You can copy from here when filling out the rest of the page.
WHARF AND CAMP CONSTRUCTION IN LAFOURCHE PARISH
NAME OF APPLICANT: Lane Adams, 310 Saint Joseph Street, Raceland, Louisiana, 70394.
LOCATION OF WORK: Lat 29.64925 / Long -90.571392; on the west bank of the Bayou Folse Canal, in Lafourche Parish, Louisiana. The Project is located within the Lafourche Basin, Hydrologic Unit 08090301.
CHARACTER OF WORK: Rebuild existing bulkheads at the banks of Bayou Folse Canal and Lake Fields. Construct two 20’ x 8’ wharfs and construct a 20’ x 20’ camp for recreational use. No fill material would be discharged and no jurisdictional wetlands would be impacted.
DEPARTMENT OF THE ARMY
NEW ORLEANS DISTRICT, CORPS OF ENGINEERS
P. O. BOX 60267
NEW ORLEANS, LOUISIANA 70160-0267
September 1, 2014
REPLY TO
ATTENTION OF:
Operations Division
West Evaluation Section
Project Manager
Johnny Duplantis
(504) 862-2548
SUBJECT: MVN-2014-1778-WPP
PUBLIC NOTICE
Interested parties are hereby notified that a permit application has been received by the
New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of
the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [ ]
Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344).
WHARF AND CAMP CONSTRUCTION IN LAFOURCHE PARISH
NAME OF APPLICANT: Lane Adams, 310 Saint Joseph Street, Raceland, Louisiana,
70394.
LOCATION OF WORK: Lat 29.64925 / Long -90.571392; on the west bank of the
Bayou Folse Canal, in Lafourche Parish, Louisiana. The Project is located within the
Lafourche Basin, Hydrologic Unit 08090301.
CHARACTER OF WORK: Rebuild existing bulkheads at the banks of Bayou Folse
Canal and Lake Fields. Construct two 20' x 8' wharfs and construct a 20' x 20' camp for
recreational use. No fill material would be discharged and no jurisdictional wetlands
would be impacted.
The comment period for the Department of the Army will close 15 days from the date
of this public notice advertisement. Written comments, including suggestions for
modifications or objections to the proposed work, stating reasons thereof, are being
solicited from anyone having interest in this permit request and must be mailed so as to
be received before or by the last day of the comment period. Letters must reference the
applicant's name and the subject number, be addressed and mailed to the above
address, ATTENTION: REGULATORY BRANCH. Individuals or parties may
request an extension of time in which to comment on the proposed work by
writing to the project manager or clicking on the project manager's name on the
public notice grid on the web page. Any request must be specific and
substantively supportive of the requested extension, and received by this office
prior to the end of the initial comment period. The Section Chief will review the
request and the requester will be promptly notified of the decision to grant or
-2-
deny the request. If granted, the time extension will be continuous to the initial
comment period and, inclusive of the initial comment period, will not exceed a
total of 30 calendar days.
The decision whether to issue a permit will be based on an evaluation of the
probable impacts, including cumulative impacts of the proposed activity on the public
interest. That decision will reflect the national concern for both protection and utilization
of important resources. The benefit which reasonably may be expected to accrue from
the proposal must be balanced against its reasonably foreseeable detriments. All
factors which may be relevant to the proposal will be considered including the
cumulative effects thereof; among those are conservation, economics, aesthetics,
general environmental concerns, wetlands, historic properties, fish and wildlife values,
flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food and
fiber production, mineral needs, considerations of property ownership and, in general,
the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal,
state, and local agencies and officials, Indian Tribes, and other interested parties in
order to consider and evaluate the impacts of this proposed activity. Any comments
received will be considered by the U.S. Army Corps of Engineers to determine whether
to make, modify, condition, or deny a permit for this proposal. To make this decision,
comments are used to assess impacts on endangered species, historic properties,
water quality, general environmental effects, and other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or
an Environmental Impact Statement pursuant to the National Environmental Policy Act.
Comments are also used to determine the need for a public hearing and to determine
the overall public interest of the proposed activity.
No properties listed on the National Register of Historic Places are near the
proposed work. The possibility exists that the proposed work may damage or destroy
presently unknown archaeological, scientific, prehistorical or historical sites or data.
Copies of this notice are being sent to the State Archeologist and the State Historic
Preservation Officer.
Our initial finding is that the proposed work would neither affect any species listed
as endangered by the U.S. Departments of Interior or Commerce, nor affect any habitat
designated as critical to the survival and recovery of any endangered species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of
the Magnuson-Stevens Fishery Conservation and Management Act. The applicant's
proposal would result in the destruction or alteration of N/A acre(s) of EFH utilized by
various life stages of red drum and penaeid shrimp. Our initial determination is that the
-3-
proposed action would not have a substantial adverse impact on EFH or federally
managed fisheries in the Gulf of Mexico. Our final determination relative to project
impacts and the need for mitigation measures is subject to review by and coordination
with the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable
waters, the evaluation of the probable impacts will include the application of guidelines
established by the Administrator of the Environmental Protection Agency. Also, a
certification that the proposed activity will not violate applicable water quality standards
will be required from the Department of Environmental Quality, Office of Environmental
Services, before a permit is issued.
Any person may request, in writing, within the comment period specified in this
notice, that a public hearing be held to consider this application. Requests for public
hearings shall state, with particularity, the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any
other parties whom you deem likely to have interest in the matter.
The applicant has certified that the proposed activity described in the application
complies with and will be conducted in a manner that is consistent with the Louisiana
Coastal Resources Program. The Department of the Army permit will not be issued
unless the applicant received approval or a waiver of the Coastal Use Permit by the
Department of Natural Resources.
Darrell S. Barbara
Chief, Western Evaluation Section
Regulatory Branch
Attachments