MAINTENANCE DREDGING AT EXISTING DOCK IN THE MISSISSPPI RIVER IN ASCENSION PARISH
NAME OF APPLICANT: Shell Chemical, LP, c/o Lanier & Associates Engineers, 4101 Magazine Street, New Orleans, Louisiana 70115.
LOCATION OF WORK: Within the Mississippi River Basin, in the Lower Mississippi River – Baton Rouge hydrologic unit (HUC 08070100), in the Mississippi River, left descending bank, approximately 183 miles above the Head of Passes, near Geismar, Louisiana, in Ascension Parish, as shown on the enclosed drawings.
CHARACTER OF WORK: The applicant proposes to use a hydraulic dredge to remove 54,000 cubic yards of silty sand within a 7.7-acre area to allow access to an existing dock and remove the scour hole at the site. The dredged material will be deposited below the -55’ contour. Dredging operations will last approximately 3-4 weeks and will occur every 2 years. No vegetated wetlands will be impacted.
JOINT PUBLIC NOTICE
January 26, 2015
United States Army
Corps of Engineers
New Orleans District
Regulatory Branch
Post Office Box 60267
New Orleans, Louisiana 70160-0267
State of Louisiana
Department of Environmental Quality
Water Quality Certification Section
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-2675
Project Manager
Jamie Crowe
Jamie.M.Crowe@usace.army.mil
Permit Application Number
MVN 2010-2982 CO
(225) 219-3225
Project Manager
Elizabeth Johnson
WQC Application Number
WQC 150116-01
Interested parties are hereby notified that a permit application has been received by
the New Orleans District of the U.S. Army Corps of Engineers pursuant to:
[X] Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC
403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental
Quality, Office of Environmental Services, for a Water Quality Certification (WQC) in
accordance with statutory authority contained in LRS30:2047 A(3), and provisions of
Section 401 of the Clean Water Act (P.L.95-17).
MAINTENANCE DREDGING AT EXISTING DOCK IN THE MISSISSPPI RIVER IN
ASCENSION PARISH
NAME OF APPLICANT: Shell Chemical, LP, c/o Lanier & Associates Engineers, 4101
Magazine Street, New Orleans, Louisiana 70115.
LOCATION OF WORK: Within the Mississippi River Basin, in the Lower Mississippi
River Baton Rouge hydrologic unit (HUC 08070100), in the Mississippi River, left
descending bank, approximately 183 miles above the Head of Passes, near Geismar,
Louisiana, in Ascension Parish, as shown on the enclosed drawings.
CHARACTER OF WORK: The applicant proposes to use a hydraulic dredge to
remove 54,000 cubic yards of silty sand within a 7.7-acre area to allow access to an
existing dock and remove the scour hole at the site. The dredged material will be
deposited below the -55' contour. Dredging operations will last approximately 3-4
weeks and will occur every 2 years. No vegetated wetlands will be impacted.
The comment period for the Department of the Army Permit and the Louisiana
Department of Environmental Quality WQC will close 30 days from the date of this joint
public notice. Written comments, including suggestions for modifications or objections
to the proposed work, stating reasons thereof, are being solicited from anyone having
interest in this permit and/or this WQC request and must be mailed so as to be received
before or by the last day of the comment period. Letters concerning the Corps of
Engineers permit application must reference the applicant's name and the Permit
Application Number, and be mailed to the Corps of Engineers at the address above,
ATTENTION: REGULATORY BRANCH Letters concerning the Water Quality
Certification must reference the applicant's name and the WQC Application number
and be mailed to the Louisiana Department of Environmental Quality at the address
above. The application for this proposed project is on file with the Louisiana
Department of Environmental Quality and may be examined weekdays between 8:00
a.m. and 4:30 p.m. Copies may be obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the
probable impacts, including cumulative impacts of the proposed activity on the public
interest. That decision will reflect the national concern for both protection and utilization
of important resources. The benefit which reasonably may be expected to accrue from
the proposal must be balanced against its reasonably foreseeable detriments. All
factors which may be relevant to the proposal will be considered including the
cumulative effects thereof; among those are conservation, economics, aesthetics,
general environmental concerns, wetlands, historic properties, fish and wildlife values,
flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food
and fiber production, mineral needs, considerations of property ownership and, in
general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal,
state, and local agencies and officials, Indian Tribes, and other interested parties in
order to consider and evaluate the impacts of this proposed activity. Any comments
received will be considered by the U.S. Army Corps of Engineers to determine whether
to make, modify, condition, or deny a permit for this proposal. To make this decision,
comments are used to assess impacts on endangered species, historic properties,
water quality, general environmental effects, and other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or
an Environmental Impact Statement pursuant to the National Environmental Policy Act.
Comments are also used to determine the need for a public hearing and to determine
the overall public interest of the proposed activity.
The New Orleans District is unaware of properties listed on the National Register of
Historic Places near the proposed work. The possibility exists that the proposed work
may damage or destroy presently unknown archeological, scientific, prehistorical,
historical sites, or data. Issuance of this public notice solicits input from the State
Archeologist and State Historic Preservation Officer regarding potential impacts to
cultural resources.
The proposed activity is located in waters known to be utilized by the pallid
sturgeon (Scaphirhynchus albus). Approximately 7.7 acres of foraging habitat will be
directly impacted by the proposed activity. The applicant has agreed to the following
conditions: (1) the cutterhead shall remain completely buried in bottom material during
dredging operations; (2) If pumping water through the cutterhead is necessary to
dislodge material or to clean the pumps or cutterheads, etc, the pumping rate shall be
reduced to the lowest rate possible until the cutterhead is at mid-depth, where the
pumping rate can be increased; (3) During dredging, the pumping rates shall be
reduced to the slowest speed feasible while the cutterhead descends to the bottom.
Based on Standard Local Operating Procedure for Endangered Species in Louisiana
(SLOPES), dated October 22, 2014, between the U.S. Army Corps of Engineers , New
Orleans and U.S. Fish and Wildlife Service , Ecological Services Office , the Corps has
determined that the proposed dredging is not likely to adversely affect the pallid
sturgeon, provided the conditions outlined above are included in the authorization.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of
the Magnuson-Stevens Fishery Conservation and Management Act. The applicant's
proposal would result in the destruction or alteration of N/A acres of EFH utilized by
various life stages of red drum and penaeid shrimp. Our initial determination is that the
proposed action would not have a substantial adverse impact on EFH or federally
managed fisheries in the Gulf of Mexico. Our final determination relative to project
impacts and the need for mitigation measures is subject to review by and coordination
with the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable
waters, the evaluation of the probable impacts will include the application of guidelines
established by the Administrator of the Environmental Protection Agency. Also, a
certification that the proposed activity will not violate applicable water quality standards
will be required from the Department of Environmental Quality, Office of Environmental
Services, before a permit is issued.
Any person may request, in writing, within the comment period specified in this
notice, that a public hearing be held to consider this application. Requests for public
hearings shall state, with particularity, the reasons for holding a public hearing. You are
requested to communicate the information contained in this notice to any other parties
whom you deem likely to have interest in the matter.
You are requested to communicate the information contained in this notice to any
other parties whom you deem likely to have interest in the matter.
John M. Herman
Chief, Central Evaluation Section