UPSTREAM SHIP AND BARGE DOCK IN MISSISSIPPI RIVER IN ASCENSION PARISH
NAME OF APPLICANT: IMTT Geismar, c/o Infinity Engineering Consultants, LLC, 2626 Canal Street, Suite 202, New Orleans, LA 70119.
LOCATION OF WORK: In the Mississippi River, Left Descending Bank, River Mile 184, at 8122 Highway 75 in Geismar, Louisiana, in Ascension Parish, within the Mississippi River Basin in hydrologic unit (HUC 08070100), as shown on the attached drawings.
CHARACTER OF WORK: The applicant has requested Department of the Army authorization to remove existing pile structures to install a new barge dock and new barge/ship dock structures including a barge platform, a barge/ship platform, a walkway, and mooring and breasting structures which will extend a maximum of 537 linear feet channelward from the toe of the levee. Approximately 1,500 cubic yards of stone rip-rap material will be hauled in and deposited for the necessary repairs to the revetment within an approximate 1,125 linear feet area. It is anticipated that the proposed action would have minimal impact on adjacent wetlands.
The applicant has designed the project to avoid and minimize direct and secondary adverse impacts to the maximum extent practicable. The applicant proposes to avoid additional direct impacts and minimize secondary impacts (to wetlands) by performing all work from the waterway utilizing vessels and marine equipment. No equipment will be placed on the batture and materials to be removed will be placed on a barge and hauled off-site. A preliminary analysis has determined that the proposed project would not directly impact wetlands therefore, no compensatory mitigation is required.
JOINT PUBLIC NOTICE
September 19, 2016
United States Army Corps of Engineers
New Orleans District
Regulatory Branch
Post Office Box 60267
New Orleans, Louisiana 70160-0267
State of Louisiana
Department of Environmental Quality
Office of Environmental Services
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-1545
Project Manager
S. Gail Gainey
Sandra.G.Gainey@usace.army.mil
MVN-2014-00284-CG
(225) 219-3225
Project Manager
Elizabeth Hill
WQC Application Number
WQC # 160916-03
Interested parties are hereby notified that a permit application has been received by the
New Orleans District of the US Army Corps of Engineers pursuant to: [ ] Section 10 of the
Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section
404 of the Clean Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality,
Office of Environmental Services, for a Water Quality Certification (WQC) in accordance
with statutory authority contained in LRS 30:2074 A(3) and provisions of Section 401 of the
Clean Water Act.
PROPOSED METHANOL PIPELINE IN ASCENSION PARISH
NAME OF APPLICANT: International Matex Tank Terminal, c/o ELOS Environmental,
LLC, 43177 East Pleasant Ridge Road, Hammond, LA 70403.
LOCATION OF WORK: East and along Highway 75, Sections 11 and 14, T10S-R2E, in
Geismar, Louisiana, in Ascension Parish, within the Lake Maurepas Basin in hydrologic
unit (HUC 08070204), as shown on the attached drawings (Latitude 30.194303 N,
Longitude -91.016059 W).
CHARACTER OF WORK: The applicant has requested Department of the Army
authorization to clear, grade, excavate and deposit fill to install and maintain a 12-inch
methanol pipeline. Horizontal Directional Drilling will be utilized along with trenching and
backfilling to install 5,850 linear feet of pipeline. Approximately 2,609 cubic yards will be
excavated and backfilled along with approx. 702 cubic yards of sand material to achieve
required grade elevation requirements. Any remaining excavated fill material will be
hauled off-site for disposal. The proposed project is situated on an approximately 6,000
linear-foot corridor that has been determined to include forested and emergent wetlands
and waters of the U.S. Of this, approximately 0.59 acres of emergent wetlands and
approx. 1.16 acres of forested wetlands would be directly impacted. The remainder of the
property will be left in its natural state. It is anticipated that the proposed action would
have minimal impact on adjacent wetlands.
2
It is presumed that the applicant has designed the project to avoid and minimize direct
and secondary adverse impacts to the maximum extent practicable. Any further reduction
would limit usage of the property and, therefore function deeming the project impracticable.
