You can copy from here when filling out the rest of the page.
The applicant has revised its plans for a facility expansion and associated mitigation.
Full Public NoticeProject PlansMitigation PlanResponse to Comments
Dow proposes to discharge fill material into 10.71 acres of adjacent wetlands (same amount as previous public notice) for the construction of a Pressure Swing Adsorption Unit along with a reduced footprint for the parking area/lay down area (change from previous public notice). The proposed Pressure Swing Adsorption Unit is needed to take a hydrocarbons waste gas stream which is currently burned and convert this waste gas stream to a beneficial use product. The parking area/lay down area will support construction and operations of the Propane Dehydrogenation Unit and Light Hydrocarbon 9 Unit facilities which are both being built in uplands, where previous manufacturing facilities and equipment were located. The entire 35.3 acre project site will be utilized for this revised project.