CONSTRUCTION
06/07/2013 (Page 11 of 13)
;7,1F Oregon Deparlment
IJ/£ of rransportatlon
Plan Sheet
-2
Columbia River
·CROSSING
Public Notice Addendum (Corps #NWP-2008-414)
SEC. 34. T. 2N .. R1 E.. W.M.
CITY OF PORTLAND
!!>77'-6" NPH PIE~5
MEi15URED ,O.LONG MVE-5N LINE
192'-10"
.246'-l!"
245'-11"
t--!
"'·
Oii:l
"'!
PLAN
/3E,O.RJNG OF NPH""Pii!iS'Ts 5 65" !37'2!!>'' E
~ PIER 3
MDE-5N ST,O., 125+52.02
I'IH 6
MVE-5N STA 1131+85.77
MDE-5N STA 129+39.!!>!!>
MVE-5N STA 127+47.02
{PIER 7
MDE-6N STA 134+131.66
~PIER 13
MDE-5N ST,0., 1136+.24.52
/TOP OF DECK
.----,-----~cr.
/SQU,O.~E
b,J '·,-:.:·- ··- ··- ··- ··- ··- ··- ··- ··- ··
·------------
··
··- ··- ··- ··- · · - · · - · · - · · - · · - · · - · · - ·
····-------------h-r·--___...__----------·-----------
E
p
--------.----------
COLUMN
VDIII. 01/.ILLED SHN'T
H
H
H
p.- E
··-··-Cll;l\li:.~L!;~.~1,~~---··-··-··-··-··-··-··
-··-··-··-··-··-··-··-··-··-··-··-··-··-··· ··-··-··-··-··-··-··-··-··-··-.-'''
~:~
1 -:-J -·-·------------------------------ --1---~------ __ ------------- ___ ----------~:·: -----------~·'--·'
-~...
------·"'-EXISTING
G~OUNO
f) MOE-5N LINE
t--.J
DEVELOPED ELEVA T/ON
STEEL PLATE GIRDERS
LOADING HL-93
DATUM
~ Waahington State
...,., Department of Transportation
MDE-5N PLAN AND ELEVATION
Ni\VO 88
FOR PERMITTING PURPOSES ONLY
NOT FOR CONSTRUCTION
06/07/2013 (Page 12 of 13)
;7,1F Oregon Deparlment
IJ/£ of rransportatlon
Plan Sheet
-3
Columbia River
·CROSSING
Public Notice Addendum (Corps #NWP-2008-414)
Columbia River
CROSSING Navigation clearance during construction
'"
Pre-Construction
Post-Construction
\
:300':
JiQri~o"ta~
:and 116' '
Min~ Vertical
Clearance
300' :
Horizc)nt81
and il4'
vemca~
Clearance
LEGEND
Channel is open
II Channel is open with width constraints
·
Channel is open with width and height constraints
·
Channel is closed
NOTE: Schedule is a projection. Actual construction durations will vary. All vertical clearances are referenced from 0 CRD. All identified clearance constraints are in reference to pre-construction conditions .
06/07/2013 (Page 13 of 13)
UPOAT£0:03/11/13
Public Notice Addendum (Corps #NWP-2008-414)