Dredging, Drill Rig and Flowlines in Plaquemines Parish, Louisiana
NAME OF APPLICANT
Hilcorp Energy Company ℅ Tim Morton & Associates Inc,
Attn: Donna Hollier, 730 E. Kaliste Saloom Road, Lafayette, Louisiana, 70508.
LOCATION OF WORK
Dixon Bay, near Venice, Louisiana, in Plaquemines Parish, as shown on the
enclosed drawings.
Hydrologic Unit Code: 08090100 - Lower Mississippi Region
Beginning Prop Wash Location Latitude: 29.10792 Longitude: 89.304722
Well Location: Latitude: 29.09436, Longitude: -89.30686
CHARACTER OF WORK
: The applicant proposes to prop wash to construct a channel and slip for
the purpose of placing a drilling rig on location to drill the Thin Ice Prospect. Additional applicant will
install and maintain two 4-inch flowlines jetted a minimum of 3 feet below the mudline. As proposed,
approximately 61,079 cubic yards of material would be excavated and stockpiled adjacent to the
access channel, slip. Approximately 1362 cubic yards of material will be jetted for the flowline
installation. Approximately 9 cubic yards of sand bag fill will be placed at existing pipeline crossings.
JOINT PUBLIC NOTICE
September 28, 2015
United States Army
Corps of Engineers
New Orleans District
Regulatory Branch
Post Office Box 60267
New Orleans, Louisiana 70160-0267
State of Louisiana
Department of Environmental Quality
ATTN: Water Quality Certifications
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-2041
Benjamin.C.Sherman@usace.army.mil
Project Manager
Benjamin Sherman
Permit Application Number
MVN 2015-01947 ES
(225) 219-3225
Project Manager
Elizabeth Hill
WQC Application Number
WQC 150924-02
Interested parties are hereby notified that a permit application has been received by the New
Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and
Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean
Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality, Water
Quality Certifications, for a Water Quality Certification (WQC) in accordance with statutory authority
contained in LRS30:2047 A(3), and provisions of Section 401 of the Clean Water Act (P.L.95-17).
Dredging, Drill Rig and Flowlines in Plaquemines Parish, Louisiana
NAME OF APPLICANT: Hilcorp Energy Company Tim Morton & Associates Inc,
Attn: Donna Hollier, 730 E. Kaliste Saloom Road, Lafayette, Louisiana, 70508.
LOCATION OF WORK: Dixon Bay, near Venice, Louisiana, in Plaquemines Parish, as shown on the
enclosed drawings.
Hydrologic Unit Code: 08090100 - Lower Mississippi Region
Beginning Prop Wash Location Latitude: 29.10792 Longitude: 89.304722
Well Location: Latitude: 29.09436, Longitude: -89.30686
CHARACTER OF WORK: The applicant proposes to prop wash approximately 61,079 cubic yards of
material to construct a channel and slip for the purpose of placing a drilling rig on location to drill the
Thin Ice Prospect. Additionally, the applicant will install and maintain two 4-inch flowlines jetted a
minimum of 3 feet below the mudline. Approximately 1,362 cubic yards of material will be jetted for
the flowline installation. Approximately 9 cubic yards of sand bag fill will be placed at existing pipeline
crossings.
The project is proposed in open water; no impacts to jurisdictional wetlands are anticipated with
project implementation, thus, no compensatory mitigation measures are proposed at this time.
-2The comment period for the Department of the Army Permit and the Louisiana Department of
Environmental Quality WQC will close 20 days from the date of this joint public notice. Written
comments, including suggestions for modifications or objections to the proposed work, stating
reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC
request and must be mailed so as to be received before or by the last day of the comment period.
Letters concerning the Corps of Engineers permit application must reference the applicant's name
and the Permit Application Number, and be mailed to the Corps of Engineers at the address above,
ATTENTION: REGULATORY BRANCH. Individuals or parties may request an extension of time
in which to comment on the proposed work by writing or e-mailing the Corps of Engineers
Project Manager listed above. Any request must be specific and substantively supportive of
the requested extension, and received by this office prior to the end of the initial comment
period. The Section Chief will review the request and the requestor will be promptly notified of
the decision to grant or deny the request. If granted, the time extension will be continuous to
the initial comment period and, inclusive of the initial comment period, will not exceed a total
of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of Environmental
Quality and may be examined during weekdays between 8:00 a.m. and 4:30 p.m. Copies may be
obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable impacts,
including cumulative impacts of the proposed activity on the public interest. That decision will reflect
the national concern for both protection and utilization of important resources. The benefit which
reasonably may be expected to accrue from the proposal must be balanced against its reasonably
foreseeable detriments. All factors which may be relevant to the proposal will be considered including
the cumulative effects thereof; among those are conservation, economics, aesthetics, general
environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards,
floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and
conservation, water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local
agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate
the impacts of this proposed activity. Any comments received will be considered by the U.S. Army
Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this
proposal. To make this decision, comments are used to assess impacts on endangered species,
historic properties, water quality, general environmental effects, and other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or an
Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are
also used to determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
The New Orleans District is unaware of properties listed on the National Register of Historic
Places near the proposed work. The possibility exists that the proposed work may damage or
destroy presently unknown archeological, scientific, prehistorical, historical sites, or data. Issuance of
this public notice solicits input from the State Archeologist and State Historic Preservation Officer
regarding potential impacts to cultural resources.
