You can copy from here when filling out the rest of the page.
WEIR STRUCTURE REHABILITATION IN BOUDREAUX CANAL
NAME OF APPLICANT: Terrebonne Levee & Conservation District, c/o T. Baker Smith, LLC, PO Box 2266, Houma, Louisiana 70361.
LOCATION OF WORK: In Boudreaux Canal, Sections 94 and 95, T19S-R18E, just west of Louisiana Highway 56 in Chauvin, Louisiana, in Terrebonne Parish, within the West Central Louisiana Coastal watershed in hydrologic unit (HUC 08090302), as shown on the attached drawings.
CHARACTER OF WORK: The applicant has requested Department of the Army authorization to maintain and rehabilitate the Boudreaux Canal Weir including replacement installation of a navigational dolphin and the deposition rip rap material to maintain the weir and stabilize the bank line. Approximately 2,320 cubic yards of rock rip rap material would be hauled in and deposited to achieve required elevation requirements to ensure proper function of the weir. Additionally, a 120’ steel pile dolphin with warning markers will be installed to mark the southwest side of the weir and provide a navigation aid to mariners.
The proposed project is situated within approximately 0.53 acres in the Boudreaux Canal in open water and along 340 linear feet of the adjacent bank line. A Preliminary analysis has determined that the proposed project would directly impact 0.02 acres of emergent wetlands.
JOINT PUBLIC NOTICE
January 18, 2016
United States Army Corps of Engineers
New Orleans District
Regulatory Branch
Post Office Box 60267
New Orleans, Louisiana 70160-0267
State of Louisiana
Department of Environmental Quality
Office of Environmental Services
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-1545
Project Manager
S. Gail Gainey
Sandra.G.Gainey@usace.army.mil
MVN 2015-02448-CG
(225) 219-3225
Project Manager
Elizabeth Hill
WQC Application Number
WQC #160108-01
Interested parties are hereby notified that a permit application has been received by the
New Orleans District of the US Army Corps of Engineers pursuant to: [X] Section 10 of the
Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section
404 of the Clean Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality,
Office of Environmental Services, for a Water Quality Certification (WQC) in accordance
with statutory authority contained in LRS 30:2074 A(3) and provisions of Section 401 of the
Clean Water Act.
WEIR STRUCTURE REHABILITATION IN BOUDREAUX CANAL
NAME OF APPLICANT: Terrebonne Levee & Conservation District, c/o T. Baker Smith,
LLC, PO Box 2266, Houma, Louisiana 70361.
LOCATION OF WORK: In Boudreaux Canal, Sections 94 and 95, T19S-R18E, just west
of Louisiana Highway 56 in Chauvin, Louisiana, in Terrebonne Parish, within the West
Central Louisiana Coastal watershed in hydrologic unit (HUC 08090302), as shown on the
attached drawings.
CHARACTER OF WORK: The applicant has requested Department of the Army
authorization to maintain and rehabilitate the Boudreaux Canal Weir including replacement
installation of a navigational dolphin and the deposition rip rap material to maintain the weir
and stabilize the bank line. Approximately 2,320 cubic yards of rock rip rap material would
be hauled in and deposited to achieve required elevation requirements to ensure proper
function of the weir. Additionally, a 120' steel pile dolphin with warning markers will be
installed to mark the southwest side of the weir and provide a navigation aid to mariners.
The proposed project is situated within approximately 0.53 acres in the Boudreaux Canal
in open water and along 340 linear feet of the adjacent bank line. A Preliminary analysis
has determined that the proposed project would directly impact 0.02 acres of emergent
wetlands.
2
The applicant has designed the project to avoid and minimize direct and secondary
adverse impacts to the maximum extent practicable. Any further reduction in the proposed
fill would not meet the standards to ensure proper function of the weir structure or to
stabilize the bank line. The applicant proposes to avoid any direct impacts and minimize
secondary impacts to wetlands by utilizing marine equipment and waterways to access the
project site. As compensation for unavoidable wetland impacts, the applicant proposes to
develop a mitigation plan pursuant to agency guidelines if necessary.
The comment period for the Department of Army will close in 20 days from the date
of this joint public notice. Written comments, including suggestions for modifications or
objections to the proposed work, stating reasons thereof, are being solicited from anyone
having interest in this permit and/or this WQC request and must be mailed so as to be
received before or by the last day of the comment period. Letters concerning the Corps of
Engineers permit application must reference the applicant's name and the Permit
Application Number, and be mailed to the Corps of Engineers at the address above,
ATTENTION: REGULATORY BRANCH. Similar letters concerning the Water Quality
Certification must reference the applicant's name and the WQC application number and be
mailed to the Louisiana Department of Environmental Quality at the address above.
