The U.S. Army Corps of Engineers, Albuquerque District, Regulatory Division has issued new guidance, effective immediately, for processing of Nationwide Permits where work would be located within designated Gold Medal Waters on the Arkansas River in the State of Colorado, as designated by Colorado Parks and Wildlife. The purpose of this guidance is to inform prospective applicants of timing requirements and special conditions that may be required in order to avoid adverse impacts to important spawning areas in accordance with the Nationwide Permits General Condition No. 3 and Colorado Regional Condition No. 7.
Summary: The U.S. Army Corps of Engineers, Albuquerque District, Regulatory Division (Corps) has issued new guidance, effective immediately, for processing of Nationwide Permits where work would be located within designated Gold Medal Waters on the Arkansas River in the State of Colorado, as designated by Colorado Parks and Wildlife (CPW). The purpose of this guidance is to inform prospective applicants of timing requirements and special conditions that may be required in order to avoid adverse impacts to important spawning areas in accordance with the Nationwide Permits General Condition No. 3 and Colorado Regional Condition No. 7.
Background: The Corps authorizes Nationwide Permits for projects discharging fill into waters of the U.S. The Pueblo Regulatory Office verifies Nationwide Permit compliance for projects discharging fill into the Arkansas River drainage. The Clean Water Act, Section 404, 2012 Nationwide Permits include conditions that need to be met in order to use or operate under the authorization.
General Condition (GC) No. 3 is a national condition and refers to Spawning Areas. Activities in spawning areas during spawning seasons must be avoided to the maximum extent practicable. Activities that result in the physical destruction (e.g., through excavation, fill, or downstream smothering by siltation) of an important spawning area are not authorized.
Regional Condition (RC) No. 7 is a regional condition applicable to all Nationwide Permits in Colorado, is an amendment to GC No. 3 above, and refers to Important Spawning Areas. Activities are not authorized by any nationwide permit except after case-by-case review and consultation with CPW if the activities would destroy important spawning areas or would be conducted in these waters during trout and Kokanee spawning seasons. Bio-engineering techniques, such as native riparian shrub plantings, are required for all bank protection activities that exceed 50 linear feet in important spawning areas. For activities located in these important spawning areas, a Pre-Construction Notification (PCN) is required and consultation with CPW must be conducted. Important spawning areas are identified in the list of Gold Medal Waters in Colorado (Attachment 2).
Attachment 2 of the Regional Conditions includes the preface: The following list of important spawning areas has been defined as Gold Medal Waters by the State of Colorado. As a reminder, according to RC 7 above, a PCN is required for all proposed nationwide permit activities in these waters; consultation with CPW must be conducted.
NOTE: This list of Gold Medal Waters is subject to change. For the most current list, please refer to the CPW Colorado Fishing Brochure available on the CPW website (http://cpw.state.co.us/) or contact any CPW or USACE office in Colorado.
Until recently, the Arkansas River drainage was not designated as a Gold Medal Water. The 2012 Regional Condition list of Gold Medal Waters in Attachment 2 was updated on September 5, 2014 to include the Arkansas River following its recent designation as a Gold Medal Water by the State of Colorado, from the confluence with the Lake Fork of the Arkansas, near Leadville, downstream to Parkdale at the Hwy. 50 bridge crossing above the Royal Gorge. The Gold Medal Water designation is contiguous for approximately 102 miles between Leadville and Parkdale.
Discussion: The general purpose of this public notice is to inform prospective permit applicants and other interested parties of specific details concerning the spawning characteristics of rainbow and brown trout in the Arkansas River Gold Medal Water and new seasonal restrictions that may be imposed to protect the fish during spawning. The Corps routinely receives PCNs for Nationwide Permits to conduct work in the above specified section of the Arkansas River; a more detailed understanding of timing for spawning fish will help to avoid or minimize impacts to important spawning areas, help the Corps to inform permit applicants of the changes resulting from the Gold Medal Water designation, and standardize the consultation process between the Corps and CPW.