-3The New Orleans District has determined that the project footprint is located in waters known to
be utilized by the West Indian manatee (Trichechus manatus) and determined the activity is "not likely
to adversely affect" this species based on the Standard Local Operating Procedure for Endangered
Species in Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps of
Engineers, New Orleans and U.S. Fish and Wildlife Service, Ecological Services Office. If authorized,
"The Standard Manatee Conditions for In-Water Activities" will be made part of the permit's special
conditions.
Our initial finding is that the proposed work would not affect any species, nor affect any habitat
designated as critical to the survival and recovery of such species, listed as endangered by the U.S.
Department of Commerce.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the
destruction or alteration of 9.8 acres of EFH utilized by various life stages of red drum and penaeid
shrimp. Our initial determination is that the proposed action would not have a substantial adverse
impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative
to project impacts and the need for mitigation measures is subject to review by and coordination with
the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters, the
evaluation of the probable impacts will include the application of guidelines established by the
Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity
will not violate applicable water quality standards will be required from the Department of
Environmental Quality, Water Quality Certifications, before a permit is issued.
Any person may request, in writing, within the comment period specified in this notice, that a
public hearing be held to consider this application. Requests for public hearings shall state, with
particularity, the reasons for holding a public hearing.
The applicant has certified that the proposed activity described in the application complies with
and will be conducted in a manner that is consistent with the Louisiana Coastal Resources Program.
The Department of the Army permit will not be issued unless the applicant received approval or a
waiver of the Coastal Use Permit by the Department of Natural Resources.
You are requested to communicate the information contained in this notice to any other parties
whom you deem likely to have interest in the matter.
Michael V. Farabee
Chief, Eastern Evaluation Section
Enclosure
As-built drawings and/or plats shall have written on them the date of completion of said
activities and shall be submitted to the Louisiana Department of Natural Resources, Office
of Coastal Management, P.O. Box 44487, Baton Rouge, LA 70804-4487 within 30 days
following project completion.
All structures built under the authorization and conditions of this permit shall be removed
from the site within 120 days of abandonment of the facilities for the herein permitted use,
or when these structures fall into a state of disrepair such that they can no longer function
as intended. This condition does not preclude the necessity for revising the current permit
or obtaining a separate Coastal Use Permit, should one be required, for such removal
activities.
Structures must also be marked / lighted in accordance with U.S Coast Guard regulations.
In order to ensure the safety of all parties, the permittee shall contact Louisiana One Call
System (1-800-272-3020) a minimum of 48 hours prior to the commencement of any
excavation (digging, dredging, jetting, etc.) or demolition activity.
NOT TO SCALE
THIS PLAT IS TO BE USED EXCLUSIVELY FOR
THE ACQUISITION OF REGULATORY PERMITS.
T23S-R31E
EX
IST
IN
8.0
'W
G
AT
ER
Hilcorp
236379
6
CH
AN
MI
NE
L
N.
Hilcorp
245869
1
PROPOSED PROP WASH, LOCATION, & F/L'S
SEE PLAN SHEET 2 OF 4
2000'
0'
REPRODUCED FROM USGS DIXON BAY QUADRANGLE
HILCORP ENERGY COMPANY
PROPOSED PROP WASH, LOCATION, & F/L'S
THIN ICE PROSPECT
South Pass Block 24 Field
Plaquemines Parish, Louisiana
HOUSTON, TEXAS 77002
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 330
4000'
SCALE IN FEET
1201 LOUISIANA, SUITE 1400
PREPARED
BY:
2000'
JOB No: 150802
DRW: REP
DATE: Aug. 26, 2015
CKD: HEK
FILE: C150802.DWG
SHEET 1 of 4
REV.
0