As compensation for unavoidable wetland impacts, the applicant proposes to mitigate inkind wetland credits from a Corps approved mitigation bank located in the watershed
The comment period for the Department of Army will close in 20 days from the date of
this joint public notice. Written comments, including suggestions for modifications or
objections to the proposed work, stating reasons thereof, are being solicited from anyone
having interest in this permit and/or this WQC request and must be mailed so as to be
received before or by the last day of the comment period. Letters concerning the Corps of
Engineers permit application must reference the applicant's name and the Permit
Application Number, and be mailed to the Corps of Engineers at the address above,
ATTENTION: REGULATORY BRANCH. Similar letters concerning the Water Quality
Certification must reference the applicant's name and the WQC application number and be
mailed to the Louisiana Department of Environmental Quality at the address above.
Individuals or parties may request an extension of time in which to comment on the
proposed work by writing or e-mailing the Corps of Engineers Project Manager listed
above. Any request must be specific and substantively supportive of the requested
extension, and received by this office prior to the end of the initial comment period. The
Section Chief will review the request and the requestor will be promptly notified of the
decision to grant or deny the request. If granted, the time extension will be continuous to
the initial comment period and, inclusive of the initial comment period, will not exceed a
total of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of
Environmental Quality and may be examined during weekdays between 8:00 a.m. and
4:30 p.m. Copies may be obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable
impacts, including cumulative impacts of the proposed activity on the public interest. That
decision will reflect the national concern for both protection and utilization of important
resources. The benefit which reasonably may be expected to accrue from the proposal
must be balanced against its reasonably foreseeable detriments. All factors which may be
relevant to the proposal will be considered including the cumulative effects thereof; among
those are conservation, economics, aesthetics, general environmental concerns, wetlands,
historic properties, fish and wildlife values, flood hazards, floodplain values, land use,
navigation, shoreline erosion and accretion, recreation, water supply and conservation,
water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the people.
The US Army Corps of Engineers is soliciting comments from the public, federal, state,
and local agencies and officials, Indian Tribes, and other interested parties in order to
consider and evaluate the impacts of this proposed activity. Any comments received will
be considered by the US Army Corps of Engineers to determine whether to make, modify,
condition, or deny a permit for this proposal. To make this decision, comments are used to
3
assess impacts on endangered species, historic properties, water quality, general
environmental effects, and other public interest factors listed above. Comments are used
in the preparation of an Environmental Assessment and/or an Environmental Impact
Statement pursuant to the National Environmental Policy Act. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
The New Orleans District is unaware of properties listed on the National Register of
Historic Places near the proposed work. The possibility exists that the proposed work may
damage or destroy presently unknown archeological, scientific, prehistorical, historical
sites, or data. Copies of this notice are being sent to the State Archeologist and the State
Historic Preservation Officer.
Our initial finding is that the proposed work would neither affect any species listed as
endangered by the U.S. Departments of Interior or Commerce, nor affect any habitat
designated as critical to the survival and recovery of any endangered species. Utilizing
Standard Local Operating Procedure for Endangered Species in Louisiana (SLOPES),
dated October 22, 2014, between the U.S. Army Corps of Engineers, New Orleans and
U.S. Fish and Wildlife Service, Ecological Services Office, the Corps has determined that
the proposed activity would have no effect on any listed species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the
Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal
would result in the destruction or alteration of up to 0 acres of EFH utilized by various life
stages of red drum and penaeid shrimp. Our initial determination is that the proposed
action would not have a substantial adverse impact on EFH or federally managed fisheries
in the Gulf of Mexico. Our final determination relative to project impacts and the need for
mitigation measures is subject to review by and coordination with the National Marine
Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters,
the evaluation of the probable impacts will include the application of guidelines established
by the Administrator of the Environmental Protection Agency. Also, a certification that the
proposed activity will not violate water quality standards will be required from the
Department of Environmental Quality, Office of Environmental Services before a permit is
issued.
Any person may request, in writing, within the comment period specified in this notice,
that a public hearing be held to consider this application. Requests for public hearings
shall state, with particularity, the reasons for holding a public hearing. You are requested
to communicate the information contained in this notice to any other parties whom you
deem likely to have interest in the matter.
JOHN M. HERMAN
Chief, Central Evaluation Section
Regulatory Branch