The Gold Medal Water designation is based on numbers and size of trout per river acre. Spawning periods can vary according to elevation, water temperature and day length and generally last longer at high elevation.
Some basic (approximate) timeframes for critical spawning periods for the majority of the Gold Medal reach include:
Brown Trout – Breed (lay and fertilize eggs) in the fall of the year, usually from mid-October through mid-November. Fertilized eggs are deposited in gravel and develop over the winter, hatching and emerging from the gravel into moving water as small fry in the spring of the following year, starting in April through mid-May.
Rainbow Trout – Breed (lay and fertilize eggs) in the spring of the year, usually starting around mid-March through April. Fertilized eggs are deposited in gravel and develop over late spring into summer, hatching and emerging from the gravel into moving water as small fry in June of the same year.
For both fish species, the Corps and CPW generally agree that the months of October through mid-May are important for successful trout reproduction. In addition, the spring months into early summer are an active period for aquatic insect spawning in the same areas and under similar conditions as the trout species mentioned.
Arkansas River Flows: Flows in the river can fluctuate dependent on time of year from both human and natural events. The Corps and CPW acknowledge that there are conflicts between high flows and construction access in relation to critical important spawning periods. Additional water is generally released into the river channel for human use beginning in mid-November through the end of February, creating higher flows during this period as the water is conveyed to Pueblo Reservoir on the downstream end for storage. Spring run-off from snow melt is a naturally occurring event that increases flow in the river and occurs around mid-May through mid-August.
High flows in most cases are not conducive to project construction activities in the river, but the low flow periods that allow better construction access coincide with the most critical times for important spawning areas. The exception is in the fall, from mid-August when snow melt run-off is usually over and flows are lower in the river, until mid-October when the brown trout breeding period begins. This is also CPWs preferred construction timeframe for sediment disturbance in relation to important spawning areas.
Another factor to consider is optimum flows in the river for fish habitat. Optimum flows for fish habitat occur generally from 250 cubic feet per second (cfs) to 400 cfs, measured at the Wellsville gauge. CPW would consider work proposed in the river if flows were over about 500 cfs on a case-by-case basis, especially if project proponents are asking for implementation times that occur at less than optimal periods in relation to important spawning areas.
Construction timeframes in relation to Important Spawning Areas:
Best – Late August through early October. Construction disturbance in the river bed would have the least amount of impact to spawning, and CPW prefers this time of year for potential impacts and discharge of sediment. The consultation process is expected to be minimal in most cases prior to USACE permit authorization and construction activities in the river. This is typically the lowest flows of the year which makes utilizing heavy equipment in the water much easier.
Possible with Best Management Practices (BMPs) and CPW Consultation – December through mid-March, late May through mid-August. Although not as preferred as the first category, CPW would consider project disturbance of river bed sediment in spawning areas during these periods. Project design must implement BMPs to avoid or greatly minimize discharges of sediment. CPW must approve the project design prior to Corps permit authorization and construction activities in the river.
Prohibited – April through May, October through November. Considered the most critical times of year for spawning activities. Sediment discharges from construction disturbance in the river has a very high probability of physical destruction of an important spawning area, through excavation, fill, or downstream smothering by substantial siltation. The Corps will not authorize construction activities under Nationwide Permits during these periods.
Regardless of project timing, all Nationwide Permit applications reviewed by the USACE within the Gold Medal Water section of the Arkansas River will have the following stipulations:
BMPs must be included in project designs that demonstrate avoidance or significant reduction of discharges of sediment in the river. Certain types of cofferdams seem to work well at reducing sediment discharges, but just about any device or technique that avoids sediment discharge into the river will be considered. Final designs are subject to CPW review and approval prior to Corps permit authorization.
Adequate fish passage will be incorporated into projects that affect the river grade and/or go from bank to bank. Primarily applies to any project that alters the hydrologic connectivity or velocity of the channel, such as drop structures, flow structures for recreational boating, check dams, etc. Project designs requiring fish passage will be subject to CPW review and approval prior to Corps permit authorization.