You can copy from here when filling out the rest of the page.
APPLICANT: Wayne Miller
PROJECT LOCATION: In the Osage Fork of the Gasconade River on the right descending bank in Section 4, Township 34 north, Range 14 west, Laclede County, Missouri.
ACTIVITY: The applicant proposes to construct a Longitudinal Fill Stone Toe Protection revetment. The revetment would be constructed by placing approximately 1,012 cubic yards of Type II riprap, shot rock, and broken concrete along the eroding stream bank.
APPLICANT: Wayne Miller
PROJECT LOCATION: In the Osage Fork of the Gasconade River on the right descending bank in Section 4, Township 34 north, Range 14 west, Laclede County, Missouri.
ACTIVITY: The applicant proposes to construct a Longitudinal Fill Stone Toe Protection revetment. The revetment would be constructed by placing approximately 1,012 cubic yards of Type II riprap, shot rock, and broken concrete along the eroding stream bank.
PUBLIC NOTICE
Permit No. NWK-2015-1935
Issue Date: November 9, 2015
Expiration Date: November 30, 2015
US Army Corps
of Engineers
Kansas City District
21-Day Notice
______________________________________________________________________________
This public notice is issued jointly with the Missouri Department of Natural Resources, Water
Pollution Control Program. The Department of Natural Resources will use the comments to this
notice in deciding whether to grant Section 401 water quality certification. Commenters are
requested to furnish a copy of their comments to the Missouri Department of Natural Resources,
P.O. Box 176, Jefferson City, Missouri 65102.
APPLICANT: Wayne Miller
29639 Garrett Road
Richland, Missouri 65556
PROJECT LOCATION (As shown on the attached drawings): In the Osage Fork of the
Gasconade River; on the right descending bank; in Section 4, Township 34 north, Range 14
west, Laclede County, Missouri.
USGS Quadrangle Map MO - Drynob
Latitude: 37.70462° North --- Longitude: -92.48001° West
AUTHORITY: Section 404 of the Clean Water Act (33 USC 1344).
ACTIVITY (As shown on the attached drawings) PROPOSED: The applicant proposes to
construct a Longitudinal Fill Stone Toe Protection revetment. The revetment would be
constructed by placing approximately 1,012 cubic yards of Type II riprap, shot rock, and broken
concrete along the eroding stream bank. The length of the proposed revetment is approximately
950 linear feet and 5 feet tall, the width would be 3 feet wide with a flat crown adjacent to the
stream bank, and then taper on a 2:1 slope to the existing stream bed, with a base width of 13
feet. The bank is 12 feet high vertical and the channel is approximately 75 feet wide. The work
would be accomplished utilizing a backhoe or trackhoe to place the bank stabilization material.
The applicant also proposes to remove the existing gravel point bar approximately 315 feet long,
28 feet wide and 2.5 feet high located in the middle of the channel. The gravel bar would be
removed approximately two feet below the water line. The removal and placement method
would be excavation by backhoe or trackhoe. The material would be placed along the eroding
bank to fill voids and provide a base for the bank stabilization revetment and removed off site.
The purpose of this project is to stop lateral stream bank erosion along the right descending
bank of the Osage Fork of the Gasconade River adjacent to an agricultural field. The bank is
approximately 12 feet high vertical and is severely sloughing and eroding. The rate of bank
loss is approximately 8 to 10 feet laterally per year. The bank has eroded to an approximately
90 degree bend at the center of project. Consultation has been made on-site with the Missouri
Department of Conservation (Fisheries Division) and they have provided the example design and
estimates of quantity of rock fill for the construction of a Longitudinal Fill Stone Toe Protection
revetment at this site.
WETLANDS/AQUATIC HABITAT: No wetlands would be impacted by the proposed
activity.
APPLICANT'S STATEMENT OF AVOIDANCE, MINIMIZATION, AND
COMPENSATORY MITIGATION FOR UNAVOIDABLE IMPACTS TO AQUATIC
RESOURCES: Impacts to waters of the United States are being avoided by utilizing the
appropriate type of fill material and the least amount of fill that can be installed in a short period
of time to stabilize the eroding bank (Longitudinal Fill Stone Toe Protection). The purpose of the
project is to stabilize an eroding stream bank. Therefore, this project should benefit the overall
water quality, stream channel stability and stream habitat in this section of the Osage Fork of the
Gasconade River. And thus, compensatory mitigation should not be required.
ADDITIONAL INFORMATION: Additional information about this application may be
obtained by contacting Mr. Mel B. Stanford, Regulatory Project Manager, Truman Regulatory
Satellite Office, 15837 Truman Road, Warsaw, Missouri 65355; Phone: 816-389-3981,
FAX: 660-438-6909, e-mail mel.b.stanford@usace.army.mil. All comments to this public
notice should be directed to the above address.
CULTURAL RESOURCES: Kansas City District will comply with the National Historic
Preservation Act of 1966 and 36 CFR 800. We have checked the National Register of Historic
Places and the Federal Register and no property listed in the Register or proposed for listing is
located in the permit area. This is the extent of our knowledge about historic properties in the
permit area at this time. However, we will evaluate input by the State Historic Preservation
Officer, Tribal Historic Preservation Officers (or Tribe designated representative) and the public
in response to this public notice, and we may conduct or require a reconnaissance survey of the
permit area to check for unknown historic properties, if warranted.