Individuals or parties may request an extension of time in which to comment on the
proposed work by writing or e-mailing the Corps of Engineers Project Manager listed
above. Any request must be specific and substantively supportive of the requested
extension, and received by this office prior to the end of the initial comment period. The
Section Chief will review the request and the requestor will be promptly notified of the
decision to grant or deny the request. If granted, the time extension will be continuous to
the initial comment period and, inclusive of the initial comment period, will not exceed a
total of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of
Environmental Quality and may be examined during weekdays between 8:00 a.m. and
4:30 p.m. Copies may be obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable
impacts, including cumulative impacts of the proposed activity on the public interest. That
decision will reflect the national concern for both protection and utilization of important
resources. The benefit which reasonably may be expected to accrue from the proposal
must be balanced against its reasonably foreseeable detriments. All factors which may be
relevant to the proposal will be considered including the cumulative effects thereof; among
those are conservation, economics, aesthetics, general environmental concerns, wetlands,
historic properties, fish and wildlife values, flood hazards, floodplain values, land use,
navigation, shoreline erosion and accretion, recreation, water supply and conservation,
water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the people.
The US Army Corps of Engineers is soliciting comments from the public, federal, state,
and local agencies and officials, Indian Tribes, and other interested parties in order to
consider and evaluate the impacts of this proposed activity. Any comments received will
3
be considered by the US Army Corps of Engineers to determine whether to make, modify,
condition, or deny a permit for this proposal. To make this decision, comments are used to
assess impacts on endangered species, historic properties, water quality, general
environmental effects, and other public interest factors listed above. Comments are used
in the preparation of an Environmental Assessment and/or an Environmental Impact
Statement pursuant to the National Environmental Policy Act. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
The New Orleans District is unaware of properties listed on the National Register of
Historic Places near the proposed work. The possibility exists that the proposed work may
damage or destroy presently unknown archeological, scientific, prehistorical, historical
sites, or data. Copies of this notice are being sent to the State Archeologist and the State
Historic Preservation Officer.
Our initial finding is that the proposed work would neither affect any species listed as
endangered by the U.S. Departments of Interior or Commerce, nor affect any habitat
designated as critical to the survival and recovery of any endangered species. The New
Orleans District has determined that the proposed project is located in waters known to be
utilized by the West Indian Manatee (Trichechus manatus) and the Pallid Sturgeon
(Scaphirhynchus albus). Utilizing Standard Local Operating Procedure for Endangered
Species in Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps of
Engineers, New Orleans and U.S. Fish and Wildlife Service, Ecological Services Office,
the Corps has determined that with the inclusion of the Standard Manatee Conditions for
In-Water Activities, proposed work is not likely to adversely affect the West Indian
Manatee. Because the proposed work involves the maintenance of a riverine pathway
obstruction structure, the U.S. Fish and Wildlife Service, Ecological Services Office has
been contacted directly for further consultation.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the
Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal
would result in the destruction or alteration of up to 0 acres of EFH utilized by various life
stages of red drum and penaeid shrimp. Our initial determination is that the proposed
action would not have a substantial adverse impact on EFH or federally managed fisheries
in the Gulf of Mexico. Our final determination relative to project impacts and the need for
mitigation measures is subject to review by and coordination with the National Marine
Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters,
the evaluation of the probable impacts will include the application of guidelines established
by the Administrator of the Environmental Protection Agency. Also, a certification that the
proposed activity will not violate water quality standards will be required from the
Department of Environmental Quality, Office of Environmental Services before a permit is
issued.
Any person may request, in writing, within the comment period specified in this notice,
that a public hearing be held to consider this application. Requests for public hearings
shall state, with particularity, the reasons for holding a public hearing. You are requested
to communicate the information contained in this notice to any other parties whom you
4
deem likely to have interest in the matter.
The applicant has certified that the proposed activity described in the application
complies with and will be conducted in a manner that is consistent with the Louisiana
Coastal Resources Program (Coastal Zone Applications P20151081, P20151083). The
Department of the Army permit will not be issued unless the applicant received approval or
a waiver of the Coastal Use Permit by the Department of Natural Resources.
JOHN M. HERMAN
Chief, Central Evaluation Section
Regulatory Branch
Enclosures