ENDANGERED SPECIES: In compliance with the Endangered Species Act, a preliminary
determination has been made that the described work will not affect species designated as
threatened or endangered or adversely affect critical habitat. In order to complete our evaluation
of this activity, comments are solicited from the U.S. Fish and Wildlife Service and other
interested agencies and individuals.
The U.S. Fish and Wildlife Service Information for Planning and Conservation (IPaC) web site
did not identify any federally listed threatened or endangered aquatic species in the project area.
The search did list the Gray bat (Myotis grisescens), Indiana bat (Myotis sodalis), and Northern
long-eared Bat (Myotis septentrionalis) but no habitat would be impacted by the project.
FLOODPLAINS: This activity is being reviewed in accordance with Executive Order 11988,
Floodplain Management, which discourages direct or indirect support of floodplain development
whenever there is a practicable alternative. By this public notice, comments are requested from
individuals and agencies that believe the described work will adversely impact the floodplain.
WATER QUALITY CERTIFICATION: Section 401 of the Clean Water Act (33 USC 1341)
requires that all discharges of dredged or fill material must be certified by the appropriate state
agency as complying with applicable effluent limitations and water quality standards. This
public notice serves as an application to the state in which the discharge site is located for
certification of the discharge. The discharge must be certified before a Department of the Army
permit can be issued. Certification, if issued, expresses the state's opinion that the discharge will
not violate applicable water quality standards.
PUBLIC INTEREST REVIEW: The decision to issue a permit will be based on an evaluation
of the probable impact including the cumulative impacts of the proposed activity on the public
interest. That decision will reflect the national concern for both protection and utilization of
important resources. The benefits which reasonably may be expected to accrue from the
proposal must be balanced against its reasonably foreseeable detriments. All factors which may
be relevant to the proposal will be considered including the cumulative effects thereof; among
those are conservation, economics, esthetics, general environmental concerns, wetlands, cultural
values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline
erosion and accretion, recreation, water supply and conservation, water quality, energy needs,
safety, food and fiber production, mineral needs and, in general, the needs and welfare of the
people. The evaluation of the impact of the activity on the public interest will include
application of the guidelines promulgated by the Administrator, Environmental Protection
Agency under authority of Section 404(b) of the Clean Water Act (33 USC 1344). The Corps of
Engineers is soliciting comments from the public; Federal, state, and local agencies and officials;
Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this
proposed activity. Any comments received will be considered by the Corps of Engineers to
determine whether to issue, modify, condition or deny a permit for this proposal. To make this
decision, comments are used to assess impacts on endangered species, historic properties, water
quality, general environmental effects, and the other public interest factors listed above.
Comments are used in preparation of an Environmental Assessment and/or an Environmental
Impact Statement pursuant to the National Environmental Policy Act. Comments are also used
to determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
COMMENTS: This notice is provided to outline details of the above-described activity so this
District may consider all pertinent comments prior to determining if issuance of a permit would
be in the public interest. Any interested party is invited to submit to this office written facts or
objections relative to the activity on or before the public notice expiration date. Comments both
favorable and unfavorable will be accepted and made a part of the record and will receive full
consideration in determining whether it would be in the public interest to issue the Department of
the Army permit. Copies of all comments, including names and addresses of commenters, may
be provided to the applicant. Comments should be mailed to the address shown on page 2 of this
public notice.
PUBLIC HEARING: Any person may request, in writing, prior to the expiration date of this
public notice, that a public hearing be held to consider this application. Such requests shall state,
with particularity, the reasons for holding a public hearing.
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 1 OF 7
DATED 9 NOVEMBER 2015
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 2 OF 7
DATED 9 NOVEMBER 2015
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 3 OF 7
DATED 9 NOVEMBER 2015
Gravel Bar (to be removed)
315 feet-long x 28 feet-wide x 2.5 feet-high
Flow
Bank Stabilization Area
950 feet-long
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 4 OF 7
DATED 9 NOVEMBER 2015
The photo shows the upstream portion of project with severely eroding vertical 12 feet-high
bank. The bank has eroded to an approximately 90 degree bend at the center of project on left.
The photo shows the downstream portion of the project with severely eroding 12 feet-high
vertical bank and 90 degree bend at the center of the project.
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 5 OF 7
DATED 9 NOVEMBER 2015
A
950'
12'
3'
5'
13'
Channel Width 75'
B
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 6 OF 7
DATED 9 NOVEMBER 2015
Figure 1. (A) Cross section and plan view of a generic experimental farm rock toe project. (B) Cross section and
plan view of a generic traditional rip rap blanket project.
A
B
Figure 2. Rock being dumped at the toe of the bank. (A) Dump truck used during project construction at Weaubleau
Creek. (B) Backhoe used during project construction at Sulphur Branch.
4
Right Descending Bank
Revetment
12'
13'
APPLICATION NO. NWK-2015-1935
WAYNE MILLER
REVETMENT
OSAGE FORK OF THE GASCONADE RIVER
LACLEDE COUNTY, MISSOURI
SHEET 7 OF 7
DATED 9 NOVEMBER 2015